Minn. R. 7835.0500 : Public Utilities Commission — COGENERATION AND SMALL POWER PRODUCTION —FILING REQUIREMENTS — SCHEDULE A

Schedule A must contain the estimated system average incremental energy costs by seasonal peak and off-peak periods for each of the next five years. For each seasonal period, system incremental energy costs must be averaged during system daily peak hours, system daily off-peak hours, and all hours in the season. The energy costs must be increased by a factor equal to 50 percent of the line losses shown in schedule B. Schedule A must describe in detail the method used to determine the on-peak and off-peak hours and seasonal periods and must show the resulting on-peak and off-peak and seasonal hours selected.

Minn. R. 7835.0500

9 SR 993

Statutory Authority: MS s 216A.05; 216B.08; 216B.164

SECTIONS