Factual and Procedural Background
An agreement containing an arbitration clause (Clause 25) was entered into between the parties, whereby the respondent was to execute certain work. The clause stipulated that disputes were to be referred to a sole arbitrator appointed by the Engineer Member of the Delhi Development Authority (DDA). The respondent invoked the arbitration clause due to arising disputes, and an arbitrator was appointed. During the arbitration proceedings, the respondent sought to add more disputes to the arbitration reference, but the Engineer Member did not respond. After the arbitrator issued an award on the initially referred disputes, the respondent requested again to refer additional disputes to arbitration. Upon no response, the respondent filed an application under section 20 of the Arbitration Act, 1940, seeking direction for the Engineer Member to appoint an arbitrator and refer the additional disputes. The appellants opposed the application, contending the court lacked jurisdiction and that principles analogous to Order II Rule 2 of the Code of Civil Procedure (CPC) barred the respondent from raising additional disputes after initial reference. The learned single Judge allowed the application, directing the Engineer Member to appoint an arbitrator and refer the additional disputes. The appellants appealed against this decision.
Legal Issues Presented
- Whether the Engineer Member of the appellant No. 1 can be directed by the court to appoint an arbitrator and refer the disputes between the parties.
- Whether the provisions of Order II Rule 2 of the Code of Civil Procedure are applicable to arbitration proceedings.
Arguments of the Parties
Appellants' Arguments
- The appointment of an arbitrator under the agreement is to be made by the Engineer Member, and therefore, an application under section 20 of the Arbitration Act is not maintainable as the court lacks jurisdiction to direct such appointment.
- Since disputes had already been referred to an arbitrator, principles analogous to Order II Rule 2 of the CPC should apply, preventing the respondent from raising disputes that could have been raised earlier.
Respondent's Arguments
- The court has jurisdiction under section 20(4) of the Arbitration Act to direct the Engineer Member to appoint an arbitrator in accordance with the arbitration clause.
- The provisions of Order II Rule 2 of the CPC and analogous principles are not applicable to arbitration proceedings, allowing the respondent to seek reference of additional disputes during the pendency of arbitration.
Table of Precedents Cited
| Precedent |
Rule or Principle Cited For |
Application by the Court |
| Shri V. P. Mittal v. Union of India and others (Suit No. 625-A of 1982, decided 28th May 1984) |
Jurisdiction of the court to direct the competent authority to appoint an arbitrator under an arbitration clause similar to Clause 25. |
The Court relied on this Full Bench decision to hold that the court has jurisdiction to direct the Engineer Member to appoint an arbitrator as per the arbitration agreement. |
| Jiwanani Engineering Works Pvt. Ltd. v. Union of India, AIR 1978 Calcutta 228 |
Applicability of principles analogous to Order II Rule 2 of the CPC in arbitration proceedings. |
The Court acknowledged the principle that disputes once settled should not be reopened and that multiplicity of proceedings must be avoided, agreeing with the principle but distinguishing its application before and after the making of an award. |
Court's Reasoning and Analysis
The Court first affirmed the jurisdiction of the court under section 20(4) of the Arbitration Act to direct the Engineer Member to appoint an arbitrator in accordance with the arbitration clause, relying on the Full Bench decision in Shri V. P. Mittal. The Court disagreed with the learned single Judge’s conclusion that the principles analogous to Order II Rule 2 of the CPC are never applicable to arbitration proceedings. It recognized that while the Code of Civil Procedure does not directly apply to arbitration, analogous principles do apply to prevent multiplicity of proceedings and to uphold finality once disputes are settled by award or competent court.
The Court distinguished between the situation before and after the making of an award. Before an award, the claimant can request to add more disputes, akin to the power of a civil court to allow amendment of pleadings under Order 6 Rule 17 of the CPC. The Court held that the principles analogous to Order 6 Rule 17 should be invoked during the pendency of arbitration to allow additional disputes to be referred, provided the arbitration proceedings have not concluded.
Conversely, after an award is made, the principles analogous to Order II Rule 2 apply, barring the claimant from raising disputes that could or should have been raised earlier. The Court reasoned that the arbitrator’s jurisdiction depends on the terms of reference and that if additional disputes were omitted by oversight but arbitration is ongoing, the claimant can ask the Engineer Member to refer these to arbitration. If the Engineer Member fails to do so, the court can direct the reference under section 20 of the Act.
Thus, the Court held that both principles analogous to Order II Rule 2 and Order 6 Rule 17 of the CPC have their place in arbitration proceedings, depending on the stage of arbitration. The Court found the learned single Judge’s view that Order II Rule 2 would never apply to arbitration to be incorrect.
Holding and Implications
The appeal is dismissed.
The Court directed the Engineer Member to appoint an arbitrator within two months and to refer the additional disputes specified in the respondent’s letter dated 3rd October 1979 to the arbitrator. Interim orders were vacated, and the parties were left to bear their own costs due to the peculiar circumstances of the case.
The decision clarifies that courts have jurisdiction under section 20 of the Arbitration Act to direct appointment of arbitrators as per the arbitration agreement, and that principles analogous to Order II Rule 2 and Order 6 Rule 17 of the CPC apply to arbitration proceedings at appropriate stages. This ensures a balance between finality of arbitration awards and fairness in allowing additional disputes to be raised during ongoing arbitration, preventing multiplicity of proceedings without unduly restricting legitimate claims.