Structured Summary of the Opinion

Factual and Procedural Background

The petitioners are the owners of land on which a building for respondent No.1 (a Housing Society) has been constructed. The petition is filed under section 8 of the Arbitration and Conciliation Act, 1996, seeking reference of disputes in Suit No. 445 of 2008 to arbitration. The Society and one member had instituted Suit No. 445 of 2008 against the petitioners (owners) for specific performance based on an agreement for sale dated 15-5-2002.

The agreement contains (inter alia) clause 1 (obligation of the promoters/petitioners to construct the building in accordance with sanctioned plans) and clause 40 (a comprehensive arbitration clause providing for reference of disputes to arbitration under the Arbitration and Conciliation Act, 1996; arbitration to be held in Mumbai; mechanism for appointment of arbitrators; award to be final and binding).

The suit by the Society seeks multiple reliefs including specific performance of the agreement, enforcement of obligations under provisions of the Maharashtra Ownership Flats Act, 1963, cancellation of a condominium declaration in respect of certain flats and parking spaces, delivery of possession of recreational ground and related mandatory injunctions and directions against the defendants (which include the petitioners and the Municipal Corporation as respondent No.3).

By consent of parties, the Rule was made returnable forthwith and the petition was heard finally. The petitioners sought relief that the Court refer the disputes to arbitration under section 8 and stay proceedings pending the arbitration.

Legal Issues Presented

  1. Whether the disputes arising out of Suit No. 445 of 2008 are referable to arbitration under section 8 of the Arbitration and Conciliation Act, 1996, in view of the arbitration clause (clause 40) in the agreement dated 15-5-2002.
  2. Whether the presence of a third party (the Municipal Corporation/respondent No.3), and reliefs sought against such third party, precludes reference of disputes between the Society/members and the petitioners to arbitration.
  3. Whether the arbitration clause empowers the arbitrator to decide remedies sought (including specific performance) and thus requires the suit to be stayed or referred to arbitration before adjudication by the Court.

Arguments of the Parties

Respondent (Society and member) — Arguments as recorded

  • The learned counsel for the respondent relied on Sukanya Holdings Pvt. Ltd. v. Jayesh H Pandya (2003) and a judgment of this Court in Bombay Isle Developers Pvt. Ltd. v. Kamladevi Jagdish Diwan (2006), arguing that because the reliefs in the suit are sought not only against the petitioners but also against the Municipal Corporation (a local sanctioning authority and respondent No.3), the disputes cannot be simply referred to arbitration; the existence of reliefs against the Corporation meant the arbitration clause could not be utilized to oust the Court's jurisdiction in this matter.
  • It was contended that the reliefs and averments in the plaint cannot be neatly dissected to isolate matters covered by the arbitration clause, and that the reliefs against the Municipal Corporation rendered the suit non-referable to arbitration, so the petition under section 8 should be dismissed.

Petitioners (Owners) — Position as recorded

  • The petitioners invoked section 8 of the Arbitration and Conciliation Act, 1996, seeking reference of the disputes in Suit No. 445 of 2008 to arbitration in view of the arbitration clause in the agreement (clause 40). They sought a stay of the suit pending arbitration.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Sukanya Holdings Pvt. Ltd. v. Jayesh H Pandya, (2003) 5 SCC 531 : AIR 2003 SC 2252 Authority on the scope and effect of arbitration clauses and the interplay with court jurisdiction (as relied upon by respondents). The respondents relied upon Sukanya Holdings to oppose the section 8 petition; the Court recorded that the law laid down in Sukanya "needs no discussion" but found the respondents' submissions based on it to be unacceptable in the facts of the present case.
Bombay Isle Developers Pvt. Ltd. v. Kamladevi Jagdish Diwan, 2006 (4) Mh.L.J 115 Used by respondents to show circumstances where arbitration clause could not be invoked because reliefs were inseparable and involved a municipal corporation not party to arbitration agreement. The Court distinguished Bombay Isle on facts: in that case the Corporation was not party to the development agreement and there was termination and I.O.D. non-compliance—facts which are different from the present matter where members are in occupation and seek specific performance; thus Bombay Isle did not preclude reference to arbitration here.

Court's Reasoning and Analysis

The Court's analysis proceeded from the text of the agreement and the statutory mandate of section 8 of the Arbitration and Conciliation Act, 1996:

  1. Identification of the arbitration clause: Clause 40 of the agreement expressly provides that "all disputes or differences whatsoever" touching the agreement shall be referred to arbitration under the Act, that the reference shall be to one arbitrator if the parties concur, otherwise each party shall appoint one, and that the arbitration proceedings shall be held in Mumbai. The clause extends to successors-in-title and transferees.
  2. Mandatory nature of section 8: The Court emphasized that the mandate of section 8 is mandatory and must be respected by parties to an arbitration agreement. There was no dispute about the existence or validity of the arbitration clause; the clause was annexed to the petition.
  3. Competence of the arbitrator: The Court held that the arbitrator is competent and empowered to decide issues arising out of the contract, including claims for specific performance; thus the arbitrator could decide merits or grant appropriate reliefs, including specific performance, if warranted on the materials and submissions placed before him/her.
  4. Effect of third-party/multi-party reliefs: The Court considered the argument that the presence of the Municipal Corporation as a party and reliefs sought against it should prevent reference to arbitration. The Court rejected that argument in the present facts: simply joining a local authority or third party is not a sole criteria to reject a petition under section 8. The Court held that the overall pleadings and prayers must be considered to decide the applicability of section 8, and where the basic averments fall within the arbitration clause, the matter should be referred to arbitration even if a third party is joined.
  5. Distinguishing precedent: The Court distinguished Bombay Isle Developers on its facts, noting that in that case the Corporation was not party to the agreement and facts involved termination and I.O.D. non-compliance; in the present case the Society/members are in occupation based on an occupation certificate and seek specific performance, and there is no request to revoke commencement certificate or seek stop-work directions. Hence, the arbitrator can direct performance by the parties here.
  6. Relief of the petitioners: Given the arbitration clause's breadth and binding effect, and the mandatory nature of section 8, the Court concluded there was no reason to allow the Society and its members to proceed with the suit without first resorting to arbitration. The Court therefore referred all disputes/issues arising out of the agreement to arbitration and granted the relief sought in prayer (a) of the petition.
  7. Interim relief and procedure: The Court recorded that an existing interim order against the petitioners in the suit would continue until the arbitrator modifies or passes appropriate orders. The parties were given liberty to apply to the arbitrator (including applications for amendment/modification of interim relief). The parties and arbitrator were directed to take steps to complete arbitration within a reasonable time.

Holding and Implications

Holding: Petition allowed in terms of prayer clause (a) — the Court referred all disputes/issues arising out of the agreement to arbitration under section 8 of the Arbitration and Conciliation Act, 1996.

Direct consequences and practical implications as recorded in the opinion:

  • All disputes/issues arising out of the agreement are referred to the Arbitrator.
  • The parties are to appoint an arbitrator by consent and take steps accordingly.
  • Existing interim order granted in the suit against the petitioners shall continue until the Arbitrator modifies or passes appropriate orders; parties have liberty to make appropriate applications to the Arbitrator, including for amendment or modification of interim relief.
  • The parties and the arbitrator are directed to take steps to complete the arbitration within a reasonable time.
  • No costs were awarded.

The opinion does not state that it lays down any new legal precedent; it confines itself to applying the arbitration clause and the mandatory mandate of section 8 to the facts, and keeps all points/issues open for determination by the Arbitrator.

Petition allowed.

    A.B.K Dubhash And Others v. Petit Towers Co-Operative Housing Society Ltd., Mumbai And Others

    1. By consent of the parties, Rule made returnable forthwith. Heard finally. The others are formal parties.

    2. The petition is under section 8 of the Arbitration and Conciliation Act, 1996 (for short “the Act”), filed by the petitioners, who are the owners of the land on which a building for respondent No. 1 a Housing Society (for short “the Society”), has been constructed. All the members of the Society have been occupying the respective flats, based upon a occupation certificate, granted in their favour. The prayers in the petition are as under:

    a) That this Hon'ble Court be pleased to refer the parties to arbitration in respect of the disputes raised in Suit No. 445 of 2008, under section 8 of the Arbitration and Conciliation Act, 1996.

    b) that pending the hearing and final disposal of this petition the proceedings in Notice of Motion No. 603 of 2008 and Suit No. 445 of 2008 pending before this Hon'ble Court be stayed,

    c) For interim and ad interim reliefs in terms of prayer clause (b) above.

    3. Suit No. 445 of 2008 is filed by the society and one member basically against the petitioners/owners for specific performance based upon an agreement for sale (for short “the agreement”) dated 15-5-2002 between them.

    4. This agreement in question provides following clauses.

    1. The Promoters shall construct the said building consisting of basement, stilt floor, plenum floor and 24 upper floors on the said property, in accordance with the plans, designs and specifications approved and sanctioned by the concerned local authority and which have been seen and approved by the Purchaser/s with only such amendments, alterations, variations, modifications and/or additions thereto therein as the Promoters may consider necessary or as may be required by the concerned government/local authorities to be made in them or any of them.

    40. All disputes or differences whatsoever (subject to the provisions of clause 13 herein) which shall at any time hereafter (whether during the continuance of this Agreement or upon or after its discharge or determination) arise between the parties hereto or their respective heirs, legal representatives, successors-in-title, transferees and assigns (as the case may be), touching or concerning this Agreement or its construction or effect, or as to the rights, duties, obligations, responsibilities or liabilities of the parties hereto or any of the, under or by virtue of this Agreement or otherwise, or as to any other matter, in any way connected with or arising out of or in relation to the subject-matter of this Agreement, shall be referred to arbitration in accordance with and subject to the provisions of the Arbitration and Conciliation Act, 1996, or any statutory modification or re-enactment thereof for the time being in force. The reference shall be made to one arbitrator if the parties concur in the appointment of a single arbitrator, failing which each party shall appoint one arbitrator. In the even of there being an even number of arbitrators, the arbitrators shall before entering upon the reference, in turn appoint a presiding arbitrator. The award of the arbitrator/s shall be final and binding on the parties to the reference. The arbitration proceedings shall be held in Mumbai only.

    5. The main prayers of the suit are as under.

    a) That this Hon'ble Court be pleased to grant specific performance of the said agreement at Exhibit “A” hereto as well as enforce the obligation under section 10 of the Maharashtra Ownership Flats Act, 1963 for an order and decree and direction to the Defendants to specifically perform the said agreement and comply with the obligation under section 11 of the Maharashtra Ownership Flats Act, 1963 for the purpose of conveying the building and grant necessary lease of that portion of the land app. 6000 sq. mts., which is necessary for the purpose of covering the FSI which is also consumed by the Defendants/Promoters for construction of the said building.

    b) That this Hon'ble Court be pleased to direct the Defendants to enforce the obligations which are contained under various provisions of the Maharashtra Ownership Flats Act, 1963 as well as under the contract entered into by and between the parties being Exhibit “A” hereto.

    c) That this Hon'ble Court be pleased to cancel the said so called condominium constituted by the Defendants in respect of the 8 flats and 32 parking spaces and a declaration filed under section 2 of the Maharashtra Apartment Ownership Act, 1970 be declared as null and void and cancel the same.

    d) That this Hon'ble Court be pleased to pass an order and decree in favour of the Plaintiffs and against the Defendants directing the Defendants by mandatory permanent order and injunction to hand over possession of the entire recreational ground and area in accordance with the provisions of the sanctioned plan.

    e) ‘That this Hon’ ble Court be pleased to issue a permanent mandatory injunction directing the defendant No. 8 to enforce the sanctioned plan and direct the defendant Nos. 1 to 7 to comply with the requisition contained in the said letter dated 30-7-2005 (being Exhibit H hereto).

    6. The learned counsel, appearing for the respondent has strongly relied upon the Supreme Court Judgment in Sukanya Holdings Pvt. Ltd. v. Jayesh H Pandya, (2003) 5 SCC 531 : AIR 2003 SC 2252 and a judgment of this Court, in Bombay Isle Developers Pvt. Ltd. v. Kamladevi Jagdish Diwan, 2006 (4) Mh.L.J 115, contending that in view of the prayer clauses itself and in view of the averments made in the suit, it is difficult to dissect these averments as well as the prayer clauses so made. The reliefs are not only against the petitioners but also against the Municipal Corporation, a local sanctioning authority, respondent No. 3, who can only direct or take action against the petitioners for non compliance or breaches of the clauses and no-one else, though there exists the agreement of arbitration between the parties. Therefore, the petition as filed is liable to be dismissed.

    7. Clause (1) of the agreement as reproduced above itself provides the obligations of the petitioners to get the building constructed in accordance with the plan, design and specifications, approved and sanctioned by the concerned authorities. The averments in the suit itself show alleged breaches of the agreement. Therefore, the main reliefs for the specific performances are sought. If there are breaches of agreement clauses, the clear clause of arbitration as reproduced above, which is binding not only to the parties to the agreement but also to the successors-in-title, transferees, as agreed by them, as reflected in clause 40 of the agreement and same should be resorted to first. I see there is no reason to allow respondent Nos. I & 2.original plaintiffs to continue with the suit in view of these agreed and binding clauses.

    8. It is settled that the mandate of section 8 of the Act, needs to be respected by all the parties to the arbitration agreement. It is mandatory. There is no dispute about the existence of arbitration clause in the agreement between the parties. The arbitration agreement is annexed to the petition. The arbitrator is competent and empowered to decide the issues arising out of the contract between the parties. The parties cannot ignore such clauses without getting their disputes/issues settled through the arbitration proceedings. The arbitration agreement is valid, binding, operative and enforceable. In these background and as subject-matters of the suit are covered by the arbitration agreement, it is necessary to refer the matter to the arbitrator. The arbitration must go on first. In my view, it is in consonance with the object of the Act for encouraging resolution of disputes expeditiously.

    9. The breaches, if any, fall within the ambit of the agreement which provides to settle such differences, whatsoever, by the process of arbitration. The basic reliefs and even otherwise after considering the merits of the matter, and considering the rival disputed questions and facts, the Arbitrator can decide and/or give specific order or direction accordingly. Even otherwise, the Arbitrator is empowered to grant specific performance. Such suit by joining Municipal Corporation as respondent No. 3 as party and seeking same relief or direction against the petitioners upon the clauses of the agreement, in my view is nothing but to overlook the mandate of section 8 of the Act. Let the Arbitrator decide and/or resolve the dispute if any first. The overall and the totality of the pleadings and prayers need to be considered to decide all the aspects of section 8 of the Act. The third party to the suit and the arbitration agreement itself cannot be the sole criteria to reject petition under section 8 of the Act, In the agreement with the builder or owner, the society or its member, by joining local authority or third person, wants to frustrate the object of arbitration process though specifically agreed by them to follow the same in case of disputes.

    10. The prayer clause (a) even if considered as a basic relief which the society and the member are seeking against the local authority for enforcement of the sanctioned plan and direction against the petitioners, still that itself cannot be the reason to permit such members or the society, who are admittedly in occupation of the respective flats, based upon the occupation certificate granted by the local authority by its letter dated 30th July, 2005, to continue with the suit. The demand/representation was already made by the society for compliances of agreement and specially of the clause (1) as produced above. All the pleadings and prayers revolve around the agreement between the parties. The petitioners may able to comply with the given directions and/or settle the grievances or conflicts, even by negotiations. There is no reason that the suit at the instance of such members or the society be permitted to continue, as done in the present case, to settle their personal grudges or conflicts. Their intent and purpose should be the completion of the building as agreed.

    11. The case of Bombay Isle Developers Pvt. Ltd. (supra), was of termination of development agreement itself. Admittedly, the Corporation was not a party to the same and as such arbitration clause could not have been utilized, the learned Single Judge has passed the order by observing as under:

    “Having considered the rival submissions, I have no hesitation in taking the view that this Appeal is devoid of merits. I am in agreement with the conclusion reached by the trial Court that all the issues raised in the plaint are not governed by the arbitration agreement between the plaintiff and the defendant No. 1; and that the cause of action for instituting the suit against defendant No. 2-Corporation who is not party to the Arbitration agreement is inseparable”.

    In that case there was non-compliance of conditions of I.O.D, and in spite of that commencement certificate was issued by the Corporation. The construction was commenced based upon the same. Therefore, the arbitrator could not have passed any order with that regard in the arbitration proceedings. The facts and circumstances are totally different. In the present case the respondent members after construction of the building, which they have been occupying, want the specific performance of the agreement, by alleging breaches. The arbitrator in the present case can direct the parties to perform their part of the contract. There is no question of ‘stop work notice’ and/or a prayer to revoke the commencement certificate, at the instance of the society and its members, who are admittedly enjoying the possession since long.

    12. The parties, therefore, if approached the Arbitrator and place their submissions and documents and in a given case the compliances can be directed, I see, there is no reason for such society and its members to agitate such issues further, except to see that the other party comply with the basic requirement. Any such action or permitting the suit to be filed or continue will be contrary to the scheme of the Arbitration Act.

    13. The law laid down in case of Sukanya Holdings Pvt. Ltd. (supra), needs no discussion. The submissions so made by the learned counsel appearing for the respondent opposing the present petition are unacceptable in view of the facts and circumstances of the present case.

    In view of above, the submission so raised by the learned counsel for the respondents referring for the local authority being third party to the agreement and on that ground itself such dispute/differences cannot be agitated before the Arbitrator even though there is clear arbitration clause is unacceptable. If basic averments read with the agreement between parties, itself is sufficient to consider the case of referring the matter to the Arbitrator in view of the agreed clauses between the parties which is mandate of the Act, I see, there is no reason that such arbitration clause need not be resorted to first. The matter needs to be decided by the Arbitrator in accordance with law and in view of the agreed clause itself. Making some third person or party to such suit and by overlooking the basic facts and the agreement between the parties, the respondent society wants to frustrate the whole purpose of such arbitration agreement. I am of the view that the present petition needs to be allowed in terms of prayer clause (a) which reads thus:

    (a) that this Hon'ble Court be pleased to refer the parties to arbitration in respect of the disputes raised in Suit No. 445 of 2008, under section 8 of the Arbitration and Conciliation Act, 1996;

    All the points/issues are kept open.

    All disputes/issues arising out the agreement are referred to the Arbitrator.

    The parties to appoint arbitrator by consent and take steps accordingly.

    14. Admittedly in a suit after hearing both parties there is a interim relief granted against the petitioners, that interim order to continue till the Arbitrator modify or pass appropriate order. Liberty is also granted to the parties to take out an appropriate application before the Arbitrator including for amendment and/or modification of interim relief if any.

    15. The Parties and the arbitrator to take steps in view of above, within reasonable time to complete the arbitration proceedings. The petition is allowed in terms of prayer clause (a), No costs.

    Petition allowed.