RAJNESH SHARMA v. M/S BUSINESS PARK TOWN PLANNERS LIMITED

Supreme Court Of India
Sep 24, 2025
Smart Summary (Beta)

Case Summary: Rajnesh Sharma v. M/s. Business Park Town Planners Ltd.
Civil Appeal No. 3988 of 2023, decided 24 September 2025

Factual and Procedural Background

The appellant, Rajnesh Sharma, booked a plot in a project named “Park Land” developed by the respondent, M/s. Business Park Town Planners Ltd. On 10 March 2006, he booked plot no. 2, Block G-4, Phase 2, admeasuring 343 square yards, for a total sale consideration of Rs. 36,03,692/- (basic price Rs. 30,87,000/-). On the same day he paid Rs. 7,86,218/- towards advance/registration charges.

A formal plot buyer agreement (“AGREEMENT”) was executed on 11 December 2007. Under clause 22 of the AGREEMENT, possession of the plot was to be handed over within 24 months of the sanction of the service plans of the entire colony. Clause 12 stipulated that time was of the essence and that, in the event of default by the buyer, the respondent could levy late payment charges at 18% per annum on the due amount, compounded at every succeeding instalment or three months, whichever was earlier.

By April 2011, the appellant had paid Rs. 28,79,065/-. On 13 April 2011, more than five years after the first payment, the respondent informed him that due to “changes in the layout plan” it had decided to allot an alternative plot. The alternative plot was 7 square yards larger than the original, and the respondent demanded an additional Rs. 2,30,784/-. An addendum to the AGREEMENT was executed on the same date. Clause 7 of the AGREEMENT (later reproduced in the judgment) provided for allotment of an alternative plot if a change in the layout plan was required by any statutory authority.

On 11 March 2015, the appellant paid Rs. 83,377.67, out of which Rs. 83,300.76 represented interest at 18% per annum, charged by the respondent on the ground of the appellant’s alleged default in payment. According to the respondent’s statement of accounts dated 23 March 2015, the appellant had by then paid a total of Rs. 43,13,312.67/-.

Aggrieved by the respondent’s failure to hand over possession, the appellant terminated the AGREEMENT by letter dated 27 March 2017. On the same day, he issued a legal notice intimating termination and seeking: (i) refund of Rs. 43,13,212/- with interest at 24% per annum, and (ii) Rs. 72,30,000/- on account of loss of appreciation of the property.

In April 2018, he filed Consumer Case No. 885 of 2018 before the National Consumer Disputes Redressal Commission (NCDRC). After this complaint was filed, the respondent, on 8 May 2018, offered possession of the plot, subject to payment of a further sum of Rs. 7,60,900.33/-.

By order dated 13 January 2023, the NCDRC disposed of the consumer complaint. It directed the respondent to refund the entire principal amount of Rs. 43,13,212/- with simple interest at 9% per annum from the dates of each payment till the date of refund, and to pay Rs. 25,000/- as litigation costs. The NCDRC’s order was passed on the basis of an offer made by the respondent’s counsel during hearing to repay the principal with 9% simple interest per annum, and without going into the merits of the case. The order did not record any acceptance of this offer by the appellant.

The present civil appeal before the Supreme Court of India challenges this NCDRC order at the instance of the partly successful complainant, the appellant herein, essentially on the ground that the rate of interest awarded is inadequate in light of the contractual terms and the respondent’s conduct.

Legal Issues Presented

  1. Whether, on the facts and circumstances of the case—including the terms of the AGREEMENT, the delay in offering possession, the respondent’s conduct, and the interest rate charged by the respondent for the appellant’s defaults—the NCDRC erred in awarding delay compensation in the form of interest at 9% per annum instead of a higher rate.

Arguments of the Parties

Appellant's Arguments

  • The NCDRC wrongly “forced” upon the appellant a refund limited to the principal amount paid, with only 9% simple interest per annum, despite serious lapses on the respondent’s part.
  • The appellant paid a total of Rs. 43,13,313/- in instalments as and when demanded by the respondent. Although the plot was booked in 2006, possession was not offered until 2018. In this context, interest at 9% per annum was inadequate and caused substantial loss to the appellant.
  • The respondent wrongly levied several additional charges, causing the total payment to overshoot the initial sale consideration of Rs. 36,03,692/-. In particular:
    • After allotting an alternative plot in 2011, the respondent demanded Rs. 2,30,784/- as additional price for the 7 square yards increase. According to the appellant, on the basis of the basic rate (Rs. 9,000/- per sq. yard), External Development Charges (EDC) at Rs. 1,024/- per sq. yard, and Infrastructure Development Charges (IDC) at Rs. 445/- per sq. yard, the correct additional amount should have been Rs. 73,283/- only.
    • The respondent charged Rs. 4,81,600/- under the head “Enhanced EDC”, an amount beyond the EDC and IDC specifically provided for in the AGREEMENT.
    • On 11 March 2015—four years after the previous payment in 2011—the respondent demanded Rs. 83,300.67/- as “interest” on delayed payment without supplying any calculation details.
    The appellant paid these amounts to avoid disputes with the respondent.
  • After the consumer complaint was filed, the respondent’s offer of possession dated 8 May 2018 demanded an additional Rs. 7,60,900.33/-, broken down as: Rs. 83,302/- (interest), Rs. 3,13,250/- (electricity and STP charges), Rs. 15,000/- (utility connect charges), Rs. 59,086/- (GST), Rs. 70,262.33/- (previous dues), and Rs. 2,20,000/- (stamp duty). The appellant submitted:
    • The payment plan in Schedule I (Schedule of Costs) to the AGREEMENT, which details all payable charges, does not mention electricity and STP charges; hence, these could not be validly demanded.
    • GST was introduced in 2017, whereas all payments had been made prior to 2012; therefore, GST could not properly be levied on such transactions.
  • Preferential Location Charges (PLC) of Rs. 75,000/- were paid by the appellant as per Schedule I of the AGREEMENT. Yet, in the 8 May 2018 offer letter, the respondent sought an increased PLC amount of Rs. 3,15,000/-, which was unexplained.
  • Even after the NCDRC passed the impugned order, the respondent failed to make payment within the prescribed time. When the appellant’s power-of-attorney holder approached the respondent for compliance, the respondent refused to pay, questioning the authenticity of the power of attorney.
  • Overall, the respondent’s conduct throughout the transaction was “full of blemishes”, including unexplained delays, excessive and opaque charging, and non-compliance with the NCDRC’s order.
  • The respondent had charged the appellant interest at 18% per annum for payment delay, yet only offered to refund the principal with interest at 9% per annum. This lack of symmetry was said to be illogical and unreasonable; for its own default, the respondent should be held to the same standard and be made to pay 18% interest to the appellant.

Respondent's Arguments

  • Requirement of proving actual loss under the Consumer Protection Act, 1986:
    Relying on Section 14 of the Consumer Protection Act, 1986, and particularly on the wording that compensation is to be paid “for any loss or injury suffered by the consumer due to the negligence of the opposite party”, the respondent contended:
    • For an award of compensation, including interest, the consumer must lead evidence to prove actual loss or injury.
    • Compensation cannot exceed the actual loss and cannot become a gain-based remedy.
    • While the AGREEMENT supported the respondent’s right to charge interest at 18% per annum on the buyer’s default, the appellant’s claim for 18% interest from the respondent was unsustainable because the appellant had not proved actual loss.
    To support this proposition, reliance was placed on Ghaziabad Development Authority v. Balbir Singh and Fortune Infrastructure v. Trevor D'Lima.
  • Interest generally around 9% in consumer matters:
    It was argued that the Supreme Court has consistently avoided equating the consumer’s compensatory interest rate with the higher rate contractually chargeable by builders to buyers. Instead, the Court has usually granted around 9% interest in cases of deficiency of service by developers.
  • Claims for parity in interest consistently rejected:
    According to the respondent, the Supreme Court has repeatedly rejected claims by consumers who seek “parity” with builders in the matter of interest rates for delay. Reliance was placed on IREO Grace Realtech (P) Ltd. v. Abhishek Khanna, where the Court:
    • Found the contractual delay compensation of Rs. 7.5 per square foot (equating to about 0.9% to 1% per annum on the deposited amount) to be inadequate; but
    • Rejected the claim for compound interest at 20% per annum as disconnected from the prevailing commercial realities.
    The respondent highlighted that in related matters such as IREO Grace Realtech (P) Ltd. v. Subodh Pawar and IREO Grace Realtech (P) Ltd. v. Surendra Arora, the Court recorded counsel’s statement for refund with interest at 10% per annum, and orders were passed accordingly (prior to the COVID-19 pandemic).
  • Further support from other decisions on interest rates:
    The respondent referred to:
    • Vidya v. Parsvnath Developers Ltd., where this Court held that interest should at least match the rate agreed in the contract (12% per annum in that case), modifying the NCDRC’s grant of 9% to 12% per annum.
    • Kolkata West International City Pvt. Ltd. v. Devasis Rudra, where:
      • The builder-buyer agreement imposed 18% interest on the buyer’s delayed payments, but only the SBI savings bank rate on the builder’s delay in handing over possession.
      • The Court found the agreement to be one-sided, held that this did not preclude the buyer’s right to reasonable interest or compensation, and ultimately reduced the NCDRC’s awarded interest from 12% to 9% per annum.
    • Pioneer Urban Land and Infrastructure Ltd. v. Govindan Raghavan, where the Court upheld an NCDRC order granting simple interest at 10.7% per annum, even though the builder was contractually entitled to charge 18% for buyer’s delays, illustrating that courts do not automatically align buyer’s interest with the builder’s contractual rate.
    From these authorities, the respondent argued that the Court does not accept parity-based claims, and that typical awards are around 9% interest.
  • Non-enforceability of one-sided agreements even for buyers:
    The respondent submitted that if a builder-buyer agreement is found to be one-sided, it cannot be enforced in its entirety, even at the instance of the buyer, implying that buyers cannot selectively rely on punitive clauses against builders while discarding the overall imbalance.
  • Justification of the amounts demanded:
    Addressing the appellant’s allegation of excessive and unjustified charges, the respondent stated:
    • The increase in PLC was due to the allotment of an alternative plot situated on a wider road with potential for commercial usage, justifying a higher PLC.
    • The Rs. 83,300/- interest amount was charged only for the period 2007–2011 on account of delayed payment by the appellant; no interest was charged thereafter.
    • Electrification and STP (sewage treatment plant) charges were payable under clauses 2.5(b) and 2.5(c) of the AGREEMENT, and were therefore contractually permissible.
    • GST was levied only on those charges first raised on 8 May 2018 (offer of possession letter), and only on the “eligible” heads.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Ghaziabad Development Authority v. Balbir Singh (2004) 5 SCC 65 Cited by the respondent for the proposition that, under Section 14 of the Consumer Protection Act, 1986, compensation must be based on “loss or injury” actually suffered due to the opposite party’s negligence; proof of actual loss is required, and compensation cannot exceed such loss or become a gain-based remedy. The Supreme Court agreed in principle that compensation requires proof of actual loss, but clarified that in the present case it was not adjudicating the quantum of loss. Instead, the Court limited itself to determining a reasonable rate of interest on the principal already paid, taking into account the respondent’s conduct and contractual interest rate.
Fortune Infrastructure v. Trevor D'Lima (2018) 5 SCC 442 Cited alongside Balbir Singh to reinforce that compensation under the Consumer Protection Act must correspond to actual loss or injury proved by the consumer and cannot operate as a windfall or gain-based remedy. The Court accepted the general principle that proof of actual loss guides the award of compensation, but emphasized that its task in this appeal was confined to fixing a reasonable interest rate on the refund, not computing damages for loss of appreciation or similar heads.
IREO Grace Realtech (P) Ltd. v. Abhishek Khanna (2021) 3 SCC 241 Cited by the respondent to show that:
  • Contractual delay compensation (Rs. 7.5 per sq. ft., equating to about 0.9–1% per annum) may be deemed inadequate.
  • Claims for very high compound interest (20% per annum) are rejected as inconsistent with prevailing commercial realities.
  • The Court has not accepted extreme parity-based claims by buyers for high interest rates.
The present Court noted that IREO Grace Realtech did not decide the broader question whether buyers can ever claim parity with builders on interest rates. Instead, in that case the Court merely declined the particular 20% compound interest claim as excessive. The Court relied on this to reject the respondent’s contention that parity claims are always barred.
IREO Grace Realtech (P) Ltd. v. Subodh Pawar, 2019 SCC OnLine SC 1937 Mentioned as a related matter where the Court recorded the developer’s statement to refund the amount with interest at 10% per annum, leading to orders on that basis. Used illustratively to show that interest rates have been fixed in prior cases having regard to their specific facts, sometimes at 10% per annum, and that such orders do not establish a rigid, uniform interest rate for all cases.
IREO Grace Realtech (P) Ltd. v. Surendra Arora, 2019 SCC OnLine SC 1943 Similarly cited as a case where, prior to the COVID-19 pandemic, the Court passed orders accepting a 10% per annum interest rate as offered by the developer’s counsel. Again referenced to underline that earlier interest awards were fact-specific and not binding templates for all housing delay disputes. The present Court treated these decisions as context-specific, not as a bar to awarding a different rate here.
Vidya v. Parsvnath Developers Ltd. (2024) 9 SCC 651 Cited to show that where the agreement itself provided for a 12% per annum rate, an NCDRC award of 9% was considered too low:
  • The Court held that the Commission ought at least to have awarded 12% per annum.
  • The Court modified the order to grant 12% per annum from the dates of deposit until refund.
The respondent used this to argue that the Supreme Court adjusts interest rates on a case-by-case basis rather than equating them with builder’s higher contractual default rates.
The present Court read Vidya as an example where the increase to 12% interest was not justified on a general principle of parity, but because 9% was unreasonably low compared to the contractual 12% in the facts of that case. It reinforced the view that no fixed 9% rule exists and that reasonableness must be assessed in each case.
Kolkata West International City Pvt. Ltd. v. Devasis Rudra (2020) 18 SCC 613 Cited to demonstrate the Court’s treatment of one-sided builder-buyer agreements:
  • The agreement imposed 18% interest on the buyer’s delayed payments, but only SBI savings bank interest on the developer’s delay.
  • The Court found the agreement one-sided and held that this did not bar the buyer from claiming reasonable interest/compensation.
  • The Court reduced the NCDRC’s awarded interest from 12% to 9% per annum.
The present Court referred to this case among several to highlight that previous interest determinations (9% or otherwise) flowed from the specific factual context, including the one-sided nature of agreements, and do not constitute an inflexible cap applicable to all disputes. The reasoning also supports the idea that unfair clauses can be moderated by the Court.
Pioneer Urban Land and Infrastructure Ltd. v. Govindan Raghavan (2019) 5 SCC 725 Cited to show that:
  • The Court upheld an NCDRC order awarding simple interest of 10.7% per annum to the buyer.
  • This was done even though the builder was contractually entitled to charge 18% interest for buyer’s delay, indicating that buyer’s compensation is not automatically aligned with the builder’s contractual rate.
The Court used this precedent, along with others, to underscore that there is no uniform rule either fixing interest at 9% or mandating parity with the builder’s default interest. Instead, interest is calibrated to what is reasonable in each case, taking into account contractual terms and overall conduct.

Court's Reasoning and Analysis

The Supreme Court began by examining the respondent’s arguments, particularly the reliance on past case law to suggest that courts consistently award around 9% interest and reject parity-based claims by consumers.

On reviewing the cited decisions, the Court observed that in those earlier cases it had not laid down a general rule against parity, nor had it offered detailed reasons for rejecting claimed rates; rather, it had adjusted interest rates based on a variety of case-specific factors such as prevailing market conditions and, in some instances, the impact of the COVID-19 pandemic.

Specifically, the Court noted that in IREO Grace Realtech (P) Ltd. the issue of whether buyers can claim parity with builders as to interest rates was not squarely addressed. The buyers’ demand for 20% compound interest per annum was rejected because it was considered excessive and unrelated to commercial realities, not because parity was categorically impermissible. Similarly, in Vidya v. Parsvnath Developers Ltd., the Court increased the interest from 9% to 12% per annum on the ground that 9% was less than the contractual rate of 12% and thus unjustified in the particular circumstances, not because of any rule either for or against parity.

From this survey, the Court concluded that it could not be said that the Supreme Court has always rejected parity claims. It explicitly stated that there is no principle of law that the rate of interest charged by a builder for the buyer’s default can never be granted to the buyer in the converse situation.

The Court reaffirmed that the governing standard is reasonableness: the rate of interest must be reasonable, and what is reasonable varies from case to case. The sequence of judgments cited by the respondent to show a “consistent” award of 9% interest did not, in the Court’s view, control the present dispute, because each of those cases turned on its own facts.

Turning to the facts, the Court examined the contractual framework and the respondent’s conduct. Under clause 22 of the AGREEMENT, possession was to be offered within 24 months from the sanction of service plans for the entire colony. It was undisputed that no offer of possession was made until 2018. The Court also scrutinised the events surrounding the allotment of an alternative plot under clause 7.

Clause 7 allowed a change of location or area of the plot if changes in the layout plan were required by a governmental or statutory authority. During arguments, the Court asked the respondent’s senior counsel to demonstrate the basis for invoking clause 7, i.e., to show that a statutory authority had indeed required changes in the layout plan. Counsel responded that the alternative allotment had been made in 2011 and that the appellant had not objected until 2018. The Court found this answer unsatisfactory, stating that whether the appellant had raised a demur was irrelevant to validating the respondent’s conduct under clause 7. Moreover, the respondent’s written submissions did not disclose any material showing that a governmental or statutory direction necessitated the change in layout.

The Court nonetheless proceeded on the basis that, even after the alternative plot was allotted in 2011, possession of that alternative plot was offered only in 2018. This underscored a long delay attributable to the respondent.

The Court then addressed the respondent’s reliance on Section 14 of the Consumer Protection Act, 1986, and the requirement of proof of actual loss. It agreed that before compensation can be granted by the NCDRC, the consumer must establish actual loss and that compensation should not be transformed into a windfall. Proof of actual loss typically requires evidence and serves as a guide for the quantification of compensation.

However, the Court emphasised that, in the present case, it was not called upon to determine the quantum of actual loss or to award damages based on property appreciation or similar heads. Its remit was limited to deciding the appropriate rate of interest to be applied to the refund of the principal amount paid by the appellant to the respondent. Thus, while the abstract legal principle about proof of loss stood accepted, it did not preclude the Court from revisiting the interest rate set by the NCDRC.

In making that determination, the Court took into account:

  • The extended delay in offering possession of the plot, measured against the contractual timeline.
  • The fact that the respondent had levied interest at 18% per annum on the appellant for delayed payments, under clause 12 of the AGREEMENT.
  • The appellant’s decade-long wait and the attendant harassment and anxiety, which the Court considered “writ large” on the record.

Given this, the Court found that the NCDRC’s award of refund with 9% per annum interest would not serve the ends of justice. It reasoned that the respondent could not be permitted to escape with a merely nominal financial consequence for its own default—especially when it had contractually imposed a high rate of 18% per annum on the appellant for any default in payment.

While carefully noting that the builder’s contractual rate for buyer’s default cannot be mechanically applied to the buyer in all cases as a “rule of thumb”, the Court held that, in the specific circumstances of this case, equity and fairness demanded parity. To hold otherwise would, in its view, perpetuate a “manifestly wrong bargain” in which the builder enjoyed a punitive interest regime against the buyer but faced only mild consequences for its own significant default.

Consequently, the Court concluded that the interest rate must be enhanced from 9% to 18% per annum on the principal amount to be refunded, with all other terms of the NCDRC’s order left undisturbed.

Holding and Implications

Holding: The Supreme Court partly allowed the appeal. It:

  • Substituted the rate of interest awarded by the NCDRC, increasing it from 9% per annum to 18% per annum on the principal amount of Rs. 43,13,212/- to be refunded to the appellant.
  • Directed that all other terms of the NCDRC’s order, including the direction to refund the principal amount and the award of litigation costs of Rs. 25,000/-, would remain intact.
  • Ordered the respondent to refund the requisite amount (principal plus interest at 18% per annum from the dates of payment until refund) within two months from the date of the Supreme Court’s judgment.
  • Made no order as to costs in the appeal.

In summary, the core ruling is that the NCDRC’s direction of refund with 9% interest is modified so that the refund carries 18% per annum interest, reflecting the same rate that the respondent had contractually imposed on the appellant for payment defaults.

Implications: The immediate consequence for the parties is that the appellant will receive a significantly enhanced amount towards interest on the principal he had paid, while the respondent faces a substantially higher financial liability than under the NCDRC’s order, with a fixed two-month timeline for compliance.

At the level of legal principle, the judgment clarifies several points based on the text of the opinion:

  • There is no absolute legal rule that a buyer can never be awarded the same rate of interest that the builder is entitled to charge the buyer for delay. Whether such parity is appropriate depends on the facts and the demands of equity and fairness.
  • The proper interest rate in consumer disputes remains a question of reasonableness, to be determined case by case, taking into account factors such as contractual provisions, market realities, and the conduct of the parties (including delays and one-sided clauses).
  • Even while acknowledging that compensation under Section 14 of the Consumer Protection Act must correspond to actual loss or injury, courts may still adjust interest rates on refunds to ensure that the outcome is not nominal or unjust in light of prolonged delay and asymmetric contractual terms.
  • The judgment underscores that a builder who has imposed a punitive contractual interest rate on a buyer cannot necessarily expect to bear only a relatively low interest burden for comparable or greater delays on its own part, particularly when such an outcome would perpetuate a “manifestly wrong bargain”.

The opinion primarily adjusts relief in the particular factual matrix before the Court. While it offers general guidance on the possibility of parity and the need for reasonable interest, it does not purport to fix any universal rate or formula for all housing or consumer disputes.

Show all summary ...

2025 INSC 1149

1

NON-REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 3988 OF 2023

RAJNESH SHARMA … APPELLANT

VS.

M/S. BUSINESS PARK TOWN PLANNERS LTD. … RESPONDENT

J U D G M E N T

DIPANKAR DATTA, J.

THE APPEAL

1. This appeal assails an order dated 13thJanuary, 2023, passed by the National Consumer Disputes Redressal Commission, New Delhi1 disposing of a consumer complaint lodged before it by the appellant.

FACTS

2. Facts in brief, necessary for the disposal of the present appeal, are as follows:

a. On 10thMarch, 2006, the appellant booked a plot2in a project of the respondent named Park Land for a total sale consideration of Rs. 36,03,692/- (basic price - Rs. 30,87,000/-). As

1 NCDRC

2 Plot bearing no. 2 , Block G-4, Phase -2 admeasuring 343 square yards

1

2

advance/registration charges, Rs. 7,86,218/- was paid on the same day.

b. On 11thDecember, 2007, a plot buyer agreement3was executed between the parties.

c. As per clause 22 of the AGREEMENT, the possession of the plot was to be handed over within 24 months of sanction of service plans of the entire colony. Furthermore, clause 12 provided that time is of the essence, and in case of default by the buyer, late payment charges at 18% p.a. on the due amount, compounded at the time of every succeeding instalment or three months, whichever is earlier, would be levied by the respondent.

d. By April, 2011, the appellant had paid a sum of Rs. 28,79,065/-. On 13thApril, 2011, more than 5 (five) years after the first payment, the respondent informed the appellant that due to changes in the layout plan, it had decided to allot an alternative plot to the appellant. Since the new plot was 7 sq. yards larger than the original plot, the respondent further demanded a sum of Rs. 2,30,784/- as an additional amount. Accordingly, an addendum to the AGREEMENT was executed between the parties on 13thApril, 2011. Clause 7 of the AGREEMENT (discussed in the latter part of the judgment) provided for allotment of an alternative plot if a change in layout plan was required by any statutory authority.

3 AGREEMENT

3

e. The appellant on 11thMarch, 2015, paid a sum of Rs. 83,377.67, out of which Rs. 83,300.76 was towards interest @ 18% p.a. charged by the respondent for the appellant's default in making the payments.

f. As per the statement of accounts dated 23rdMarch, 2015 prepared by the respondent, the appellant had paid a sum total of Rs. 43,13,312.67/-.

g. Aggrieved by the respondent's inaction in allotting the plot, the appellant terminated the AGREEMENT with the respondent vide letter dated 27thMarch, 2017.

h. Thereafter, on 27thMarch, 2017, the appellant issued a legal notice informing the respondent about such termination and seeking a refund of Rs. 43,13,212/- along with 24% interest p.a. and a sum of Rs. 72,30,000/- on account of loss of appreciation of property.

i. Ultimately, in April 2018, the appellant lodged the consumer complaint4before the NCDRC referred to in the opening paragraph. j. After the lodging of the complaint, the respondent offered the possession of the plot on 8thMay, 2018, subject to payment of a further amount of Rs. 7,60,900.33/-.

k. Vide the impugned order, the consumer complaint was disposed of with directions to the respondent to refund the entire principal amount of Rs. 43,13,212/- along with simple interest @ 9% p.a.

4 Consumer Case No. 885 of 2018

4

from the date of each payment till the date of refund. Additionally, Rs. 25,000/- was awarded towards litigation costs to the appellant. l. The said order is under challenge before this Court in this appeal at the instance of the partly successful complainant.

IMPUGNED ORDER

3. During the course of hearing before the NCDRC, learned counsel for the respondent offered to repay the principal amount with 9% simple interest per annum. This weighed with the NCDRC, and it ordered accordingly without going into the merits of the case. It is imperative to mention that the impugned order nowhere records that the appellant accepted such an offer. Rather, the NCDRC disposed of the matter merely based on the offer made by the counsel for the respondent.

SUBMISSIONS ON BEHALF OF THE APPELLANT

4. It was submitted by Mr. Vivek Malik, learned counsel appearing for the appellant, that the impugned order is liable to be set aside for more than one reason. Inter alia, it was urged that:

4.1 The NCDRC erred in forcing upon the appellant refund of the principal amount paid by him with a meagre simple interest of 9% p.a.

4.2 The appellant paid a total sum of Rs. 43,13,313/-, in instalments, as and when demands were raised by the respondent. Despite booking the plot in the year 2006, the possession thereof was not

5

delivered until 2018. In such view of the facts, interest @ 9% p.a. was insufficient causing huge loss to the appellant.

4.3 Various additional costs were wrongly charged by the respondent, because of which the appellant ended up paying Rs. 43,13,313/-, whereas the initial sale consideration was Rs. 36,03,692/-. First, after allotting an alternative plot in 2011, the respondent demanded a sum of Rs. 2,30,784/-, whereas since the alternative plot was larger by only 7 sq. yards, the correct amount should have been Rs. 73,283/- [Rs. 9,000 (basic rate) x 7 + Rs. 1024 (EDC) x 7 + Rs. 445 (IDC) x 7]. Secondly, the developer charged Rs. 4,81,600/- under the head "Enhanced EDC", which is over and above the EDC5and IDC6specified in the AGREEMENT. Thirdly, on 11thMarch, 2015, four years after the last payment was made in the year 2011, the respondent demanded a sum of Rs. 83,300.67/- towards "interest" on delayed payment without giving any details as to how such an amount was arrived at. The appellant paid the amounts, as demanded, as he did not want to be embroiled in a dispute with the respondent.

4.4 After filing the consumer complaint, the respondent offered possession of the plot on 8thMay, 2018, but demanded a further sum of Rs. 7,60,900.33/- [interest of Rs. 83,302/-, electricity and STP charges of Rs. 3,13,250/-, utility connect charges of Rs.

5 External Development Charges

6 Infrastructure Development Charges

6

15,000, GST of Rs. 59,086/-, previous dues of Rs. 70,262.33/- and stamp duty charges of Rs. 2,20,000]. After inviting our attention to the payment plan contained in Schedule I (Schedule of Costs) to the AGREEMENT, which contains details of all the charges payable by the buyer, it was submitted that electricity and STP charges do not find mention in the table and hence could not have been demanded. Furthermore, the respondent sought to charge GST, which was introduced in the year 2017, whereas all the payments were made prior to 2012.

4.5 Preferential location charges (PLC) of Rs. 75,000/-, payable as per Schedule I to the AGREEMENT, was paid by the appellant. However, the respondent, in the offer letter dated 8thMay, 2018, sought to charge a sum of Rs. 3,15,000/-, which is unexplained.

4.6 Even after the passing of the impugned order, when the respondent did not make payments within the timeline prescribed by the NCDRC, the appellant (through his power of attorney) approached the respondent for compliance with the impugned order; however, the respondent refused to give money, questioning the authenticity of the power of attorney.

4.7 Thus, the conduct of the respondent has been full of blemishes throughout.

4.8 Finally, the respondent charged the appellant interest @ 18% p.a. whereas agreed to give back to the appellant the principal amount with 9% interest, which is in defiance of logic and reason.

7

Respondent, for its default, should have been judged by the same standard and made to pay back 18% interest.

SUBMISSIONS ON BEHALF OF THE RESPONDENT

5. Per contra, learned senior counsel for the respondent Mr. Nayyar with considerable vehemence supported the impugned order and made fourfold submissions:

5.1 First, it was submitted that for grant of relief under the Consumer Protection Act, 19867, it is imperative for the consumer to prove actual loss or injury to him due to neglect of the other party. Reference was made to section 14 of the Act, which reads thus:

14. Finding of the District Forum.-

(l) If, after the proceeding conducted under section 13, the District Forum is satisfied that the goods complained against suffer from any of the defects specified in the complaint or that any of the allegations contained in the complaint about the services are proved, it shall issue an order to the opposite party directing him to do one or more of the following things, namely:-

(a) …;

(b) …;

(c) …;

(d) to pay such amount as may be awarded by it as compensation to the consumer for any loss or injury suffered by the consumer

due to the negligence of the opposite party; ***

(emphasis supplied by counsel)

Therefore, evidence must be led to prove actual loss suffered by the consumer before the grant of compensation. Grant of compensation cannot be beyond actual loss and cannot venture into the territory of gain-based remedies. In the present case, while the respondent's claim for charging interest @ 18% on

7 the Act

8

default is supported by the AGREEMENT, the appellant's claim for grant of interest @ 18% cannot be sustained, as he did not lead evidence to prove actual loss. In support of this proposition, reliance was placed on the judgment of this Court in Ghaziabad Development Authority v. Balbir Singh8and Fortune Infrastructure v. Trevor D'Lima9.

5.2 Secondly, a consumer cannot, as a matter of routine, be awarded compensation at the rate charged by the builder under the contract. This Court has consistently granted a 9% interest rate to the consumers for deficiency in services.

5.3 Thirdly, this Court has consistently rejected the claims of consumers who claimed parity with builders in the interest charged on delayed payments. Reliance was placed upon the judgment of this court in IREO Grace Realtech (P) Ltd. v. Abhishek Khanna10where this Court held:

51. We have considered the rival submissions made by both the parties. The delay compensation specified in the apartment buyer's Agreement of Rs 7.5 per square foot which translates to 0.9% to 1% p.a. on the amount deposited by the apartment buyer cannot be accepted as being adequate compensation for the delay in the construction of the project. At the same time, we cannot accept the claim of the apartment buyers for payment of compound interest @ 20% p.a., which has no nexus with the commercial realities of the prevailing market. We have also taken into consideration that in IREO Grace Realtech (P) Ltd. v. Subodh Pawar [IREO Grace Realtech (P) Ltd. v. Subodh Pawar, 2019 SCC OnLine SC 1937] , this Court recorded the statement of the counsel for the developer that the amount would be refunded with interest @ 10% p.a. A similar order was passed in IREO Grace Realtech (P) Ltd. v. Surendra Arora [IREO Grace Realtech (P) Ltd. v. Surendra Arora, 2019 SCC OnLine SC

8 2004 5 SCC 65, para 8

9 2018 5 SCC 442, paras 19 and 25

10 (2021) 3 SCC 241

9

1943] . However, the order in these cases were passed prior to the outbreak of the pandemic.

(emphasis supplied by the counsel)

Similarly, in Vidya v. Parsvnath Developers Ltd.11, this Court held:

19. Shri Jain therefore submitted that, applying the principle of parity, the learned Commission ought to have awarded the interest @ 24% p.a. It is submitted that, in any case the interest at the rate of only 9% p.a. is not sustainable in law.

******

22. However, we find that, insofar as award of interest @ 9% p.a. is concerned, the learned Commission was not justified in the facts of the case to award a lesser interest than even the one agreed upon in the agreement. Undisputedly, the facts of the case show that the project was delayed inordinately. The appellant complainants were made to suffer for long, for no fault of them. In spite of making the entire payment, they were deprived of the possession within the stipulated time.

23. In our view, the learned Commission, at least, ought to have awarded interest @ 12% p.a. in view of Clause 7(b) of the agreement.

24. In the result, the appeal is partly allowed. The direction made by the learned Commission for refund of the entire amount deposited by the appellant complainants is upheld. However, the direction with regard to interest is modified to the extent that it shall be paid @ 12% p.a. from the date of respective deposit till the date of refund. The unpaid amount in terms of the aforesaid shall be paid within a period of three months from the date of this judgment [Vidya v. Parsvnath Developers Ltd., 2022 SCC OnLine NCDRC 522]. In Kolkata West International City Pvt. Ltd. v. Devasis Rudra12, the builder-buyer agreement imposed an interest rate of 18% on the buyer for its delay in making payments, while the interest rate imposed on the developer was the equivalent of the prevailing savings bank interest of SBI. This Court found

11 (2024) 9 SCC 651

12 (2020) 18 SCC 613

10

the said agreement to be one-sided and modified the NCDRC's order by reducing the interest rate from 12% p.a. to 9% p.a. The relevant passage is reproduced below:

7. It is the above clause which is pressed in aid by the developer. Under the aforesaid clause, any delay beyond 30-6-2009 would result in the developer being required to pay interest at the prevailing savings bank interest of State Bank of India. Interestingly, where the buyer is in default, the agreement stipulates that interest @ 18% from the date of default until the date of payment would be charged for a period of two months, failing which the allotment would be cancelled by deducting 5% of the entire value of the property. The agreement was evidently one-sided. For a default on the part of the buyer, interest @ 18% was liable to be charged. However, a default on the part of the developer in handing over possession would make him liable to pay interest only at the savings bank rate prescribed by SBI. There is merit in the submission which has been urged by the buyer that the agreement was one-sided. The clause which has been extracted in the earlier part of this order will not preclude the right and remedy available to the buyer to claim reasonable interest or, as the case may be, compensation.

******

10. Having regard to all the facts and circumstances of the case, we modify the order [Kolkata West International City (P) Ltd. v. Devasis Rudra, 2016 SCC OnLine Ncdrc 2411] of NCDRC by directing that the appellant shall pay interest @ 9% p.a. to the respondent instead and in place of 12% as directed by NCDRC. Save and except for the above modification, we affirm the directions of NCDRC. Similarly, in Pioneer Urban Land and Infrastructure Ltd. v. Govindan Raghavan13, this Court upheld an order of the NCDRC which awarded simple interest of 10.7% even though, as per the agreement, the builder was entitled to charge 18% on delay in payments by the buyer.

13 (2019) 5 SCC 725

11

5.4 Fourthly, if the builder-buyer agreement is found to be one- sided, it cannot be enforced, even at the instance of the buyer.

5.5 Lastly, the appellant's allegation of demand of excessive amount is unsustainable because: (i) the PLC was increased on account of allotment of an alternative plot which was on a wider road and had potential of commercial usage; (ii) the interest amount of Rs. 83,300/- was charged on account of delayed payment by the appellant for the period of 2007-2011, and no further interest was charged; (iii) the electrification and STP charges were payable in terms of clause 2.5 (b) and 2.5 (c) of the AGREEMENT; and (iv) GST was charged only for the eligible charges levied for the first time on 8thMay 2018 (letter of offer of possession).

ISSUE

6. Whether on facts and in the circumstances of the present case, viz. the terms of the agreement, the delay in offering possession, the conduct of the respondent and the interest rate charged by the respondent for default in payment by the appellant, the NCDRC erred in awarding delay compensation @ 9% p.a. instead of a higher rate?

ANALYSIS

7. We start by analyzing the arguments raised by the respondent.

8. It was argued that this Court has consistently rejected the claim of parity raised by buyers. Various judgments of this Court, which were cited, have been noted. On perusal thereof, we find that in all such cases this

12

Court did not give elaborate reasons for rejecting the claim for parity but reduced/increased the rate of interest based on other factors peculiar to the facts and circumstances of each case, such as the prevailing market conditions, lockdown due to COVID, et cetera.

9. To discuss a few, in IREO Grace Realtech Pvt. Ltd. (supra), this Court did not consider the issue as to whether the buyer can claim parity with the builder in interest rate for default. The buyer claimed interest @ 20% p.a.; however, this Court denied the same finding it to be excessive as per the prevailing commercial realities. Similarly in Vidya (supra), this Court granted an interest rate of 12%, not by applying the principle of parity but after finding that the grant of an interest rate of 9% by the NCDRC, even when the agreement provided for a grant of interest of 12%, was very low.

10. Therefore, it cannot be said that this Court has always rejected the claim of parity.

11. Suffice it to say, there is no principle of law that interest in default charged by the builder can never be granted to the buyer.

12. Law is well settled that the amount of interest should be reasonable. What is reasonable varies from case to case. The same is to be granted considering the facts and circumstances of each case. The series of judgments cited by the respondent to buttress its argument that this Court has consistently granted interest @ 9% p.a. will make no difference to the decision in this lis, as all the said cases were decided in light of the peculiar facts of each case.

13

13. We now proceed to determine if the grant of interest awarded by the NCDRC was reasonable considering the facts and circumstances of the present case.

14. As per clause 22 of the AGREEMENT, possession of the plot was to be handed over within 24 months of sanction of service plans of the entire colony. Admittedly, no offer for possession was made until the year 2018. The conduct of the respondent in the interregnum is also worthy of a discussion.

15. In April, 2011, the respondent invoked clause 7 of the AGREEMENT, and allotted an alternative plot to the appellant. The reason cited for such allotment was "due to changes in the layout plan". Clause 7 of the AGREEMENT reads as follows:

The Seller/Confirming Party is in the process of developing Parklands in accordance with tentative and consolidated layout plan for the entire colony, as submitted to the Statutory /Competent Authority for final approval, which have been explained to and understood by the Purchaser(s). However, if any changes in the said layout plan and/or drawings are required by any statutory authority(s) of Govt., Or otherwise, the same may be effected suitably, to which the Purchaser(s) hereby agrees and has given his consent to the Seller to carry out the same.

Provided, however, if as a result thereof, there by any change in the location, preferential location, number, boundaries or area of the said Plot, the same shall be valid and binding on the Purchaser(s). Further, if there is any increase or decrease in the area of the said Plot, revised price shall proportionally be determined by the Seller/Confirming Party on the basis of the original price.

If any preferentially located Plot, ceases to be so located, the Seller/Confirming Party will be liable only to refund without interest such extra charges paid by the Purchaser(s), for such preferential location. The Purchaser shall not raise any objection and shall have no claim monetary or otherwise of any nature whatsoever in this regard.

16. Clause 7 provides that the location of the plot may be changed if the government or any statutory authority requires a change in the existing layout plan. During arguments, we enquired of Mr. Nayyar for the

14

respondent to show the basis for invoking clause 7 of the AGREEMENT, i.e., to show us that the layout plan was sought to be changed by the government or statutory authority. In answer thereto, it was submitted that the alternative allotment was made in the year 2011; however, till 2018, the appellant raised no demur as regards the same. The answer is neither here nor there. Whether or not the appellant raised a demur is not relevant for validation of the respondent's conduct. Also, the basis for offering such alternative allotment has not been disclosed in the written submissions filed by the respondent.

17. Be that as it may, the possession of the alternative plot (allotted in the year 2011) was offered only in the year 2018.

18. Having noted thus, we agree with Mr. Nayyar that before compensation can be granted by the NCDRC, actual loss must be proved to have been suffered by the consumer. The objective of granting compensation cannot be altered such that it amounts to a windfall gain to the other party. Proof of actual loss would require evidence to be tendered, for, it is a guiding lamp for grant of compensation. Be that as it may, in this case, we are not deciding the actual loss suffered by the appellant. We are only concerned with deciding the rate of interest to be awarded to the appellant on the principal amount paid by him to the respondent.

19. Keeping in mind the overall conduct of the respondent: the delay caused by it in offering the plot, the fact that the respondent charged the appellant delay compensation @ 18% p.a. on the due amount, and the long wait that the appellant had to endure over a period of a decade,

15

causing harassment and anxiety, which are writ large, we find that this is an appropriate case where refund of the principal amount with interest @ 9% p.a., as awarded by the NCDRC, will not serve the ends of justice.

20. In view of the conduct of the respondent, it cannot be permitted to escape with a nominal liability for its default, while it charged interest @ 18% on default committed by the appellant. Although, the rate of interest charged by the builder cannot be granted to the buyer as a rule of thumb, however, in the present case, equity and fairness demands that the respondent be put to the same rigours for charging 18% interest and face consequences similar to those imposed on the appellant for default committed by him. If we hold otherwise, we will be perpetuating a manifestly wrong bargain.

21. We, therefore, substitute the rate of interest awarded by the NCDRC and increase it from 9% to 18% per annum, while keeping the other terms intact. Respondent shall refund the requisite amount within a period of two months from date.

22. The appeal is, accordingly, partly allowed, without any order for costs.

………..…………………J.

(DIPANKAR DATTA)

…………..…………..………………J.

(AUGUSTINE GEORGE MASIH)

NEW DELHI;

SEPTEMBER 24, 2025.