- Bookmark
- Share
- CaseIQ
Union Of India v. Ambica Construction .
Factual and Procedural Background
The case arises from a construction contract awarded to M/s Ambica Construction on 8 September 1989 for fabrication of tie bars. A final agreement was executed on 30 November 1989 and the work was completed on 21 November 1990. Disputes regarding payment led the contractor to seek arbitration. Although the contractor executed a “full and final” settlement on 5 March 1991 due to financial hardship, an arbitrator was never appointed. Consequently, an application under Section 20 of the Arbitration Act, 1940 (“the Act”) was filed before the Calcutta High Court. Two joint arbitrators were first appointed (2 June 1992) but failed to publish an award; their mandate was revoked and a sole arbitrator eventually issued an award on 30 December 1997.
On Union of India’s application the High Court remitted the award for item-wise break-up, leading to a revised award on 12 May 1998. The High Court then set aside the award for lack of intelligibility and for ignoring a supplementary agreement dated 5 March 1991. The Division Bench affirmed this decision, but the Supreme Court (Civil Appeal 6621/2005, order dated 7-11-2005) remitted the matter to the arbitrator for a reasoned fresh award, which was delivered on 11 February 2006.
The Union of India again challenged the award under Sections 30 and 33 of the Act. After several orders, a Single Judge (22-8-2007) set aside the award regarding pre-reference interest and limited interest to 10 % p.a. from 1-9-1992 on the principal sum. The Division Bench partly allowed appeals in 2008. Both parties filed special-leave petitions (SLP 17219/2009 by the contractor; SLP 11114/2009 by the Union). A Division Bench of the Supreme Court doubted earlier two-Judge decisions on pendente lite interest and referred the question to a larger Bench, resulting in the present reference.
Legal Issues Presented
- Whether, under the Arbitration Act, 1940, an arbitrator has power to award pendente lite interest when the contract expressly bars payment of interest.
- Whether the earlier decisions in Port of Calcutta v. Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani Construction Corpn. (P) Ltd. v. Union of India (2010) 1 SCC 549 were correctly decided on this point.
Arguments of the Parties
Union of India’s Arguments
- The arbitrator is bound by the contractual terms; where the contract bars interest, no pendente lite interest can be awarded.
- The earlier two-Judge Bench rulings permitting such interest irrespective of a contractual bar were erroneous.
Contractor (M/s Ambica Construction)’s Arguments
- Relying on Engineers-De-Space-Age and Madnani, the contractor contended that the contractual bar applies only to pre-reference interest and does not prevent the arbitrator awarding pendente lite interest.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Irrigation Deptt., State of Orissa v. G.C Roy (1992) 1 SCC 508 (Constitution Bench) | Arbitrator may award interest (pre-reference, pendente lite, future) unless the contract expressly prohibits it. | Treated as the governing principle; reaffirmed that an express contractual bar removes arbitrator’s power. |
| Dhenkanal Minor Irrigation Division v. N.C Budharaj (2001) 2 SCC 721 (Constitution Bench) | Arbitrator’s jurisdiction to award pre-reference interest where not excluded by contract. | Relied on to underscore that contractual exclusion controls. |
| Port of Calcutta v. Engineers-De-Space-Age (1996) 1 SCC 516 | Had held that a bar on the employer did not bar the arbitrator from granting pendente lite interest. | Its correctness doubted; confined only to clauses similar to that case. |
| Madnani Construction Corpn. (P) Ltd. v. Union of India (2010) 1 SCC 549 | Followed Engineers-De-Space-Age on arbitrator’s power. | Diluted; subject to express contractual bar. |
| Sayeed Ahmed & Co. v. State of U.P. (2009) 12 SCC 26 | Emphasised that an absolute contractual bar prevents award of interest. | Used to question the broad view in Engineers-De-Space-Age. |
| Sree Kamatchi Amman Constructions v. Railways (2010) 8 SCC 767 | Under 1996 Act, arbitrator bound by “unless otherwise agreed” clause. | Cited for principle that contract prevails. |
| Hindustan Construction Co. Ltd. v. State of J&K (1992) 4 SCC 217 | Arbitrator can award pendente lite/post-award interest absent bar. | Read consistently with G.C Roy; not contrary to present conclusion. |
| Deptt. of Irrigation v. Abhaduta Jena (1988) 1 SCC 418 | Earlier restrictive view on interest. | Noted as overruled prospectively regarding pre-reference interest. |
| State of Orissa v. B.N Agarwalla (1997) 2 SCC 469 | Arbitrator’s power depends on contract; no bar in that case. | Explained/distinguished; supports principle that wording of clause is decisive. |
| State of U.P. v. Harish Chandra & Co. (1999) 1 SCC 63 | Clause barring interest limited to retention money. | Distinguished; shows need to analyse exact wording. |
| Supt. Engineer v. B. Subba Reddy (1999) 4 SCC 423 | Pre-reference interest requires agreement/Interest Act; arbitrator may grant pendente lite. | Cited in support of differential treatment of periods. |
| State of Rajasthan v. Ferro Concrete Construction (P) Ltd. (2009) 12 SCC 1 | Summarised principles on contractual provision for, or bar to, interest. | Adopted for analytical framework. |
| Union of India v. Bright Power Projects (India) (P) Ltd. (2015) 9 SCC 695 | Section 31(7)(a) of 1996 Act: arbitrator cannot award interest if parties have agreed otherwise. | Referenced to show continued primacy of contract under new Act. |
| Union of India v. Krafters Engg. & Leasing (P) Ltd. (2011) 7 SCC 279 | Agreement may exclude arbitrator’s jurisdiction to grant interest. | Relied on to reinforce contractual primacy. |
| Tehri Hydro Development Corpn. Ltd. v. Jai Prakash Associates Ltd. (2012) 12 SCC 10 | Clauses 1.2.14 & 1.2.15 barred pendente lite interest. | Used as precedent showing that explicit bar prevails. |
| Asian Techs Ltd. v. Union of India (2009) 10 SCC 354 | Considered scope of contractual bar. | Cited to illustrate discordance with Engineers-De-Space-Age. |
| Additional earlier Supreme Court decisions (Raipur Development Authority; Nachiappa Chettiar; Satinder Singh; Madanlal Roshanlal; Bungo Steel Furniture; Saith & Skelton; Gujarat Water Supply; Seth Thawardas Pherumal; Ashok Construction) | General historical development of arbitrator’s power to award interest. | Referenced in historical survey; not determinative of the holding. |
Court's Reasoning and Analysis
The Court began by examining Section 3 of the 1940 Act, which imports the First Schedule into every arbitration agreement unless expressly excluded, and observed that an arbitrator, unlike a court, derives power strictly from the agreement. Section 29 of the Act authorises only the court (not the arbitrator) to award post-decree interest, while Section 34 CPC governs a court’s power over pre-suit and pendente lite interest.
Reviewing the Constitution Bench authorities (G.C Roy and N.C Budharaj), the Court reiterated that:
- If the contract permits interest, the arbitrator may grant it.
- If the contract expressly prohibits interest for the relevant period, the arbitrator lacks jurisdiction to award it.
- Where the contract is silent, interest is an “implied term,” and the arbitrator has discretion to award it.
The Court then scrutinised the two-Judge Bench rulings in Engineers-De-Space-Age and Madnani, recognising that they allowed arbitrators to ignore a contractual bar because the clause there only restrained the department, not the arbitrator. Later decisions (Sayeed Ahmed, Sree Kamatchi Amman, Krafters Engg., Tehri Hydro) had criticised or confined that view.
After analysing numerous contract clauses from earlier cases, the Court concluded that whether a bar on interest applies to an arbitrator depends on the exact language and context of the clause. A clause that unequivocally excludes interest “for any reason whatsoever” or “in respect of any money payable” disables an arbitrator from granting pendente lite interest. Conversely, a clause confined to retention money or to departmental officers may not oust the arbitrator’s power.
Accordingly, the broad proposition in Engineers-De-Space-Age/Madnani was “diluted”: an arbitrator cannot award pendente lite interest in the face of an express contractual prohibition.
Holding and Implications
HOLDING: If the contract expressly bars the award of pendente lite interest, an arbitrator appointed under the Arbitration Act, 1940 has no jurisdiction to grant such interest.
Implications: The decision restores doctrinal consistency by aligning two-Judge Bench precedents with Constitution Bench rulings. It clarifies that contractual autonomy prevails over arbitral discretion regarding interest, and earlier contrary observations in Engineers-De-Space-Age and Madnani stand curtailed. The specific disputes between Ambica Construction and the Union of India are remitted to the Division Bench for decision on the merits in light of this legal standard; no new substantive rights are created beyond this clarification.
Arun Mishra, J.— The issue involved in the reference is in regard to the power of the arbitrator to award pendente lite interest when contract contains bar for grant of interest in a case covered by the Arbitration Act, 1940 (hereinafter referred to as “the Act”). A Division Bench of this Court had doubted SLP (C) No. 11114 of 2009, order dated 22-9-2010 (SC) the correctness of the decisions in Port of Calcutta v. Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani Construction Corpn. (P) Ltd. v. Union of India (2010) 1 SCC 549 , (2010) 1 SCC (Civ) 168. In view of the decisions of the Constitution Bench judgments in Irrigation Deptt., State of Orissa v. G.C Roy Irrigation Deptt., (1992) 1 SCC 508 and Dhenkanal Minor Irrigation Division v. N.C Budharaj (2001) 2 SCC 721 which held that the arbitrator had the jurisdiction and authority to award interest for pre-reference period, pendente lite and future period if there was no express bar in the contract regarding award of interest. A doubt was expressed about the correctness of the decisions in Engineers-De-Space-Age (1996) 1 SCC 516 in Sayeed Ahmed & Co. v. State of U.P (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629 and Sree Kamatchi Amman Constructions v. Railways (2010) 8 SCC 767 , (2010) 3 SCC (Civ) 575. Hence, the matter had been referred to a larger Bench for decision.
2. The case has a chequered history. The tender of M/s Ambica Construction for fabrication of tie bars from M.S Flats in CST-9 sleepers was accepted on 8-9-1989. Final agreement was executed on 30-11-1989. The work was completed on 21-11-1990. With respect to payments, certain differences and disputes arose between the parties. Thus, M/s Ambica Construction prayed for appointment of an arbitrator. On 5-3-1991, as the petitioner M/s Ambica Construction was in serious financial difficulties, it accepted the amount in full and final settlement. Later on, the Union of India informed the petitioner on 11-3-1991 that the matter was under consideration. However, the arbitrator was not appointed.
3. An application under Section 20 of the Act was filed before the High Court of Calcutta for referring the case to arbitration. On 2-6-1992, the High Court directed to file the arbitration agreement in court and appointed two arbitrators in terms of the arbitration clause. The said arbitrators failed to publish the award and as such an application was filed for revocation of the authority of joint arbitrators and another sole arbitrator was appointed. The sole arbitrator ultimately published the award on 30-12-1997.
4. On an application filed by the Union of India, the High Court vide order dated 9-4-1998 Award Case No. 9 of 1998, order dated 9-4-1998 (Cal) remitted the award to the arbitrator to give an item-wise break-up. On 12-5-1998, the sole arbitrator published the item-wise award. Again the Union of India questioned the same before the High Court. The award was set aside on the ground that the arbitrator had not given an intelligible award in terms of Clause 64(3)(a)(iii) of the agreement and had not taken into effect the supplementary agreement dated 5-3-1991. The appeal preferred by the petitioner was dismissed by the Division Bench of the High Court on 15-10-2004 APO No. 255 of 2001, order dated 15-10-2004 (Cal) against which an SLP was filed in which leave was granted and ultimately CA No. 6621 of 2005 was allowed and the case was remitted vide order dated 7-11-2005 Civil Appeal No. 6621 of 2005, order dated 7-11-2005 (SC) passed by this Court to the arbitrator for assigning reasons and to pass fresh award.
5. Thereafter, the arbitrator passed a fresh award on 11-2-2006. Again an application was filed by the Union of India under Sections 30 and 33 of the Act. The Single Judge dismissed the application vide order dated 26-6-2007. The Union of India filed an application for recall. The order dated 26-6-2007 was recalled. Vide order dated 22-8-2007 2007 SCC OnLine Cal 495 , (2007) 3 Cal LT 587 the learned Single Judge set aside the award with regard to interest for pre-reference period and directed that interest would be allowed on the principal sum of Rs 9,82,660 @ 10% p.a from 1-9-1992, the date from which the original arbitrator entered upon the reference. An appeal was preferred before the Division Bench and the same had been partly allowed 2008 SCC OnLine Cal 236 , (2008) 2 CHN 949 with regard to Claims 6 and 7. Aggrieved thereby, M/s Ambica Construction had preferred SLP (C) No. 17219 of 2009 in this Court and the Union of India has also assailed the judgment and order of the High Court in SLP (C) No. 11114 of 2009.
6. The only question for consideration is whether an arbitrator has the power to award pendente lite interest in case contract bars the same in a case covered by the Act and decisions of this Court in Engineers De-Space-Age (1996) 1 SCC 516 and Madnani Construction Corpn. (P) Ltd. (2010) 1 SCC 549 , (2010) 1 SCC (Civ) 168 have been correctly decided?
7. It was submitted on behalf of the Union of India that the arbitrator is bound by the terms of the contract and cannot award interest in case the contract bars the same. On the other hand, the learned counsel appearing on behalf of M/s Ambica Construction has contended that in view of the decision in Engineers-De-Space-Age (1996) 1 SCC 516 followed in Madnani Construction Corpn. (P) Ltd. (2010) 1 SCC 549 , (2010) 1 SCC (Civ) 168 notwithstanding the terms in the contract agreement barring the award of interest would cover the pre-reference period and not pendente lite interest.
8. There are certain provisions which are statutorily implied in the arbitration agreement unless excluded in the agreement. Section 3 of the 1940 Act deals with the provisions which are implied in the arbitration agreement. Section 3 is extracted below:
“3. Provisions implied in arbitration agreement.—An arbitration agreement, unless a different intention is expressed therein, shall be deemed to include the provisions set out in the First Schedule insofar as they are applicable to the reference.”
9. The provisions of Section 3 make it clear that unless a different intention is expressed in the arbitration agreement, the agreement would include the provisions contained in the First Schedule so far as they are applicable to the reference. The provisions in the First Schedule contain eight paragraphs. It provides for reference to a sole arbitrator and in case there are even numbers of arbitrators, appointment of umpire is also provided. An arbitrator is required to pass award within 4 months from the date of entering on the reference. In case the arbitrator fails to pass an award within the specified time the umpire shall make the award within 2 months. Para 6 of the First Schedule provides that the arbitrator or umpire shall examine the matters in difference and the award shall be final and binding. The arbitrator or umpire has the power for examining the witnesses and production of relevant documents. Para 8 of Schedule I provides for costs of reference and awards shall be in the discretion of the arbitrator.
10. The “court” has been defined in Section 2(c) of the Act to mean a civil court having jurisdiction to decide the questions forming the subject-matter of the reference. Section 41 of the Act is extracted hereunder:
“41. Procedure and powers of court.—Subject to the provisions of this Act and of rules made thereunder:
(a) the provisions of the Code of Civil Procedure, 1908 (5 of 1908), shall apply to all proceedings before the court, and to all appeals, under this Act; and
(b) the court shall have, for the purpose of, and in relation to, arbitration proceedings, the same power of making orders in respect of any of the matters set out in the Second Schedule as it has for the purpose of, and in relation to, any proceedings before the court:
Provided that nothing in clause (b) shall be taken to prejudice any power which may be vested in an arbitrator or umpire for making orders with respect to any of such matters.”
The court can exercise the power specified in the Second Schedule to the Act. However, the arbitrator is not a court. The arbitrator is the outcome of agreement. He decides the disputes as per the agreement entered into between the parties. Arbitration is an alternative forum for resolution of disputes but an arbitrator ipso facto does not enjoy or possess all the powers conferred on the courts of law.
11. Section 29 of the Act confers on the court power to award interest from the date of decree. Section 34 CPC confers on the court power to award interest prior to the institution of the suit and during pendency of the suit and post-decree.
12. A Constitution Bench of this Court in G.C Roy Irrigation Deptt., (1992) 1 SCC 508 has considered the question of power of the arbitrator to award pendente lite interest and it has been laid down that if the arbitration agreement or the contract itself provides for interest, the arbitrator would have the jurisdiction to award the interest. Similarly, where the agreement expressly provides that no interest pendente lite shall be payable on the amount due, the arbitrator has no power to award pendente lite interest. In G.C Roy Irrigation Deptt., (1992) 1 SCC 508 this Court has held thus:
“7. … If the arbitration agreement or the contract itself provides for award of interest on the amount found due from one party to the other, no question regarding the absence of arbitrator's jurisdiction to award the interest could arise as in that case the arbitrator has power to award interest pendente lite as well. Similarly, where the agreement expressly provides that no interest pendente lite shall be payable on the amount due, the arbitrator has no power to award pendente lite interest. But where the agreement does not provide either for grant or denial of interest on the amount found due, the question arises whether in such an event the arbitrator has power and authority to grant pendente lite interest.”
13. The question involved in G.C Roy Irrigation Deptt., (1992) 1 SCC 508 was with respect to the award of interest for the period commencing from the date of the arbitrator entering upon the reference till the date of making the award. In G.C Roy Irrigation Deptt., (1992) 1 SCC 508, this Court has considered decisions in Raipur Development Authority v. Chokhamal Contractors (1989) 2 SCC 721; Deptt. of Irrigation v. Abhaduta Jena (1988) 1 SCC 418; Nachiappa Chettiar v. Subramaniam Chettiar AIR 1960 SC 307; Satinder Singh v. Umrao Singh AIR 1961 SC 908; Firm Madanlal Roshanlal Mahajan v. Hukumchand Mills Ltd. AIR 1967 SC 1030; Union of India v. Bungo Steel Furniture (P) Ltd. AIR 1967 SC 1032; Ashok Construction Co. v. Union of India (1971) 3 SCC 66; State of M.P v. Saith and Skelton (P) Ltd. (1972) 1 SCC 702, various foreign courts' decisions and decisions of the High Court. This Court has also referred to Halsbury's Laws of England in paras 36 and 37 thus: (G.C Roy case Irrigation Deptt., (1992) 1 SCC 508)
“36. … ‘534. Express and implied clauses.—In general, the parties to an arbitration agreement may include in it such clauses as they think fit. By statute, however, certain terms are implied in an arbitration agreement unless a contrary intention is expressed or implied therein. Moreover, it is normally an implied term of an arbitration agreement that the arbitrator must decide the dispute in accordance with the ordinary law. This includes the basic rules as to procedure, although parties can expressly or impliedly consent to depart from those rules. The normal principles on which terms are implied in an agreement have to be considered in the context that the agreement relates to an arbitration.’
37. At p. 303, Para 580 (4th Edn., Vol. 2) dealing with the award of interest, it reads:
‘580. Interest.—An arbitrator or umpire has power to award interest on the amount of any debt or damages for the whole or any part of the period between the date when the cause of action arose and the date of the award.’”
14. Ultimately, in G.C Roy Irrigation Deptt., (1992) 1 SCC 508, this Court has answered the question whether the arbitrator has the power to award interest pendente lite. Their Lordships have reiterated that they have dealt with the situation where the agreement does not provide for grant of such interest nor does it prohibit such grant when the agreement is silent as to award of interest. This Court has laid down various principles in paras 43-44 of the Report thus:
“43. The question still remains whether arbitrator has the power to award interest pendente lite, and if so, on what principle. We must reiterate that we are dealing with the situation where the agreement does not provide for grant of such interest nor does it prohibit such grant. In other words, we are dealing with a case where the agreement is silent as to award of interest. On a conspectus of the aforementioned decisions, the following principles emerge:
(i) A person deprived of the use of money to which he is legitimately entitled has a right to be compensated for the deprivation, call it by any name. It may be called interest, compensation or damages. This basic consideration is as valid for the period the dispute is pending before the arbitrator as it is for the period prior to the arbitrator entering upon the reference. This is the principle of Section 34 of the Civil Procedure Code and there is no reason or principle to hold otherwise in the case of arbitrator.
(ii) An arbitrator is an alternative form (sic forum) for resolution of disputes arising between the parties. If so, he must have the power to decide all the disputes or differences arising between the parties. If the arbitrator has no power to award interest pendente lite, the party claiming it would have to approach the court for that purpose, even though he may have obtained satisfaction in respect of other claims from the arbitrator. This would lead to multiplicity of proceedings.
(iii) An arbitrator is the creature of an agreement. It is open to the parties to confer upon him such powers and prescribe such procedure for him to follow, as they think fit, so long as they are not opposed to law. (The proviso to Section 41 and Section 3 of the Arbitration Act illustrate this point). All the same, the agreement must be in conformity with law. The arbitrator must also act and make his award in accordance with the general law of the land and the agreement.
(iv) Over the years, the English and Indian courts have acted on the assumption that where the agreement does not prohibit and a party to the reference makes a claim for interest, the arbitrator must have the power to award interest pendente lite. Thawardas Pherumal v. Union of India AIR 1955 SC 468 has not been followed in the later decisions of this Court. It has been explained and distinguished on the basis that in that case there was no claim for interest but only a claim for unliquidated damages. It has been said repeatedly that observations in the said judgment were not intended to lay down any such absolute or universal rule as they appear to, on first impression. Until Deptt. of Irrigation v. Abhaduta Jena (1988) 1 SCC 418 almost all the courts in the country had upheld the power of the arbitrator to award interest pendente lite. Continuity and certainty is a highly desirable feature of law.
(v) Interest pendente lite is not a matter of substantive law, like interest for the period anterior to reference (pre-reference period). For doing complete justice between the parties, such power has always been inferred.
44. Having regard to the above consideration, we think that the following is the correct principle which should be followed in this behalf:
Where the agreement between the parties does not prohibit grant of interest and where a party claims interest and that dispute (along with the claim for principal amount or independently) is referred to the arbitrator, he shall have the power to award interest pendente lite. This is for the reason that in such a case it must be presumed that interest was an implied term of the agreement between the parties and therefore when the parties refer all their disputes—or refer the dispute as to interest as such—to the arbitrator, he shall have the power to award interest. This does not mean that in every case the arbitrator should necessarily award interest pendente lite. It is a matter within his discretion to be exercised in the light of all the facts and circumstances of the case, keeping the ends of justice in view.”
(emphasis in original)
The Constitution Bench of this Court has laid down that where the agreement between the parties does not prohibit grant of interest and where the party claims interest and that dispute is referred to the arbitrator, he shall have the power to award interest pendente lite. The law declared has been held applicable prospectively.
15. Another Constitution Bench of this Court in N.C Budharaj (2001) 2 SCC 721, considered the question of award of interest by the arbitrator for the pre-reference period. In that connection, discussion has been made and it has been observed as long as there is nothing in the arbitration agreement to exclude the jurisdiction of the arbitrator entertaining claim for interest on the amount due under the contract or any provision to claim interest on the amount due, the jurisdiction of the arbitrator to award interest for pre-reference period under Section 29 of the Arbitration Act, 1940 has to be upheld. In majority opinion, this Court has held thus:
“25. If that be the position, courts which of late encourage litigants to opt for and avail of the alternative method of resolution of disputes, would be penalising or placing those who avail of the same in a serious disadvantage. Both logic and reason should counsel courts to lean more in favour of the arbitrator holding to possess all the powers as are necessary to do complete and full justice between the parties in the same manner in which the civil court seized of the same dispute could have done. By agreeing to settle all the disputes and claims arising out of or relating to the contract between the parties through arbitration instead of having recourse to civil court to vindicate their rights the party concerned cannot be considered to have frittered away and given up any claim which otherwise it could have successfully asserted before courts and obtained relief. By agreeing to have settlement of disputes through arbitration, the party concerned must be understood to have only opted for a different forum of adjudication with less cumbersome procedure, delay and expense and not to abandon all or any of its substantive rights under the various laws in force, according to which only even the arbitrator is obliged to adjudicate the claims referred to him. As long as there is nothing in the arbitration agreement to exclude the jurisdiction of the arbitrator to entertain a claim for interest on the amounts due under the contract, or any prohibition to claim interest on the amounts due and become payable under the contract, the jurisdiction of the arbitrator to consider and award interest in respect of all periods subject only to Section 29 of the Arbitration Act, 1940 and that too the powers of the court thereunder, has to be upheld. The submission that the arbitrator cannot have jurisdiction to award interest for the period prior to the date of his appointment or entering into reference which alone confers upon him power, is too stale and technical to be countenanced in our hands, for the simple reason that in every case the appointment of an arbitrator or even resort to court to vindicate rights could be only after disputes have cropped up between the parties and continue to subsist unresolved, and that if the arbitrator has the power to deal with and decide disputes which cropped up at a point of time and for the period prior to the appointment of an arbitrator, it is beyond comprehension as to why and for what reason and with what justification the arbitrator should be denied only the power to award interest for the pre-reference period when such interest becomes payable and has to be awarded as an accessory or incidental to the sum awarded as due and payable, taking into account the deprivation of the use of such sum to the person lawfully entitled to the same.
26. For all the reasons stated above, we answer the reference by holding that the arbitrator appointed with or without the intervention of the court, has jurisdiction to award interest, on the sums found due and payable, for the pre-reference period, in the absence of any specific stipulation or prohibition in the contract to claim or grant any such interest. The decision in Jena case (1988) 1 SCC 418 taking a contra view does not lay down the correct position and stands overruled, prospectively, which means that this decision shall not entitle any party nor shall it empower any court to reopen proceedings which have already become final, and apply only to any pending proceedings. No costs.”
It has also been observed that G.C Roy case Irrigation Deptt., (1992) 1 SCC 508 cannot be said to have overruled Deptt. of Irrigation case (1988) 1 SCC 418 insofar as it dealt with the power of the arbitrator to award interest for the pre-reference period.
16. A three-Judge Bench of this Court in Hindustan Construction Co. Ltd. v. State of J&K (1992) 4 SCC 217 has laid down that the arbitrator has the power to award pendente lite interest on the basis of principle of Section 34 of the Code of Civil Procedure though same is not applicable. However, the observation has to be considered in case there is no express bar in the agreement for awarding pendente lite interest as it has simply followed what has been laid down in G.C Roy Irrigation Deptt., (1992) 1 SCC 508. This Court has laid down thus: (Hindustan Construction case (1992) 4 SCC 217)
“5. The question of interest can be easily disposed of as it is covered by recent decisions of this Court. It is sufficient to refer to the latest decision of a five-Judge Bench of this Court in Irrigation Deptt., State of Orissa v. G.C Roy Irrigation Deptt., (1992) 1 SCC 508. Though the said decision deals with the power of the arbitrator to award interest pendente lite, the principle of the decision makes it clear that the arbitrator is competent to award interest for the period commencing with the date of award to the date of decree or date of realisation, whichever is earlier. This is also quite logical for, while award of interest for the period prior to an arbitrator entering upon the reference is a matter of substantive law, the grant of interest for the post-award period is a matter of procedure. Section 34 of the Code of Civil Procedure provides both for awarding of interest pendente lite as well as for the post-decree period and the principle of Section 34 has been held applicable to proceedings before the arbitrator, though the section as such may not apply. In this connection, the decision in Union of India v. Bungo Steel Furniture (P) Ltd. AIR 1967 SC 1032 may be seen as also the decision in Gujarat Water Supply & Sewerage Board v. Unique Erectors (Gujarat) (P) Ltd. (1989) 1 SCC 532 which upholds the said power though on a somewhat different reasoning. We, therefore, think that the award on Item 8 should have been upheld.”
17. In Sayeed Ahmed (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629 various decisions of this Court have been referred. In State of Orissa v. B.N Agarwalla (1997) 2 SCC 469, this Court has laid down thus: (B.N Agarwalla case (1997) 2 SCC 469)
“18. In view of the aforesaid decisions there can now be no doubt with regard to the jurisdiction of the arbitrator to grant interest. The principles which can now be said to be well settled are that the arbitrator has the jurisdiction to award pre-reference interest in cases which arose after the Interest Act, 1978 had become applicable. With regard to those cases pertaining to the period prior to the applicability of the Interest Act, 1978, in the absence of any substantive law, contract or usage, the arbitrator has no jurisdiction to award interest. For the period during which the arbitration proceedings were pending in view of the decision in G.C Roy case Irrigation Deptt., (1992) 1 SCC 508 and Hindustan Construction Co. Ltd. case (1992) 4 SCC 217, the arbitrator has the power to award interest. The power of the arbitrator to award interest for the post-award period also exists and this aspect has been considered in the discussion relating to Civil Appeal No. 9234 of 1994 in the later part of this judgment.”
18. The decision in B.N Agarwalla (1997) 2 SCC 469 has been considered and distinguished by this Court in Sayeed Ahmed (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629 thus: (Sayeed Ahmed case (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629)
“20. The appellant next relied upon the judgment of this Court in State of Orissa v. B.N Agarwalla (1997) 2 SCC 469. In that case, this Court held that the arbitrator has jurisdiction to award: (i) interest for pre-reference period, (ii) interest for pendente lite, and (iii) future interest. This Court also held that the following part of Clause (4) of the Contract dealing with “Rates, materials and workmanship” did not bar award of interest by the arbitrator on the claims of the contractor:
“No interest is payable on amount withheld under the item of the agreement.”
Interpreting the said clause (which provided that interest was not payable on the amount which was withheld), this Court held that it referred only to the amount withheld by the employer State towards retention money for the defect liability period. This Court in fact clarified the position that if the terms of contract expressly stipulated that no interest would be payable, then the arbitrator would not get the jurisdiction to award interest. As Clause G1.09 in the present case contains an express bar and is different from the clause considered in B.N Agarwalla (1997) 2 SCC 469 the said decision is also of no assistance.”
19. In B.N Agarwalla (1997) 2 SCC 469 this Court has observed that Clause 4 of the contract dealing with “Rates, materials and workmanship” did not bar award of interest by the arbitrator on the claims of the contractor. The stipulation was that no interest was payable on amount withheld under the agreement.
20. In Sayeed Ahmed (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629, this Court has referred to the decision in State of U.P v. Harish Chandra & Co. (1999) 1 SCC 63, in which this Court has interpreted the stipulation contained in Clause 1.9 of the agreement which came up for consideration before a three-Judge Bench of this Court. Clause 1.9 is extracted hereunder: (Sayeed Ahmed case (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629)
“17. ‘9. “1.9 No claim for delayed payment due to dispute, etc.—No claim for interest or damages will be entertained by the Government with respect to any monies or balances which may be lying with the Government owing to any dispute, difference; or misunderstanding between the Engineer-in-Charge in marking periodical or final payments or in any other respect whatsoever.”’ (Harish Chandra case (1999) 1 SCC 63)”
This Court has interpreted Clause 1.9 and held that there is no provision which could be culled out against the respondent contractor that he could not raise claim of interest by way of damages before the arbitrator on the relevant items placed for adjudication.
21. This Court in Sayeed Ahmed (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629 has also distinguished the decision in Harish Chandra (1999) 1 SCC 63 in which Clause 1.09 came up for consideration thus: (Sayeed Ahmed case (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629)
“17. … This Court held that the said clause did not bar award of interest on any claim for damages or for claim for payment for work done. We extract below the reasoning for such decision:
‘10. A mere look at the clause shows that the claim for interest by way of damages was not to be entertained against the Government with respect to only a specified type of amount, namely, any monies or balances which may be lying with the Government owing to any dispute, difference between the Engineer-in-Charge and the contractor; or misunderstanding between the Engineer-in-Charge and the contractor in making periodical or final payments or in any other respect whatsoever. The words “or in any other respect whatsoever” also referred to the dispute pertaining to the monies or balances which may be lying with the Government pursuant to the agreement meaning thereby security deposit or retention money or any other amount which might have been with the Government and refund of which might have been withheld by the Government. The claim for damages or claim for payment for the work done and which was not paid for would not obviously cover any money which may be said to be lying with the Government. Consequently, on the express language of this clause, there is no prohibition which could be culled out against the respondent contractor that he could not raise the claim for interest by way of damages before the arbitrator on the relevant items placed for adjudication.’
18. In Harish Chandra (1999) 1 SCC 63 a different version of Clause 1.09 was considered. Having regard to the restrictive wording of that clause, this Court held that it did not bar award of interest on a claim for damages or a claim for payments for work done and which was not paid. This Court held that the said clause barred award of interest only on amounts which may be lying with the Government by way of security deposit/retention money or any other amount, refund of which was withheld by the Government.
19. But in the present case, Clause G1.09 is significantly different. It specifically provides that no interest shall be payable in respect of any money that may become due owing to any dispute, difference or misunderstanding between the Engineer-in-Charge and contractor or with respect to any delay on the part of the Engineer-in-Charge in making periodical or final payment or in respect of any other respect whatsoever. The bar under Clause G1.09 in this case being absolute, the decision in Harish Chandra (1999) 1 SCC 63 will not assist the appellant in any manner.”
(emphasis in original)
In Harish Chandra (1999) 1 SCC 63, this Court has laid down that Clause 1.09 did not bar award of interest for claim of damages for payment for work done and which was not paid for would not obviously cover any money which may be said to be lying with the Government.
22. In our opinion, it would depend upon the nature of the ouster clause in each case. In case there is express stipulation which debars pendente lite interest, obviously, it cannot be granted by the arbitrator. The award of pendente lite interest inter alia must depend upon the overall intention of the agreement and what is expressly excluded.
23. In Sayeed Ahmed (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629, this Court has referred to the decision in Supt. Engineer v. B. Subba Reddy (1999) 4 SCC 423 and observed thus: (Sayeed Ahmed case (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629)
“11. Two more decisions dealing with cases arising under the Arbitration Act, 1940 require to be noticed. In Supt. Engineer v. B. Subba Reddy (1999) 4 SCC 423 this Court held that interest for pre-reference period can be awarded only if there was an agreement to that effect or if it was allowable under the Interest Act, 1978. Therefore, claim for interest for pre-reference period, which is barred as per the agreement or under the Interest Act, 8 could not be allowed. This Court, however, held that the arbitrator can award interest pendente lite and future interest.”
24. In Sayeed Ahmed (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629 this Court has also referred to the decision in State of Rajasthan v. Ferro Concrete Construction (P) Ltd. (2009) 12 SCC 1 , (2009) 4 SCC (Civ) 604 thus: (Sayeed Ahmed case (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629)
“12. The principles relating to interest were summarised by this Court in State of Rajasthan v. Ferro Concrete Construction (P) Ltd. (2009) 12 SCC 1 , (2009) 4 SCC (Civ) 604 thus:
(a) Where a provision for interest is made on any debt or damages, in any agreement, interest shall be paid in accordance with such agreement.
(b) Where payment of interest on any debt or damages is barred by express provision in the contract, no interest shall be awarded.
(c) Where there is no express bar in the contract and where there is also no provision for payment of interest then the principles of Section 3 of the Interest Act will apply and consequently, interest will be payable:
(i) where the proceedings relate to a debt (ascertained sum) payable by virtue of a written instrument at a certain time, then from the date when the debt is payable to the date of institution of the proceedings;
(ii) where the proceedings is for recovery of damages or for recovery of a debt which is not payable at a certain time, then from the date mentioned in a written notice given by the person making a claim to the person liable for the claim that interest will be claimed.
(d) Payment of interest pendente lite and future interest shall not be governed by the provisions of the Interest Act, 1978, but by the provisions of Section 34 of the Code of Civil Procedure, 1908 or the provisions of law governing arbitration as the case may be.”
In Sayeed Ahmed (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629, the provisions of the Arbitration and Conciliation Act, 1996 were applicable.
25. A three-Judge Bench of this Court in Union of India v. Bright Power Projects (India) (P) Ltd. (2015) 9 SCC 695 , (2015) 4 SCC (Civ) 702 has considered the provisions contained in Section 31(7)(a) of the Arbitration and Conciliation Act, 1996 and considered the words “unless otherwise agreed by parties” in the said section and held that the arbitrator is bound by the terms of the contract so far as award of interest from the date of execution to the date of award is concerned. This Court considered Clause 13(3) of the contract and came to the conclusion that once agreed that contractor would not claim any interest on the amount to be paid under the contract, he could not have claimed the interest. The arbitrator while awarding interest failed to consider the provisions of Section 31(7)(a) and binding nature of Clause 13(3) of the terms of agreement. With respect to Section 31(7)(a) of the Arbitration and Conciliation Act, 1996 this Court in Union of India v. Bright Power Projects (India) (P) Ltd. (2015) 9 SCC 695 , (2015) 4 SCC (Civ) 702 has observed thus:
“18. Section 31(7)(a) of the Act ought to have been read and interpreted by the Arbitral Tribunal before taking any decision with regard to awarding interest. The said section, which has been reproduced hereinabove, gives more respect to the agreement entered into between the parties. If the parties to the agreement agree not to pay interest to each other, the Arbitral Tribunal has no right to award interest pendente lite.”
Section 31(7)(a) of the 1996 Act confers the power on the arbitrator to award interest pendente lite, “unless otherwise agreed by parties”. Thus, it is clear from the provisions contained in Section 31(7)(a) that the contract between the parties has been given importance and is binding on the arbitrator. The arbitration clause is also required to be looked into while deciding the power of the arbitrator and in case there is any bar contained in the contract on award of interest, it operates on which items and in the arbitration clause what are the powers conferred on the arbitrator and whether bar on award of interest has been confined to certain period or it relates to pendency of proceedings before the arbitrator.
26. In Sree Kamatchi Amman Constructions (2010) 8 SCC 767 , (2010) 3 SCC (Civ) 575, it was observed that the words “unless otherwise agreed by the parties” in Section 31 of the new Act of 1996 clarify that the arbitrator is bound by the terms of contract for award of interest pendente lite. It was also held thus:
“19. Section 31(7) of the new Act by using the words “unless otherwise agreed by the parties” categorically clarifies that the arbitrator is bound by the terms of the contract insofar as the award of interest from the date of cause of action to the date of award. Therefore, where the parties had agreed that no interest shall be payable, the Arbitral Tribunal cannot award interest between the date when the cause of action arose to the date of award.
20. We are of the view that the decisions in Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani (2010) 1 SCC 549 , (2010) 1 SCC (Civ) 168 are inapplicable for yet another reason. In Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani (2010) 1 SCC 549 , (2010) 1 SCC (Civ) 168 the arbitrator had awarded interest for the pendente lite period. This Court upheld the award of such interest under the old Act on the ground that the arbitrator had the discretion to decide whether interest should be awarded or not during the pendente lite period and he was not bound by the contractual terms insofar as the interest for the pendente lite period. But in the instant case, the Arbitral Tribunal has refused to award interest for the pendente lite period. Where the Arbitral Tribunal has exercised its discretion and refused award of interest for the period pendente lite, even if the principles in those two cases were applicable, the award of the arbitrator could not be interfered with. On this ground also the decisions in Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani (2010) 1 SCC 549 , (2010) 1 SCC (Civ) 168 are inapplicable. Be that as it may.”
(emphasis in original)
27. This Court in Union of India v. Krafters Engg. & Leasing (P) Ltd. (2011) 7 SCC 279 , (2011) 3 SCC (Civ) 533 has held that by a provision in the agreement, the jurisdiction of the arbitrator to award interest can be excluded. This Court considered the nature of the claim vis-à-vis the provision contained in the relevant clause.
28. It is apparent from various decisions referred to above that in G.C Roy Irrigation Deptt., (1992) 1 SCC 508 the Constitution Bench of this Court has laid down that where the agreement expressly provides that no interest pendente lite shall be payable on amount due, the arbitrator has no power to award interest. In N.C Budharaj (2001) 2 SCC 721 a Constitution Bench has observed that in case there is nothing in the arbitration agreement to exclude jurisdiction of the arbitrator to entertaining claim for interest, the jurisdiction of the arbitrator to consider and award interest in respect to all periods is subject to Section 29 of the Act. In Hindustan Construction Co. Ltd. (1992) 4 SCC 217 this Court has followed the decision in G.C Roy Irrigation Deptt., (1992) 1 SCC 508 and laid down that on the basis of principles of Section 34 the arbitrator would have the power to award pendente lite interest also. In B.N Agarwalla (1997) 2 SCC 469, this Court has again followed G.C Roy Irrigation Deptt., (1992) 1 SCC 508 and Hindustan Construction Co. Ltd. (1992) 4 SCC 217 with respect to the power of the arbitrator to award pendente lite interest and it was held that the arbitrator has the power to award interest. In Harish Chandra (1999) 1 SCC 63 this Court interpreted Clause 1.9 which provided that no claim for interest or damages will be entertained by the Government in respect to any monies or balances which may be lying with the Government. It was held that there was no provision which could be culled out against the contractor not to claim interest by way of damages before the arbitrator on the relevant items placed for adjudication. In Ferro Concrete Construction (P) Ltd. (2009) 12 SCC 1 , (2009) 4 SCC (Civ) 604 this Court considered Clause 4 containing a stipulation that no interest was payable on amount withheld under the agreement. It was held that Clause 4, which dealt with rates, material and workmanship, did not bar award of interest by the arbitrator on claims of the contractor made in the said case. In Sayeed Ahmed (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629 this Court has emphasised that award of interest would depend upon nature of the clause in the agreement. In Bright Power Projects (India) (P) Ltd. (2015) 9 SCC 695 , (2015) 4 SCC (Civ) 702 this Court has considered the expression “unless otherwise agreed by parties” employed in Section 31(7)(a) of the 1996 Act and laid down that in case contract bars claim of interest the contractor could not have claimed interest. The provision of Section 31(7)(a) of the 1996 Act is binding upon the arbitrator. In Sree Kamatchi Amman Constructions (2010) 8 SCC 767 , (2010) 3 SCC (Civ) 575 similar view has been taken.
29. Now we come to the question of correctness of decision of this Court rendered by a Bench of two Judges in Engineers-De-Space-Age (1996) 1 SCC 516 which has been referred for our consideration in which this Court after consideration of G.C Roy case Irrigation Deptt., (1992) 1 SCC 508 has observed thus: (Engineers-De-Space-Age case (1996) 1 SCC 516)
“3. … It will appear from what the Constitution Bench stated to be the legal position, that ordinarily a person who is deprived of his money to which he is legitimately entitled as of right is entitled to be compensated in deprivation thereof, call it by whatever name. This would be in terms of the principle laid down in Section 34 of the Code of Civil Procedure. Their Lordships pointed out that there was no reason or principle to hold otherwise in the case of an arbitrator. Pointing out that arbitrator is an alternative forum for resolution of disputes arising between the parties, it said that he must have the power to decide all disputes and differences arising between the parties and if he were to be denied the power to award interest pendente lite, the party entitled thereto would be required to go to a court which would result in multiplicity of proceedings, a situation which the court should endeavour to avoid. Reliance was, however, placed on the observation in sub-para (iii) wherein it is pointed out that an arbitrator is a creature of an agreement and if the agreement between the parties prohibits the payment of interest pendente lite the arbitrator must act in accordance therewith. In other words, according to Their Lordships the arbitrator is expected to act and make his award in accordance with the general law of the land but subject to an agreement, provided, the agreement is valid and legal. Lastly, it was pointed out that interest pendente lite is not a matter of substantive law, like interest for the period anterior to reference. Their Lordships concluded that where the agreement between the parties does not prohibit grant of interest and where a party claims interest and that dispute is referred to the arbitrator, he shall have the power to award interest pendente lite for the simple reason that in such a case it is presumed that interest was an implied term of the agreement between the parties; it is then a matter of exercise of discretion by the arbitrator. The position in law has, therefore, been clearly stated in the aforesaid decision of the Constitution Bench.
4. We are not dealing with a case in regard to award of interest for the period prior to the reference. We are dealing with a case in regard to award of interest by the arbitrator post reference. The short question, therefore, is whether in view of sub-clause (g) of Clause 13 of the contract extracted earlier the arbitrator was prohibited from granting interest under the contract. Now the term in sub-clause (g) merely prohibits the Commissioner from entertaining any claim for interest and does not prohibit the arbitrator from awarding interest. The opening words “no claim for interest will be entertained by the Commissioner” clearly establishes that the intention was to prohibit the Commissioner from granting interest on account of delayed payment to the contractor. Clause 13 has to be strictly construed for the simple reason that as pointed out by the Constitution Bench, ordinarily, a person who has a legitimate claim is entitled to payment within a reasonable time and if the payment has been delayed beyond reasonable time he can legitimately claim to be compensated for that delay whatever nomenclature one may give to his claim in that behalf.”
30. In Sayeed Ahmed (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629 the decision in Engineers-De-Space-Age (1996) 1 SCC 516 has been considered and it was observed that it cannot be used to support an outlandish argument that bar on the Government or department paying interest is not a bar on the arbitrator awarding interest. This Court expressed doubt as to the correctness of certain observations made in Engineers-De-Space-Age (1996) 1 SCC 516 to the extent that the arbitrator could award interest pendente lite ignoring the express bar in the contract. But this Court did not consider the question further as the case in Sayeed Ahmed (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629 arose under the Arbitration and Conciliation Act, 1996, and there was a specific provision under the new Act regarding the award of interest by the arbitrator. From the discussion made in Sayeed Ahmed (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629 it is apparent that this Court has emphasised that it would depend upon the nature of clause and claim, etc. and it is required to be found on consideration of stipulation whether interest is barred, if yes, on what amounts interest is barred under the contract.
31. A three-Judge Bench of this Court in Tehri Hydro Development Corpn. Ltd. v. Jai Prakash Associates Ltd. (2012) 12 SCC 10 , (2013) 2 SCC (Civ) 122, has considered the question which has been referred in the instant case and it has been laid down in the context of Clauses 1.2.14 and 1.2.15, imposed a clear bar on either entertainment or payment of interest in any situation of non-payment or delayed payment of either the amounts due for work done or lying in security deposit. Thus, the arbitrator had no power to grant pendente lite interest. This Court has also doubted the correctness of the decisions in Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani Construction Corpn. (P) Ltd. (2010) 1 SCC 549 , (2010) 1 SCC (Civ) 168. This Court has considered the aforesaid clauses and various decisions in Tehri Hydro Development Corpn. (2012) 12 SCC 10 , (2013) 2 SCC (Civ) 122 in which one of us Ranjan Gogoi, J. spoke for the Court. This Court has laid down thus:
“14. This will lead the court to a consideration of what is the principal bone of contention between the parties in the present case, namely, the issue with regard to payment of interest. Clauses 1.2.14 and 1.2.15 on which much arguments have been advanced by the learned counsel for both sides may now be extracted below:
‘PART II
conditions of contract
1.2.14 No claim for delayed payment due to dispute, etc.—The contractor agrees that no claim for interest of damages will be entertained or payable by the Government in respect of any money or balances which may be lying with the Government owing to any disputes, differences or misunderstandings between the parties or in respect of any delay or omission on the part of the Engineer-in-Charge in making immediate or final payments or in any other respect whatsoever.
1.2.15 Interest on money due to the contractor.—No omission on the part of the Engineer-in-Charge to pay the amount due upon measurement or otherwise shall vitiate or make void the contract, nor shall the contractor be entitled to interest upon any guarantee or payments in arrears nor upon any balance which may on the final settlement of his accounts be due to him.’
A reading of the aforesaid two clauses of the contract agreement between the parties clearly reveal that despite some overlapping of the circumstances contemplated by the two clauses, no interest is payable to the contractor for delay in payment, either, interim or final, for the works done or on any amount lying in deposit by way of guarantee. The aforesaid contemplated consequence would be applicable both to a situation where withholding of payment is on account of some dispute or difference between the parties or even otherwise.
15. Of the several decisions of this Court referred to by the learned counsel for the appellant the judgments of the Constitution Bench of this Court in Irrigation Deptt., State of Orissa v. G.C Roy Irrigation Deptt., (1992) 1 SCC 508 and Dhenkanal Minor Irrigation Division v. N.C Budharaj (2001) 2 SCC 721 will require specific notice. The true ratio laid down in the aforesaid two judgments have been elaborately considered in a more recent pronouncement of this Court in Union of India v. Krafters Engg. and Leasing (P) Ltd. (2011) 7 SCC 279 , (2011) 3 SCC (Civ) 533 In Krafters Engg. case (2011) 7 SCC 279 , (2011) 3 SCC (Civ) 533 the ratio of the decision in G.C Roy case Irrigation Deptt., (1992) 1 SCC 508 was identified to mean that if the agreement between the parties does not prohibit grant of interest and the claim of a party to interest is referred to the arbitrator, the arbitrator would have the power to award the interest. This is on the basis that in such a case of silence (where the agreement is silent) it must be presumed that interest was an implied term of the agreement and, therefore, whether such a claim is tenable can be examined by the arbitrator in the reference made to him. The aforesaid view, specifically, is with regard to pendente lite interest. In the subsequent decision of the Constitution Bench in N.C Budharaj case (2001) 2 SCC 721 a similar view has been taken with regard to interest for the pre-reference period.
16. In Krafters Engg. case (2011) 7 SCC 279 , (2011) 3 SCC (Civ) 533 the somewhat discordant note struck by the decisions of this Court in Port of Calcutta v. Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani Construction Corpn. (P) Ltd. v. Union of India (2010) 1 SCC 549 , (2010) 1 SCC (Civ) 168 were also taken note of. Thereafter, it was also noticed that the decision in Engineers-De-Space-Age case (1996) 1 SCC 516 was considered in Sayeed Ahmed & Co. v. State of U.P (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629 and the decision in Madnani Construction case (2010) 1 SCC 549 , (2010) 1 SCC (Civ) 168 was considered in Sree Kamatchi Amman Constructions v. Railways (2010) 8 SCC 767 , (2010) 3 SCC (Civ) 575. In Sayeed Ahmed case (2009) 12 SCC 26 , (2009) 4 SCC (Civ) 629 (SCC para 24) it was held that in the light of the decisions of the Constitution Bench in G.C Roy case Irrigation Deptt., (1992) 1 SCC 508 and N.C Budharaj case (2001) 2 SCC 721 it is doubtful whether the observations in Engineers-De-Space-Age case (1996) 1 SCC 516 to the effect that the arbitrator could award interest pendente lite, ignoring the express bar in the contract, is good law. In Sree Kamatchi Amman Construction case (2010) 8 SCC 767 , (2010) 3 SCC (Civ) 575 while considering Madnani case (2010) 1 SCC 549 , (2010) 1 SCC (Civ) 168 this Court noted that the decision in Madnani case (2010) 1 SCC 549 , (2010) 1 SCC (Civ) 168 follows the decision in Engineers-De-Space-Age case (1996) 1 SCC 516.
17. From the above discussions, it is crystal clear that insofar as pendente lite interest is concerned, the observations contained in paras 43 and 44 of the judgment in G.C Roy case Irrigation Deptt., (1992) 1 SCC 508 will hold the field. Though the gist of the said principle has been noticed earlier it would still be appropriate to set out para 44 of the judgment in G.C Roy case Irrigation Deptt., (1992) 1 SCC 508 which is in the following terms:
‘44. Having regard to the above consideration, we think that the following is the correct principle which should be followed in this behalf:
Where the agreement between the parties does not prohibit grant of interest and where a party claims interest and that dispute (along with the claim for principal amount or independently) is referred to the arbitrator, he shall have the power to award interest pendente lite. This is for the reason that in such a case it must be presumed that interest was an implied term of the agreement between the parties and therefore when the parties refer all their disputes—or refer the dispute as to interest as such—to the arbitrator, he shall have the power to award interest. This does not mean that in every case the arbitrator should necessarily award interest pendente lite. It is a matter within his discretion to be exercised in the light of all the facts and circumstances of the case, keeping the ends of justice in view.’
(emphasis in original)
18. The provisions of the U.P Civil Laws (Reforms and Amendment) Act amending the First Schedule to the Arbitration Act, 1940 does not assist the respondent contractor in any manner to sustain the claim of award of interest pendente lite, inasmuch, as Para 7-A of the First Schedule, as amended, is only an enabling provision which will have no application to a situation where there is an express bar to the entertainment or payment of interest on the delayed payment either of an amount due for the work done or of an amount lying in deposit as security. The decision in B.N Agarwalla case (1997) 2 SCC 469 on which reliance has been placed by the learned counsel for the respondent, once again, does not assist the claim of the respondent to interest pendente lite inasmuch as in B.N Agarwalla case (1997) 2 SCC 469 the views of the Constitution Bench in G.C Roy case Irrigation Deptt., (1992) 1 SCC 508 with regard to interest pendente lite could not have been and, in fact, were not even remotely doubted. The observation of the Bench in B.N Agarwalla case (1997) 2 SCC 469 that in G.C Roy case Irrigation Deptt., (1992) 1 SCC 508 the decision in Deptt. of Irrigation v. Abhaduta Jena (1988) 1 SCC 418 was not overruled was only in the context of the issue of award of interest for the pre-reference period. The decision in Asian Techs Ltd. case (2009) 10 SCC 354 , (2009) 4 SCC (Civ) 203 also relied on by the respondent takes note of the decision in Engineers-De-Space-Age case (1996) 1 SCC 516 to come to the conclusion that the prohibition on payment of interest contained in Clause 11 of the agreement between the parties was qua the department and did not bar the arbitrator from entertaining the claim. It has already been noticed that the correctness of the propositions laid down in Engineers-De-Space-Age case (1996) 1 SCC 516 have been doubted in the subsequent decisions of this Court, reference to which has already been made.
19. Clauses 1.2.14 and 1.2.15, already extracted and analysed, imposed a clear bar on either entertainment or payment of interest in any situation of non-payment or delayed payment of either the amounts due for work done or lying in security deposit. On the basis of the discussions that have preceded, we, therefore, take the view that the grant of pendente lite interest on the claim of Rs 10,17,461 is not justified. The award as well as the orders of the courts below are accordingly modified to the aforesaid extent.”
32. In para 4 in Engineers-De-Space-Age (1996) 1 SCC 516 this Court has observed that bar under the contract will not be applicable to the arbitrator cannot be said to be observation of general application. In our opinion, it would depend upon the stipulation in the contract in each case whether the power of the arbitrator to grant pendente lite interest is expressly taken away. If answer is “yes” then the arbitrator would have no power to award pendente lite interest.
33. The decision in Madnani Construction Corpn. (2010) 1 SCC 549 , (2010) 1 SCC (Civ) 168 has followed the decision in Engineers-De-Space-Age (1996) 1 SCC 516. The same is also required to be diluted to the extent that express stipulation under contract may debar the arbitrator from awarding interest pendente lite. Grant of pendente lite interest may depend upon several factors such as phraseology used in the agreement, clauses conferring power relating to arbitration, nature of claim and dispute referred to arbitrator and on what items power to award interest has been taken away and for which period.
34. Thus, our answer to the reference is that if the contract expressly bars the award of interest pendente lite, the same cannot be awarded by the arbitrator. We also make it clear that the bar to award interest on delayed payment by itself will not be readily inferred as express bar to award interest pendente lite by the Arbitral Tribunal, as ouster of power of the arbitrator has to be considered on various relevant aspects referred to in the decisions of this Court, it would be for the Division Bench to consider the case on merits.
Alert