PERRINI v. CITY OF NEW YORK
ORDERED that the order is reversed insofar as appealed from, on the law, with one bill of costs, those branches of the respective motions of the defendant and the third-party defendant which were for summary judgment dismissing the cause of action premised upon a violation of Labor Law § 241 Lab.(6) are granted, that cause of action is dismissed, and that branch of the plaintiffs' cross motion to amend the complaint and bill of particulars to allege a violation of 12 NYCRR 23-1.7(b)(1) is denied.
The Supreme Court erred in granting the plaintiffs' request to amend the complaint and bill of particulars to allege a violation of 12 NYCRR 23-1.7(b)(1). While it is well settled that leave to amend shall be freely given in the absence of prejudice to the opponent ( see, CPLR 3025[b]; Edenwald Contr. Co. v. City of New York, 60 N.Y.2d 957), permission to amend should be denied where the proposed amendment clearly lacks merit ( see, Parisi v. Leppard, 237 A.D.2d 419; ICC Bridgeport Ltd. Partnership v. Primrose Dev. Corp., 221 A.D.2d 417; McKiernan v. McKiernan, 207 A.D.2d 825). Since both the hazardous condition contemplated by 12 NYCRR 23-1.7(b)(1) and the safety precautions mandated therein are clearly inapplicable to the situation presented in this case, the proposed amendment patently lacks merit and permission to amend should have been denied ( see generally, Finch v. Conrail, 241 A.D.2d 952; Farrell v. Dick Enters., 227 A.D.2d 956).
Furthermore, the respective motions of the appellants for summary judgment dismissing the plaintiffs' claim based on a violation of Labor Law § 241 Lab.(6) must be granted, since the plaintiffs failed to allege the violation of a specific applicable safety regulation in support thereof ( see, Ross v. Curtis-Palmer Hydro-Elec. Co., 81 N.Y.2d 494; Sobelman v. Norstar Bank, 226 A.D.2d 444).
Alert