Alexandrov v. N.Y. State Canal Corp.

New York State Court of Claims
Nov 4, 2013

W. BROOKS DeBOW

Synopsis

Defendant's motion to dismiss claim for property damages due to flooding from Hurricane Irene granted for failure to sufficiently state the nature of the claim within the meaning of Court of Claims Act § 11 (b). Claim alleged only that defendant was negligent in its design, maintenance, control and operation of the Erie Canal System and the Mohawk River Watershed, but did not state any facts regarding any particular structures or acts or omissions of defendant's employees that would allow defendant to investigate its potential liability.

Case information

+-----------------------------------------------------------------------------+ ¦UID: ¦2013-038-566 ¦ +---------------+-------------------------------------------------------------¦ ¦ ¦MICHAEL ALEXANDROV and WILLIAM FRYE; CAROL APERANCE and ¦ ¦ ¦STEPHEN C. SCHLAMOWITZ, MARCIA AUGUSTA; CLAUDIA A. ¦ ¦ ¦JAKUBOWSKI, JANET CARTA, LINDA KNIPPER, MARION WHALEN and ¦ ¦ ¦RICHARD A. WHALEN; RONALD COLASANTI as POA for HELEN ¦ ¦ ¦COLASANTI; PATRICK COPPOLO and MARY LOU COPPOLO; SCOTT ¦ ¦ ¦CORNELIOUS; KRISTEN CUSANO; JODI DECKER; DECKERS LANDSCAPING ¦ ¦ ¦& NURSERY, INC.; SHIRLEY J. DeLUCA; EMERINA "AMY" DiCAPRIO; ¦ ¦ ¦ANTHONY DIMASCIO; ANTHONY DURANTE; ALBERT FARONE; GLORIA HART¦ ¦ ¦and DAVE HART; CARMELLA HANLEY; DANIEL HLADIK; ALLYN HOLLIDAY¦ ¦ ¦and SUZANNE HOLLIDAY; ANNE HUNGERSCHAFER; RANDALL KARL; ERIC ¦ ¦ ¦RAILINE and RENE LATELLA; MICHAEL E. LAVALLEE; JOSH LITTELL; ¦ ¦Claimant(s): ¦DEIVIDAS LUKOSIUNAS and RACHEL MANNING; ANDREW F. MARS and ¦ ¦ ¦NANCY M. MARS; PATRICIA MASTROIANNI; MICHAEL MILLER; DEBORAH ¦ ¦ ¦MONTANARO; ALICE J. MYERS; ROD NATALIE JR.; THERESA NOWICKI; ¦ ¦ ¦DAVID OROLOGIO; LISA MARIE PEARO; BONNIE PEDONE; MARIA ¦ ¦ ¦PEDONE; SOMER PEDONE and ROBERT PEDONE; JENNIFER PERRY and ¦ ¦ ¦MARK PERRY; JAY PICKER; TABATHA REIN; WILLIAM REMILLARD and ¦ ¦ ¦MARY LOU REMILLARD; SUSAN RYDER; KENNETH J. SLEZAK; GEORGE M.¦ ¦ ¦SONNENFROH; DAVID STARR; DONALD C. STEENBURGH; ANN TESTA and ¦ ¦ ¦JOSEPH TESTA; FABIO TROIANI; JAMES TROIANO; ROBERT W. TYS; ¦ ¦ ¦ALBERT VANANTWERP; PAUL VANSTON, JANE VANSTON, and BRIAN N. ¦ ¦ ¦VANSTON; JAN VAN WINGERDEN AND LORRAINE VAN WINGERDEN; ¦ ¦ ¦VICTORIA WALKER; DONNA WOLBERT; LINDSAY WOLBERT; DALE ¦ ¦ ¦WOTHERSPOON and KELLIE WOTHERSPON ¦ +---------------+-------------------------------------------------------------¦ ¦Claimant short ¦ALEXANDROV ¦ ¦name: ¦ ¦ +---------------+-------------------------------------------------------------¦ ¦Footnote ¦ ¦ ¦(claimant name)¦ ¦ ¦: ¦ ¦ +---------------+-------------------------------------------------------------¦ ¦Defendant(s): ¦THE NEW YORK STATE CANAL CORPORATION, a subsidiary of THE NEW¦ ¦ ¦YORK STATE THRUWAY AUTHORITY ¦ +---------------+-------------------------------------------------------------¦ ¦Footnote ¦ ¦ ¦(defendant ¦ ¦ ¦name) : ¦ ¦ +---------------+-------------------------------------------------------------¦ ¦Third-party ¦ ¦ ¦claimant(s): ¦ ¦ +---------------+-------------------------------------------------------------¦ ¦Third-party ¦ ¦ ¦defendant(s): ¦ ¦ +---------------+-------------------------------------------------------------¦ ¦Claim number ¦122752 ¦ ¦(s): ¦ ¦ +---------------+-------------------------------------------------------------¦ ¦Motion number ¦M-83716 ¦ ¦(s): ¦ ¦ +---------------+-------------------------------------------------------------¦ ¦Cross-motion ¦ ¦ ¦number(s): ¦ ¦ +---------------+-------------------------------------------------------------¦ ¦Judge: ¦W. BROOKS DeBOW ¦ +---------------+-------------------------------------------------------------¦ ¦Claimant's ¦THE DeLORENZO LAW FIRM, LLP ¦ ¦attorney: ¦ ¦ ¦ ¦By: Cory Ross Dalmata, Esq. ¦ +---------------+-------------------------------------------------------------¦ ¦ ¦ERIC T. SCHNEIDERMAN, ATTORNEY GENERAL OF THE STATE OF NEW ¦ ¦Defendant's ¦YORK ¦ ¦attorney: ¦ ¦ ¦ ¦By: Douglas R. Kemp, Assistant Attorney General ¦ +---------------+-------------------------------------------------------------¦ ¦Third-party ¦ ¦ ¦defendant's ¦ ¦ ¦attorney: ¦ ¦ +---------------+-------------------------------------------------------------¦ ¦Signature date:¦November 4, 2013 ¦ +---------------+-------------------------------------------------------------¦ ¦City: ¦Albany ¦ +---------------+-------------------------------------------------------------¦ ¦Comments: ¦ ¦ +---------------+-------------------------------------------------------------¦ ¦Official ¦ ¦ ¦citation: ¦ ¦ +---------------+-------------------------------------------------------------¦ ¦Appellate ¦ ¦ ¦results: ¦ ¦ +---------------+-------------------------------------------------------------¦ ¦See also ¦ ¦ ¦(multicaptioned¦ ¦ ¦case) ¦ ¦ +-----------------------------------------------------------------------------+

Decision

This claim seeks compensation for damage to the real and personal property of multiple claimants due to flooding that followed Hurricane Irene on August 29, 2011. Defendant moves in lieu of answer to dismiss the claim on the ground that it does not adequately state the nature of the claim as required by Court of Claims Act § 11 (b). Defendant's motion also seeks dismissal as against four claimants who were added by service of a supplemental notice of intention to file a claim which, defendant argues, was not timely served. Claimants oppose the motion in its entirety.

The Court of Claims Act requires that "[t]he claim shall state the time when and place where such claim arose, the nature of same, and the items of damage or injuries claimed to have been sustained and . . . the total sum claimed" (Court of Claims Act § 11 [b]). To satisfy the "nature of the claim" requirement, the claim must state facts that are sufficiently definite " 'to enable the State . . . to investigate the claim[s] promptly and to ascertain its liability under the circumstances' " (Lepkowski v State of New York, 1 NY3d 201, 207 [2003], quoting Heisler v State of New York, 78 AD2d 767, 767 [4th Dept 1980]). "Although absolute exactness is not required the claim must provide a sufficiently detailed description of the particulars of the claim . . . [and] defendant is not required to ferret out or assemble information that section 11 (b) obligates the claimant to allege" (Morra v State of New York, 107 AD3d 1115, 1115-1116 [3d Dept 2013] [internal quotations and citations omitted]). The "nature of the claim" requirement is not satisfied by conclusory or general assertions of negligence without factual allegations that reveal some act or omission that would give rise to defendant's liability (see Grumet v State of New York, 256 AD2d 441 [2d Dept 1998] [claim for slip and fall alleged that defendant was "careless, reckless and negligent"]; Cendales v State of New York, 2 AD3d 1165, 1167-1168 [3d Dept 2003] [reference to "medical staff" in notice of intention to file a claim for injuries during cell extraction was insufficient notice of medical malpractice cause of action]; Tamez v New York State Thruway Auth. and State of New York, UID No. 2007-015-213 [Ct Cl, Collins, J., July 10, 2007] [mere allegation of negligence insufficient to satisfy Court of Claims Act § 11 (b)]; see also Karen's Produce v State of New York and New York State Canal Corp., UID No. 2012-048-071 [Ct Cl, Bruening, J., Nov. 8, 2012] [proposed claim alleged negligence in oversight, operation, maintenance and/or design of the Erie Canal System and associated structures and waterways, but did "not allege[] any specific acts or omissions that caused (claimants') damage"]; Davis v State of New York, UID No. 2004-016-071 [Ct Cl, Marin, J., Nov. 19, 2004] [proposed claim that merely referred to accident and made general allegations of negligence did not satisfy Court of Claims Act § 11 (b)]). Rather, the claim must allow at least a reasonable inference to be drawn as to "how the defendant was negligent" (Heisler, 78 AD2d at 768). The failure to comply with the pleading requirements of Court of Claims Act § 11 (b) is a fatal defect in subject matter jurisdiction that requires dismissal of the claim (see Lepkowski, at 209; Kolnacki v State of New York, 8 NY3d 277, 281 [2007]), "even though this may be a harsh result" (Morra at 1116).

Defendant argues that while the claim alleges that defendant is responsible for the operation and maintenance of the Erie Canal System and the locks, bridges and dams of the Mohawk River, the pleading does comply with Court of Claims Act § 11 (b) because it alleges only that defendant was negligent but does not identify the acts or omissions that allegedly caused the flooding of claimants' properties. In relevant part, the claim includes the following allegations:

"59. This claim is for damages suffered by claimants by reason of the negligence of the State of New York, its officers, agents or employees in their acts and omissions including but not limited to the operation, control of maintenance and/or design of the Erie Canal System and the locks, dams, canals and waterways under the defendant's operation and control within the Mohawk River Watershed.

60. On or about the 29th day of August, 2011 heavy rains throughout the State of New York lead to the accumulation of water in the Mohawk River Watershed.

61. As a result of the negligent actions and omissions of the defendant, its offers [sic], agents or employees, including but not limited to failure to properly monitor, maintain, control and operate the canal; and failing to properly monitor, maintain, control and operate the locks within and along the Canal this water was unable to properly drain from the watershed and was caused to back up and flood the areas surrounding the Mohawk River Basin, the Erie Canal and ultimately the lands and properties of the claimants.

62. As a result of the negligent actions and omissions of the defendant, Claimants were each individually caused to suffer property damage . . .

63. As a result of the negligent actions and omissions of the defendant Claimants' property, both real and personal, was rendered unusable . . .

65. As a result of Defendant's violation of duty and by reason of Defendant's negligent conduct, Claimants, have each sustained personal injuries, mental anguish and emotional distress . . .

68. Upon information and belief in constructing, controlling, operating, monitoring and maintaining the Mohawk River Watershed and the Erie Canal Basin the defendants have voluntarily assumed the duty of controlling, operating, monitoring and maintaining the waters of the Watershed and Basin to [the benefit of claimants]. Claimants have all justifiably relied on the defendants' voluntary assumption of this duty to their detriment.

69. Upon information and belief following flooding along the Mohawk River in June of 2006 the defendant incorporated a task force, sponsored numerous studies, invested in remedial measures and undertook numerous flood control projects in the face of the known, blatant and dangerous safety violations pertaining to flooding along the Mohawk Valley Watershed."

(Claim 122752, filed May 22, 2013; see also Kemp Affirmation, Exhibit C). In sum and substance, the claim alleges that defendant was responsible for the design, operation, maintenance and monitoring of the Erie Canal Basin and the Mohawk River Watershed, and that it was negligent and failed to act with regard to these obligations. The generality of the pleading is highlighted by claimants' contention that "the defendants [sic] were negligent in the entirety of their operation, maintenance, control and design of the Erie Canal System" (Dalmata Affirmation, ¶ 14 [emphasis added]).

Although the claim recites the addresses of claimants' flooded properties in Rotterdam Junction and Pattersonville, New York, it does not identify any location or locations within the Erie Canal System or the Mohawk River Watershed where defendant failed to perform any duty, nor does it state the duty to claimants that was breached (compare e.g. Marston v State of New York, et al., ___ Misc2d ___, 972 NYS2d 405 [Ct Cl, Nov. 7, 2012] [claim by estate of decedent who was swept over a dam alleged that defendant failed, among other things, to warn of hidden or latent dangers of the dam, to maintain the dam in a reasonably safe condition, and to provide safeguards to prevent boats or individuals from being swept over the dam]; see also Karen's Produce). There is nothing in the claim to "alert[] the defendant[] as to the nature of the alleged negligence" (Grumet, 256 AD2d at 441). As stated above, the claim must provide some details in this regard, and no burden rests upon defendant to gather the factual information that would shed light on how defendant may have been negligent (see Morra, at 1115-1116; see also Heisler; Tamez). The instant claim does not apprise defendant of any alleged design flaw that permitted the flooding, of any particular structure(s) that may have failed, of any maintenance obligation that was poorly accomplished or left undone, of any omission or misstep in operation that allowed claimants' properties to flood, nor of any other particular act or omission related to the waterways that defendant may have utilized as even a toehold for an investigation into its potential liability. Thus, the Court concludes that the claim does not adequately state the nature of the cause of action, and that it therefore fails to comply with Court of Claims Act § 11 (b).

Claimants' arguments in opposition to defendant's motion do not persuade the Court otherwise. Claimants cite Canal Law § 120, which provides that "[t]here shall be allowed and paid to every person sustaining damages from the canals or from their use or management, or resulting or arising from the neglect or conduct of any officer of the state having charge thereof . . ." Claimants argue that since Canal Law § 120 is a waiver of the state's sovereign immunity for claims specifically arising from the operation of its canal system, the broader waiver of sovereign immunity by the Court of Claims Act should not repeal Canal Law § 120 by implication (see Dalmata Affirmation, ¶¶ 4-6). The argument, however, is based upon a misapprehension of the interplay between Canal Law § 120 and the pleading requirements of the Court of Claims Act.

Canal Law § 120 authorizes certain types of claims to be asserted against the Canal Corporation, but it is silent as to any pleading requirement for such claims. The Canal Corporation is a subsidiary of the New York State Thruway Authority and is subject to suit in the Court of Claims (see Public Authorities Law §§ 382 [2]; 361-b; Erie Blvd. Hydropower, LP v State of New York, 90 AD3d 1292 [3d Dept 2011]; Colon v New York State Thruway Authority, UID No. 2004-013-509 [Ct Cl, Patti, J., July 27, 2004]). Court of Claims Act § 11 (b) sets forth the pleading requirements that are necessary to invoke the jurisdiction of this Court, and it merely requires that, like any other pleading for a claim for damages against the State, the pleading for a claim seeking damages upon a cause of action pursuant to Canal Law § 120 must allege facts that would reveal the nature of the claim so that defendant may investigate its potential liability (cf. E. B. Metal & Rubber Indus. v State of New York, 84 AD2d 659 [3d Dept 1981] [reversing dismissal of claim because pleading adequately stated causes of action for negligent use and management of the Champlain Barge Canal and because Canal Law § 120 expressly waived sovereign immunity for damages arising from the state's misuse or mismanagement of the canal]). Thus, contrary to claimants' view, the two provisions of law are not inconsistent or incompatible, and the substantive pleading requirements of Court of Claims Act § 11 (b) do not subvert or constitute an implicit repealer of the waiver of sovereign immunity and basis of liability that is set forth in Canal Law § 120. In other words, there is no repealer of the right of action authorized by Canal Law § 120 - expressed or implied - effected by the requirement of Court of Claims Act § 11 (b) that the pleading include certain substantive allegations.

Further, claimants' reliance on E. B. Metal & Rubber Indus. for the proposition that its pleading is sufficient is misplaced. In E. B. Metal & Rubber Indus., the Appellate Division determined that there were sufficient allegations in the claim to support the elements of certain causes of action. The decision states that the claim included "allegations that the damages to claimant's property were caused by the State's faulty use and management of the canal" (id. 84 AD2d at 659), but the decision does not discuss nor set forth the facts that were pleaded, and thus, whether the pleading would have satisfied Court of Claims Act § 11 (b) is unknown based merely upon a reading of that decision. Moreover, whether a claim states a cause of action to sufficiently withstand a motion for summary judgment, as in E. B. Metal & Rubber Indus., and whether it satisfactorily states the nature of the claim within the meaning of Court of Claims Act § 11 (b) are not necessarily the same inquiries. Indeed, the instant claim appears to state a cause of action sounding in tort - that the State owed a duty to claimants and breached that duty, and claimants' suffered injury from that breach - and it also states the theories of the claim - that defendant was negligent in its operation, maintenance, control and/or design its waterways. However, it does not set forth the nature of the claim within the meaning of Court of Claims Act § 11 (b) insofar as it does not provide defendant with sufficient information to investigate its potential liability (cf. Bensen v State of New York, 88 Misc 2d 1035, 1041 [Ct Cl 1976] [recognizing the distinction between "theory of the claim" and "nature of the claim"]).

To the extent that claimants imply that they should be relieved from the jurisdictional requirement that the pleading state the nature of the claim because "the specific acts and omissions of the defendants are all facts that, at this time, are in the exclusive possession of the State" (Dalmata Affirmation, ¶ 15) is unavailing, particularly under the circumstances of this action, even if the pleading requirement was not a jurisdictional matter. The claim accrued in late August 2011, when Hurricane Irene struck. In November 2011, claimants served a Notice of Intention to File a Claim (see Kemp Affirmation, Exhibit A), as well as a Supplemental Notice of Intention to File a Claim that added additional claimants (see id. Exhibit B). Claimants offer no reason why they could not, or did not, during the six months that elapsed until the claim was filed and served in May 2013, assemble facts via pre-action discovery pursuant to CPLR 3102 (c), Freedom of Information Law (FOIL) requests, or other independent investigation, that would have provided some factual basis for the allegations of defendant's negligence and would have allowed defendant to investigate the claim.

In sum, defendant's motion to dismiss the claim for failure to sufficiently state the nature of the claim within the meaning of Court of Claims Act § 11 (b) will be granted.

Further, even if the nature of the claim was adequately stated in the pleading, the Court would grant that part of defendant's motion that sought dismissal of the claim as to the four claimants who were added to the caption of the supplemental notice of intention to serve the claim. As relevant here, a notice of intention to file a claim damages from property damage or personal injury due to the State's negligence must be served upon the Attorney General within 90 days after the accrual of the claim (Court of Claims Act § 10 [3]), and if the notice of intention is timely served, the claimants' time to serve and file the claim is extended from 90 days after accrual to two years after accrual of the claim (id.). Service upon the Attorney General of the notice of intention, by either personal service or by mail, is complete when it is received by the Attorney General (see Court of Claims Act § 11 [a] [i]). It is well established that the filing and service requirements of the Court of Claims Act must be strictly construed (see Finnerty v New York State Thruway Auth., 75 NY2d 721, 722-723 [1989]), and that the failure to comply with those requirements is a jurisdictional defect requiring dismissal of the claim (see id.; Ivy v State of New York, 27 AD3d 1190 [4th Dept 2006]; Suarez v State of New York, 193 AD2d 1037 [3d Dept 1993]).

These claimants are Carmella Hanley, Shirley J. DeLuca, Ronald Colasanti as POV [sic] of Helen Colasanti, and Lisa Somerville.

Here, the claim accrued on August 29, 2011 (see Claim No. 122752, ¶ 64), and 90 days thereafter was November 27, 2011. The initial notice of intention was timely served on the Attorney General on November 25, 2011 (see Kemp Affirmation, Exhibit A). However, the supplemental notice of intention was untimely because it was not served until November 30, 2011 (see id., Exhibit B), and the claim as asserted by the four additional claimants who were added in the supplemental notice of intention, had it survived the motion to dismiss for failure to comply with the pleading requirements of Court of Claims Act § 11 (b), would be jurisdictionally defective and would therefore be dismissed.

Accordingly, it is

ORDERED, that motion number M-83716 is GRANTED, and claim number 122752 is DISMISSED.

November 4, 2013

Albany, New York

W. BROOKS DeBOW

Judge of the Court of Claims

Papers considered:

(1) Claim number 122752, filed May 22, 2013;

(2) Notice of Motion, dated July 15, 2013;

(3) Affirmation of Douglas R. Kemp, AAG, affirmed July 15, 2013, with Exhibits A-C;

(4) Affirmation in Opposition of Cory Ross Dalmata, Esq., dated September 8, 2013;

(5) Reply Affirmation of Douglas R. Kemp, AAG, affirmed September 17, 2013.