  • section 21 and 85 of the Arbitration and Conciliation Act, 1996 (for short, the Act)
  • provisions of Clause 7-A read with Condition No. 22 and Clause 37 of GCC.
  • Clause 64 of General Conditions of Contract (for short, G.C.C).
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2011 BHC 688
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • section 21 and 85 of the Arbitration and Conciliation Act, 1996 (for short, the Act)
  • provisions of Clause 7-A read with Condition No. 22 and Clause 37 of GCC.
  • Clause 64 of General Conditions of Contract (for short, G.C.C).
Smart Summary

Structured Summary of the Opinion

Factual and Procedural Background

This petition challenges an Arbitral Award dated 16 December 2005 in a dispute arising from a Contract Agreement for Works dated 17 December 1999, relating to rail contract work.

Key factual and procedural points stated in the opinion:

  • On 21 September 1999, the respondents were awarded a contract for cutting, cropping and Almino Termite welding of rails (Kurudwad - Pandharpur gauge conversion) at a tendered cost of Rs. 1,21,07,000/-. The prescribed completion period was five months from award (i.e., on or before 21 February 2000).
  • The respondents completed the work on 31 January 2001 after obtaining five extensions; joint measurements were recorded in presence of the contractor.
  • Disputes/claims were raised by the respondents on 20 August 2001 and 21 February 2003. Pursuant to an order of this Court dated 21 February 2003, an Arbitral Tribunal was constituted; the Tribunal was formally constituted on 14 August 2003.
  • The Arbitral Tribunal, by its award dated 16 December 2005, rejected the petitioners' counter-claim and allowed nine out of the thirteen claims of the respondents (original claimants).
  • The petitioners challenged that award before this Court, leading to the opinion summarized here. The petition was partly allowed and the award was modified in certain respects by the Court.

Legal Issues Presented

  1. Whether the petitioners' counter-claim for Rs. 1,61,50,000/- should be rejected for delay, late presentation and lack of supporting evidence.
  2. Whether the Arbitral Tribunal correctly awarded the various claims made by the respondents (specifically Claim Nos. 1, 2, 3, 4, 5, 8, 9, 11).
  3. Whether extensions of time granted on the respondents' undertaking of "no claim/compensation" bar claims arising from delay, under the contract's General Conditions of Contract (GCC).
  4. Whether extra items executed at site (and their rates) were properly awarded by the Tribunal, including application of relevant schedule of rates.
  5. Whether the Arbitral Tribunal erred in awarding price variation/variation in cost of labour and material contrary to the contract terms.
  6. Whether the Court may modify parts of an arbitral award and to what extent such modification is permissible.

Arguments of the Parties

Petitioners' Arguments

  • The petitioners contended that several of the respondents' claims were "excepted matters" under specific contract provisions and hence not maintainable.
  • The petitioners challenged the respondents' counter-claim (for Rs. 1,61,50,000/-) on grounds of delay in presentation, absence of evidence/supporting material, and that it was raised for the first time in a letter dated 14 August 2003 despite arbitration proceedings commencing earlier.
  • The petitioners relied on the fact that extensions of time had been granted with clear terms of no claim or compensation, and that a token penalty (Rs. 5,000 per month) was applied for the abnormal delay.
  • The petitioners argued that certain claims (such as underutilization of overheads and sorting of old rails) were covered by all-inclusive rates and contractual clauses making them excepted matters.

Respondents' Arguments

  • The respondents maintained that they carried out the extra items at site which were necessary to complete the contracted items and thus were entitled to payment for those items.
  • The respondents had applied for time extensions under clause 17 of the GCC, providing reasons for delay, and continued to press claims arising from extra items and other works done.
  • The respondents relied on joint measurements and site records in support of claims for work done and for extra-item payments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
General Manager, Northern Railways v. Sarvesh Chopra, (2002) 4 SCC 45 : AIR 2002 SC 1272 Support for the proposition that rates quoted by tenderers are all-inclusive and certain claims (e.g., underutilization of overheads) fall within clauses making them part of the inclusive rate/excepted matters. The Court relied on this authority in concluding that the claim for underutilization of overheads (Claim No. 5) fell within the all-inclusive rate provisions and was liable to be set aside.
Ramnath International Construction (P) Ltd. v. Union of India, (2007) 2 SCC 453 : AIR 2007 SC 509 Principle that an Arbitral Tribunal cannot go beyond the agreed contractual terms (here applied to price variation/variation in cost claims). The Court applied this principle to set aside the award of payment for variation in cost of labour and material (Claim No. 9), on the basis that the contract and the respondents' undertaking barred such claims.
R.S. Jiwani (M/s.), Mumbai v. Ircon International Ltd., Mumbai, 2010 (1) Mh.L.J 547 Authority cited for the proposition that a court may modify an arbitral award and retain or set aside certain claims. The Court relied on this authority in exercising its power to modify parts of the Arbitral Award (modifying amounts and setting aside certain claim awards) while maintaining the rest.

Court's Reasoning and Analysis

The Court reviewed the record claim-by-claim and applied the contractual provisions (notably clauses of the General Conditions of Contract (GCC)) together with the procedural history of the arbitration. The Court's analysis proceeded as follows:

  1. Counter-claim: The petitioners' counter-claim for Rs. 1,61,50,000/- was rejected by the Arbitral Tribunal on account of delay in execution and for being first pleaded late (first made in letter dated 14-8-2003). The Court noted that the counter-claim was not specifically raised at the commencement of arbitration (on the date of appointment of Arbitrator, 20-8-2001), lacked supporting evidence, and the petitioners did not lead evidence before the Tribunal. The petitioners' counsel conceded this position. The Court accepted the Tribunal's rejection of the counter-claim on these grounds.
  2. Claim No. 1 (work done but not paid): The Court examined joint measurements and clause 45 of GCC, and considered the scope of "excepted matters" under clause 63. The Court concluded that the total balance amount payable on the basis of joint measurements and contract terms was Rs. 3,00,919/-, and not Rs. 8,45,267/- as awarded by the Tribunal; accordingly, it reduced the award on this head to Rs. 3,00,919/-.
  3. Claim No. 2 (extra items): The Court found no dispute that the extra items were actually carried out at site and were necessary for completing contracted items. The Tribunal had discussed quantities and rates, and had used the Central Railway-1990 schedule of rates (item 18202) applying a multiplier (four times the rate) and fixed a rate for shifting rails at Rs. 220.44 per tonne. The Court considered the Tribunal's detailed assessment reasonable and not interfered with; it upheld the Tribunal's award on these counts, resulting in a total amount of Rs. 8,84,256/- for the extra items and related claims.
  4. Claim No. 3 (refund of security deposit): The Court directed refund of the security deposit of Rs. 3,00,000/- to the respondents after completion under GCC provisions, but clarified that it should be paid without interest.
  5. Claim No. 4 (sorting of old rails): The Court held that, under clause 7-A of special condition No. 5 and clause 37 of GCC, rates quoted by tenderers are inclusive and the work for which payment was awarded already existed in the basic rate; thus this claim fell under "excepted matters" per clause 63 and the amount awarded was set aside.
  6. Claim No. 5 (underutilization of overheads): The Court found this claim fell within clauses (Clause 7-A read with Condition No. 22 and Clause 37 of GCC) implying rates were all-inclusive till successful completion, coupled with the respondents' undertaking of no claim on extensions. The Court therefore set aside the award on this claim. The Court cited General Manager, Northern Railways v. Sarvesh Chopra in support of the position.
  7. Claim No. 8 (wrongful deduction): The petitioner's counsel did not press this issue before the Court, and because the extension was granted by consent and delays were attributable to both parties, the Court left this claim as maintained by the Tribunal.
  8. Claim No. 9 (variation in cost of labour and material / price escalation): The award for price variation was set aside. The Court reasoned that the award was granted without necessary certificate for variation and in any event a specific contractual clause barred the contractor from claiming price escalation. Because time extensions were granted on the respondent's undertaking of no-claim/compensation, grant of price variation was contrary to the contract and liable to be set aside. The Court invoked Ramnath International Construction v. Union of India for the proposition that an Arbitral Tribunal cannot go beyond agreed contractual terms.
  9. Claim No. 11 (withheld amount for non-submission of certificates): The Court noted that the withheld amount was due to non-submission of certificates which were later furnished; this issue was not seriously contested and the award on Claim No. 11 was left undisturbed.
  10. Interest: Both counsel conceded that clause 16(3) of the GCC precluded the contractor (respondent) from claiming interest on awarded amounts; the Court therefore agreed with the Arbitral Tribunal's refusal to grant interest.
  11. Modification Power: Relying on the authority of R.S. Jiwani v. Ircon International Ltd., the Court accepted that the award could be modified and proceeded to modify the award in the specific respects stated above while maintaining the rest of the award.

Holding and Implications

Holding:

Petition partly allowed.

Direct consequences and implications on the parties (as explicitly recorded in the opinion):

  • The Arbitral Tribunal's rejection of the petitioners' counter-claim is sustained.
  • Claim No. 1: The Court reduced the award and held the respondents entitled only to Rs. 3,00,919/- (and not Rs. 8,45,267/- as awarded by the Tribunal).
  • Claim No. 2 (extra items): The Tribunal's award on extra items and related payments (total Rs. 8,84,256/- on the counts considered) was upheld and left undisturbed.
  • Claim No. 3: The security deposit of Rs. 3,00,000/- is to be refunded to the respondents without any interest.
  • Claim No. 4: The award for sorting of old rails was set aside as it falls within excepted matters and is covered by the all-inclusive rates.
  • Claim No. 5: The award for underutilization of overheads was set aside for being covered by all-inclusive rates and the respondents' undertaking of no-claim on extensions.
  • Claim No. 8: Maintained as awarded by the Arbitral Tribunal (not pressed by the petitioner).
  • Claim No. 9: Award for variation in cost of labour and material (price escalation) was set aside as contrary to the contract terms and absent requisite certification.
  • Claim No. 11: The award remains undisturbed.
  • Interest: No interest is payable on awarded amounts by virtue of clause 16(3) of the GCC; the Tribunal was correct in refusing interest.
  • The Court modified the arbitral award in the specified respects and maintained the remainder of the award. No order as to costs was made.

Broader legal impact: The opinion applies existing contractual and arbitral principles to the facts and relies upon cited case law to support the limited modifications of the award. The opinion does not purport to lay down a novel precedent beyond the application of the cited authorities and contractual interpretation to the facts of this case.

Final disposition recorded in the opinion: Petition partly allowed. No order as to costs.

To access the original judgment, please Sign In or Subscribe.

    Union Of India v. Sagar Thermit Corporation Ltd. .

    1. Heard finally.

    2. The petitioners have challenged an Award dated 16 December, 2005 passed by the Arbitrator appointed in a dispute arising out of a Contract Agreement for Works dated 17 December, 1999, between the parties with regard to a rail contract work.

    3. The basic facts are:

    On 21-9-1999, the respondents were awarded with a contract of work of Cutting and Cropping of Rails and Almino Termite welding of Rails by SKV process between Kurduwad - Pandharpur Guage - Conversion Project at a tendered cost of Rs. 1,21,07,000/- with a condition of completion period of 5 months from the date of acceptance/award of the contract i.e 21-9-1999 and accordingly the work was to be completed on or before 21-2-2000.

    4. On 31-1-2001 the work was completed by the respondents after obtaining 5 extensions. The joint measurements were done in the presence of the contractor.

    5. On 20-8-2001 and 21-2-2003, the respondents however had raised disputes/claims and pursuant to the Order of this Court dated 21-2-2003, the Arbitral Tribunal was constituted. The respondents submitted various claims, thereafter also.

    6. The petitioners had refuted the claims of the respondents as the same were “Excepted matters” in view of the specific provisions of the Contract.

    7. On 16-12-2005 the Arbitral Tribunal by rejecting the counter-claim of the petitioners, awarded nine out of thirteen claims, in favour of the respondents (original claimants).

    8. The respondents Original Claimants, called upon the petitioners/respondents to compensate financial loss vide letter dated 20th August, 2001, and called upon to appoint an Arbitrator under Clause 64 of General Conditions of Contract (for short, “G.C.C”). The respondents, did not response, ultimately filed an Application No. 246 of 2002 in the High Court at Bombay for referring all the claims raised in letter dated 1st August, 2001 and contested a counter-claim so made by the petitioners. By order dated 21st February, 2003, this Court referred all the claims and counter-claims before the Arbitrators, by directing to appoint Arbitral Tribunal. The arbitral tribunal was constituted on 14-8-2003.

    9. The petitioners' counter-claim for an amount of Rs. 1,61,50,000/- was rejected totally on the ground of delay in execution of work. Admittedly, by consent of the parties, the time was extended from time to time. The counterclaim was made for the first time in the letter dated 14-8-2003. It was not specifically raised though Arbitration Proceedings commenced as per section 21 and 85 of the Arbitration and Conciliation Act, 1996 (for short, “the Act”) on the date of appointment of Arbitrator, dated 20th August, 2001. It was not supported by any evidence and/or material on record except bare averments. The petitioners did not even lead any evidence to support the counter-claims before the Arbitral Tribunal. Therefore, as it was speculative in nature, it was not considered by the Arbitral Tribunal at all. The learned counsel appearing for the petitioners fairly conceded to the position during the course of hearing in this proceedings also.

    10. Admittedly, pursuance to clause 17 of GCC, the respondents applied for extension from time to time stating reasons for delay. The petitioners extended the time with clear terms of no claim or compensation based upon the same. In view of this agreed terms, there is force in the contention raised by the petitioners' counsel that the respondents-Original Claimants are not entitled for any claims arising out of and/or because of delay in completion of the project though time was extended. The extension was granted with token penalty of Rs. 5000/- per month; was due to abnormal delay in execution of work and partly because of slow and tardy progress of the work. The petitioner paid to the respondents as per the statements submitted on a regular intervals; based upon the jointly signed records and documents. The claimant completed the final work on 20th March, 2001. However, the final bill could not be drawn because of missing items of the contract. It is clear from the award as well as from the submission made by the learned counsel appearing for the petitioners that as per the joint measurement, as per clause 45 of GCC and as the same falls under “the excepted matters” in terms of Clause 63 of GCC, the total balance amount payable was only Rs. 3,00,919/-. The claim of work done (Claim No. 1) but not paid till this date to the extent of above amount which, as recorded, was excluding the mistake as discussed in the meeting. Therefore, I am of the view that, the respondent is entitled for the amount of Rs. 3,00,919/- only and not Rs. 8,45,267/- as awarded.

    11. So far as the payment of extra items (Claim No. 2), there is no denial to the fact that the respondents have carried out the said work at site. Thus, extra items were necessary to be executed at site of work, without which the contracted items could not have been completed by the respondents. The Arbitral Tribunal, therefore, after considering the fact that though these extra items were not part of the schedule items executed by the respondents, yet granted the claim. The payment of extra items were claimed by the claimant during the execution of the work itself and thereafter, carried out the work. The petitioner had not settled the rate of extra items at the relevant time and therefore, became part of the claim of the respondents. The Tribunal has discussed the quantity of the work and also each individual extra items, including the rate so demanded. As it was a gauge conversion work and there was no approach by Rail neither by broad-gauge nor by narrow-gauge, the entire transportation of rails was thus, carried out by road by a separate contractor. Admittedly, the rails were dumped at considerable distances. It is also noted that the work site was not at all approachable by rail. The NG track had been uprooted and BG in any case was not there. The transporter utilized the road vehicles for moving these rails from other divisions and then unloaded/dumped the rails at locations which were convenient and in a fit condition to be approached by the transporter trucks. The site order book also established that the claimants used cranes for the shifting of the rails. The utilization of cranes is also not in dispute. In view of this, the claim as awarded by the Arbitral Tribunal, after giving detailed discussion on the quality of the work and rates payable for the various extra items by taking note of the schedule of rates of Central Railway-1990, item 18202 by providing 4 times rate is reasonable and need no interference, including the rate of shifting of rails by the respondents @ of Rs. 220.44 per tonne. Total amount so awarded, therefore, of Rs. 8,84,256/- on these both counts need no interference. The discretion and expertized so used by the Arbitral Tribunal and awarded claim based upon the material available on record and after taking note of schedule of rates of Central Railway, in my view also is fair and reasonable.

    12. The refund of security deposit of Rs. 3,00,000/- (claim No. 3) after completion of the work under the provision of GCC, should follow. There is no dispute about this issue. However, it is made clear that it is to be paid to the respondents without any interest.

    13. So far as sorting of old rails (Claim No. 4), as per clause 7-A of special condition No. 5 and Clause 37 of GCC the rates quoted by the tenderers are all inclusive. This part of the work for which the payment was awarded, already exists in the basic rate of items. I am of the view that such claim falls under the category of excepted matter in terms of clause 63. Therefore, the amount so awarded is liable to be set aside.

    14. The underutilization of overheads (Claim No. 5), falls within the provisions of Clause 7-A read with Condition No. 22 and Clause 37 of GCC. As per this also the rates quoted by the tenderers are all inclusive till the successful completion of the contract work and as the extension was granted on the undertaking of the respondents that they shall not claim any compensation on account of such extension, the respondents are not entitled for this claim also. Even otherwise, the amount so awarded on hypothesis basis without considering the objections raised by the petitioner that this claim also falls within the ambit of “excepted matters”, is liable to be set aside. General Manager, Northern Railways v. Sarvesh Chopra, (2002) 4 SCC 45 : AIR 2002 SC 1272.

    15. With regard to the wrongful deduction (Claim No. 8), the learned counsel appearing for the petitioner did not press this issue as the extension was granted by consent of the parties and on account of respective delay of both the parties, so this claim is maintained.

    16. With regard to the payment due to variation in cost of labour and material (Claim No. 9), as awarded without necessary certificate for variation in cost, apart from the fact that there is a specific clause which debars, the contractor from raising any amount towards price escalation, as in the present case, the time was extended on typical undertaking as referred above, therefore, there is no question of any payment due to variation in cost of labour and material. Even though there is a delay because of the defaults on the part of both the parties, still in view of the specific agreement and extension of time on a condition of no claim/compensation on that ground, the grant of price variation is contrary to the terms and is liable to be set aside. The Arbitral Tribunal, cannot go beyond the agreed terms on any count. Ramnath International Construction (P) Ltd. v. Union Of India, (2007) 2 SCC 453 — (2007) 2 SCC 453 : AIR 2007 SC 509.

    17. There is no serious dispute that the same amount was withhold for non submission of certificates, though it was furnished subsequently. This was not seriously contested. The claim No. 11 therefore, as awarded, need no interference.

    18. As conceded by both the counsel, as per clause 16 (3) of GCC, the contractor-respondent is not entitled for any interest on the awarded amount. The Arbitral Tribunal, therefore, was right in not granting the said amount.

    19. In view of above, as the award can be modified and/or some of the claims can be retained/maintained in view of R.S Jiwani (M/S.), Mumbai… v. Ircon International Ltd., Mumbai…., Mumbai, 2010 (1) Mh.L.J 547, I have modified the award as above. The rest of the award is maintained.

    20. The Petition is accordingly partly allowed to the above extent. No order as to costs.

    Petition partly allowed.