The petitioner is the owner of Survey Nos.248 and 243 of Nanniyur Village,
Karur Taluk and he is cultivating the said land. He has filed the present Writ
Petition seeking to challenge the order passed by the first respondent, the
District Collector, dated 30.04.2007. By the afore-said order impugned in the
Writ Petition, the first respondent, the District Collector passed an order
purporting to exercise power under Section 17(3) of the Indian Telegraph
Act,1885 (for short "the Act"). For the sake of convenience, Section 17 of the
said Act is extracted below:-
17.Removal or alteration of telegraph line or post, on property other
than that of a local authority. (1) When, under the foregoing provisions of this
Act, a telegraph line or post has been placed by the telegraph authority under,
over, along, across, in or upon any property, not being property vested in or
under the control or management of a local authority, and any person entitled to
do so desires to deal with that property in such a manner as to render it
necessary or convenient that the telegraph line or post should be removed to
another part thereof or to a higher or lower level or altered in form, he may
require the telegraph authority to remove or alter the line of post accordingly;
Provided that, if compensation has been paid under Section 10, clause (d) he
shall, when making the requisition, tender to the telegraph authority the amount
requisite to defray the expense of the removal or alteration, or half of the
amount paid as compensation, whichever may be the smaller sum.
(2) If the telegraph authority omits to comply with the requisition, the person
making it may apply to the District Magistrate within whose jurisdiction the
property is situate to order the removal or alteration.
(3)A District Magistrate receiving an application under sub-section (2) may, in
his discretion, reject the same or make an order, absolutely or subject to
conditions, for the removal of the telegraph line or post to any other part of
the property or to a higher or lower level or for the alteration of its form;
and the order so made shall be final.
2.Before the District Collector undertook to exercise the power, the third
respondent herein filed a Writ Petition before this Court being W.P.No.6850 of
2006 seeking to set aside the order dated 10.04.2006, passed by the Power Grid
Corporation of India and to consider his representation dated 05.05.2006
requesting for slight diversion of the HT Power line so as to avoid the poultry
sheds of the petitioner.
3.This Court, by an order dated 31.01.2007 disposed of the said Writ
Petition along with another Writ Petition. The operative portion of the said
order as found in Paragraphs:4 and 5 reads as follows:-
"4.Relying on the above said order, the learned Senior Counsel for the
petitioner in W.P.No.6850 of 2006 prays this Court to direct the District
Magistrate to take note of the directions issued in Para No.27 of the said order
dated 18.01.2007, while considering the objections of the respondents as well as
the petitioner, and pass orders in accordance with law.
5.Considering the said submission of the counsel for both sides, the
petitioners are at liberty to submit their objections, if any
to the District Magistrate concerned within a period of two weeks from today.
On receipt of such objections, the District Magistrate is directed to consider
the same in the light of the order passed by this Court, which is mentioned
supra and pass orders on merits and in accordance with law after affording an
opportunity to the petitioners as well as the respondents within a period of six
weeks thereafter."
4.After the direction issued by this Court, the first respondent, the
District Collector called for remarks from the Power Grid Corporation, the
second respondent herein and other objections. The prime objection made by the
third respondent was that if the power line proceeds in Survey Nos.242/02 and
249/1 to 249/11, it will affect the production capacity of the poultry.
According to the third respondent, not only there will be a performance being
eroded, the health of the birds will also get affected in the long run.
Therefore, the alignment of the high tension power line should be slightly
modified.
5.This request of the third respondent was objected to by the second
respondent Corporation stating that the affecting of the yield of eggs in the
poultry is not a proven fact. However, the first respondent, the District
Collector was fortified in coming to the conclusion by the letter written by the
Assistant Director of the Department of Animal Husbandry dated 08.02.2006,
wherein he had stated that passing of high voltage electric current over the
poultry shed will affect the production performance and health of birds in the
long run.
6.Along with the covering letter he had enclosed expert's opinion given by
two experts in the field. The conclusions in the said opinion reads as
follows:-
A great deal of uncertainty surroundings the findings on the effects of EMF
exposure on birds. Most of the uncertainty exists because there has been a
limited number of studies involving birds. Despite the limited numbers, much of
the research has found that EMF has generally affected birds, and most of the
effects have been adverse. EMF exposure, either in the field or at
environmentally relevant levels in laboratories has altered the behaviour,
physiology, endocrine system and the immune function of birds, which generally
resulted in negative repercussions on their reproduction or development. The
suppression and seasonal phase shift of melatonin in birds suggests that they
may perceive EMFs as light, as do some mammals. This may result in early
maturity which is not desirable in birds.
7.Therefore, the District Collector, in exercise of power under Section
7(3) of the Act directed the second respondent Corporation to realign the
transmission power lines in such a way that the power lines do not pass above
the poultry shed in Surveys Nos.242/2 and 249/3 in Nanniyur Village belonging to
the third respondent. Aggrieved by the said order, the petitioner being the
neighbouring land owner has preferred this present Writ Petition.
8.Pending the Writ Petition, he had also obtained an interim stay in
M.P.No.2 of 2007 dated 10.12.2007. The third respondent had taken out a vacate
stay application in M.P.1 of 2008. In the mean while, the first and second
respondents have filed their counter affidavits. While the first respondent has
supported his order as not being violative of the provisions of Electricity Act
or the provisions of the Indian Telegraph Act,1885 which has granted him power
to pass appropriate orders. The second respondent in their counter affidavit had
stated that the realignment will result in extra expenditure for the
Corporation, which will be passed on to the general public. It must be stated
that the second respondent Corporation was also a party to the Writ Petition
W.P.No.6850 of 2006 and in the order dated 31.01.2007, they have not raised any
such plea, which are now sought to be projected regarding the jurisdiction of
the District Collector.
9.Having allowed this Court to direct the District Collector to pass an
order, it is not now open to him to come forward to state that the power under
Section 17 of the Act is not available to the District Collector and the order
was erroneous. In any event, Mr.K.Govindarajan, learned counsel for the
petitioner made the following submissions:-
" (a) The impugned order of the District Collector is erroneous and he
does not have jurisdiction under Section 17 of the Telegraph Act.
(b) By order realignment the towers, the second respondent Corporation
is put to additional expenditure.
(c) The third respondent had come into the said area and establish the
poultry farm only after the scheme was evolved and approved by the second
respondent Corporation. Having known in advance, the peril of locating their
farm, they cannot raise their objections afterwards.
10.It must be stated that under Section 17 of the Act cannot be read in
isolation. For the purpose of erecting the power grid and electric lines, the
power under the Telegraph Act has been borrowed. The argument that the stage of
exercising of power under Section 17 had not arrived, cannot be accepted. In
the impugned order in Paragraph No. 5, the District Collector has recorded the
following finding:-
With reference to the execution of the laying down fixing of the power
line towers it is stated that out of the 75 towers to be erected in Karur Taluk
about 36 towers had already been erected from substation K.Paramathy Village to
Manmangalam village and remaining 39 towers, with reference to erection of 22
towers upto location No.146/1 there was no problem. The problem is only with
reference to tower No.146/0 to 142/1 involving erection of 17 towers.
11.Therefore, it is not as if the towers have not come into existence. It
is at this stage the third respondent has raised objection and this Court has
directed the first respondent to consider the objections raised by the third
respondent. Learned counsel for the petitioner brought to the notice of this
Court an un-reported judgment of the Division Bench in W.A.No.464 of 2008
between R.Kannan, rep.by his power agent Vs. Power Grid Corporation(India)
Limited and others dated 10.04.2008 to support his proposition that under
Section 16, the only question which the District Magistrate is empowered to
decide is whether to permit the authorities to exercise power under Section 10
of the Act and that the said jurisdiction cannot be expanded to empower the
District Magistrate to suggest alternative routes.
12.He laid emphasis on para 9 of the said judgment, which is extracted
below:-
9.On behalf of the Corporation, the original plans were produced before us and
on examination of the materials placed on record, we are satisfied that the
route selected by the Corporation is the best possible route and in any event,
in our opinion, it is not permissible to the District Magistrate to accept such
opinion of the technical expert and to suggest another route for the purpose of
laying down the transmission lines. It is required to be noted that the route
selected by the Corporation is the shortest route cutting through the Reserve
Forest area, which is also in consonance with the directions of the Supreme
Court and is awaiting orders for cutting the required number of trees in the
Sudelur Forest Area, where three towers would be erected. Moreover, under
Section 16(1) of the Indian Telegraph Act, the only question which the District
Magistrate is empowered to decide is whether to permit the authority to exercise
the power under Section 10 of the Act and the jurisdiction cannot be expanded to
empower the District Magistrate to suggest alternative routes for the purpose of
laying down the transmission lines on the basis of the so-called report, when it
is on record that the Corporation has chosen the most techno-economically
feasible route.
13.In the present case, the power of the District Collector was not
exercised in terms of Section 16 of the Act, but in terms of Section 17 of the
Act. He was also directed by this Court to consider the objections raised by
the third respondent before the towers could be erected. Therefore, it cannot
be said that the first respondent did not have any jurisdiction to decide the
matter.
14.With reference to the loss to the Power Grid Corporation that the
petitioner need not worry about the same. In the absence of the second
respondent instituting any independent proceedings to challenge such order
passed by the District Collector, the petitioner's objections must fail. In any
event, the erection of tower and laying the power lines will certainly cost the
Corporation. But when there is a direction issued by the appropriate statutory
authorities, the Corporation cannot be allowed to cling on to the original
scheme. They will have to necessarily give effect to the statutory order passed
by the authorities under the Act. Therefore, the question of loss to be
incurred by the Corporation cannot be a ground in determining the re-alignment
of the power lines especially when there is an expert report in this regard and
the same having been produced before the District Magistrate.
15.This leaves us with the question raised as the third submission. By the
realignment, the petitioner will be put to loss. Ultimately, the case of the
petitioner revolves around his loss that may likely be caused by the erection of
towers. The Electricity Act clearly supports compensating the land owner for
any loss. It provides procedure and for claiming compensation under the
Electricity Act,2003. Therefore, ultimately, it is for the authorities to
determine as to what would be the greater loss and whether the objector has any
factual or legal basis to raise objection regarding the setting up of the power
transmission lines.
16.In the present case, the District Magistrate has taken into account all
relevant circumstances and also armed with the report of the expert's opinion
decided to direct the second respondent Corporation to realign the line. No
exception can be taken for the said exercise of power by the first respondent.
This Court considers that the first respondent's order does not suffer from any
legal infirmity or arbitrariness on his part.
Under the above circumstances, this Writ Petition will stand dismissed.
There will be no order as to costs. The connected M.Ps are closed.
To
1.The District Collector,
Karur District, Karur.
2.The Power Grid Corporation of India Limited,
Thermal Station, Neyveli.