Factual and Procedural Background
The petitioner, Jinnatun Khatun, challenged an order dated 14th July 2015 passed by the Prescribed Authority and Block Development Officer (BDO) of Hemtabad Development Block, Uttar Dinajpur. The order appointed the Upa-Pradhan of Bishnupur Gram Panchayat, Sri Saki Mohammad, to exercise the powers and duties of the Pradhan until further order. This writ petition was filed subsequent to the disposal of an earlier appeal on 10th August 2015, which had held that the decision to remove the Pradhan had become effective, ceasing the original cause of action of the earlier writ petitioners. The petitioner was granted liberty to challenge the removal order in accordance with law and filed the present petition accordingly.
The background involves a series of motions for removal of the petitioner as Pradhan, notices for meetings convened for this purpose, interim orders passed by this Court staying operation of such notices, dismissal of writ petitions for default, restoration applications, and finally the impugned order directing the petitioner to hand over charge.
Legal Issues Presented
- Whether the impugned order dated 14th July 2015 was issued in compliance with the mandatory timelines prescribed under sub-section (10) of Section 12 of the West Bengal Panchayat Act, 1973, which requires the entire process from submission of the motion to final action to be completed within thirty days.
- Whether the Prescribed Authority was barred under sub-section (11) of Section 12 of the said Act from taking cognizance of the second motion for removal within one year from the date appointed for the first meeting.
- Whether the interim orders passed by this Court from January to March 2015 should be excluded from the computation of the thirty-day period.
- Whether the impugned removal order is vitiated due to non-compliance with the statutory provisions and procedural fairness.
- Whether the petitioner’s removal and the subsequent appointment of a new Pradhan could be challenged in the present writ petition.
Arguments of the Parties
Petitioner's Arguments
- The impugned order was given effect to beyond the thirty-day period prescribed under sub-section (10) of Section 12 of the West Bengal Panchayat Act, 1973, rendering it bad in law.
- The entire process for removal of the Pradhan and appointment of a new Pradhan must be completed within thirty days starting from submission of the motion; here, the second motion was submitted on 19th December 2014, but the order was passed on 14th July 2015.
- Sub-section (11) of Section 12 bars any subsequent motion for removal within one year if the earlier motion is not adjudicated; since the earlier motion was still pending, the second motion was barred.
- The interim orders passed by this Court between 2nd January 2015 and 30th March 2015 should be excluded from the thirty-day period calculation.
- The prescribed authority failed to consider the withdrawal of consent by majority members prior to passing the impugned order.
- The conduct of the prescribed authority was unfair and contrary to law.
- The removal order and related proceedings violate mandatory statutory provisions and should be set aside.
- Relied on precedents including Rasul Mohammad & Ors vs State of West Bengal & Ors (2005 (4) CHN 159) and Raghunath Manna & Anr vs State of West Bengal & Ors (2001 (1) CLJ 647) to support the mandatory nature of the provisions.
Respondents' Arguments
- The impugned notice was issued within the stipulated period under sub-section (10) of Section 12 of the West Bengal Panchayat Act, 1973; there was no violation of statutory provisions as alleged by the petitioner.
- The decision to remove the petitioner as Pradhan had become effective as per the order dated 10th August 2015 of the Division Bench, which dismissed the writ petition.
- The action taken by the Prescribed Authority to hold the election of a new Pradhan was lawful and in accordance with the directions of the Division Bench.
- Sub-section (11) of Section 12 was complied with and the requisition for removal was valid, supported by signatures of 11 out of 17 members expressing lack of confidence.
- The petitioner’s challenges to notices and meetings were dismissed or quashed with liberty to act in accordance with law.
- Relied on Supreme Court decision in Bhanumati & Others vs State of Uttar Pradesh (2010 (12) SCC 1) emphasizing democratic principles and confidence of public bodies in elected heads.
- Relied on unreported Division Bench decisions and other precedents to support the validity of the removal process and election of new Pradhan.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Rasul Mohammad & Ors vs State of West Bengal & Ors, 2005 (4) CHN 159 | Mandatory compliance with procedural timelines and convening meetings within prescribed period under the West Bengal Panchayat Act. | Supported the petitioner's contention that statutory timelines must be adhered to and failure to do so renders the action invalid. |
| Raghunath Manna & Anr vs State of West Bengal & Ors, 2001 (1) CLJ 647 | Interpretation of procedural requirements under Panchayat Act and statutory bars on motions within one year. | Reinforced the statutory bar on second motion for removal within one year if the first motion is pending. |
| Bhanumati & Others vs State of Uttar Pradesh, 2010 (12) SCC 1 | Democratic principles require that persons heading public bodies continue only if they enjoy confidence of members. | Respondents relied on this to justify the removal and election process as reflecting democratic confidence. |
| Minara Bibi & Others vs Muslima Bibi & Others (Unreported Division Bench, Calcutta High Court, 3rd March 2014) | Authority’s obligation to conduct elections promptly and in accordance with law after removal of incumbent. | Supported respondents' argument for holding election of new Pradhan without undue delay. |
| Upananda Chatterjee vs State of West Bengal & Others, 2007 (4) CHN 605 | Distinction between mandatory and directory provisions; procedural provisions require substantial compliance unless there is no notice, opportunity or hearing. | Court used this to analyze whether procedural lapses vitiated the removal order. |
| State Bank of India vs S.K. Sharma, AIR 1996 SC 1669 | Principles on mandatory vs procedural compliance, prejudice test in procedural violations. | Guided the Court's reasoning on procedural compliance and whether violation prejudiced the petitioner. |
Court's Reasoning and Analysis
The Court examined the timeline and procedural compliance under Section 12 of the West Bengal Panchayat Act, 1973. It found that the entire process of removal and appointment was not completed within the mandatory thirty-day period starting from the submission of the motion dated 19th December 2014. The Court noted that the interim orders passed by this Court between 2nd January 2015 and 30th March 2015 should be excluded from this period, further extending the timeline.
The Court also found that the second motion for removal was issued within one year of the first motion, contravening sub-section (11) of Section 12, which bars subsequent motions within one year if the earlier motion is pending adjudication.
Additionally, the Court observed that the Prescribed Authority failed to consider the withdrawal of consent by majority members prior to passing the impugned order, which affected procedural fairness.
While the respondents relied on democratic principles and prior orders validating the removal and election, the Court emphasized strict compliance with statutory provisions, particularly the mandatory timelines and statutory bars, over the majority's resolution.
Relying on precedents distinguishing mandatory and directory provisions, the Court held that Section 12’s provisions are mandatory, and non-compliance cannot be overlooked. The Court rejected the argument that the majority decision justifies the removal when statutory provisions are violated.
Consequently, the Court concluded that the impugned removal order dated 14th July 2015 was passed beyond the statutory period and without adherence to mandatory procedural requirements, rendering it legally unsustainable.
Holding and Implications
The impugned order dated 14th July 2015 passed by the Prescribed Authority and Block Development Officer, Hemtabad Development Block, Uttar Dinajpur, removing the petitioner from the office of Pradhan of Bishnupur Gram Panchayat, is set aside and quashed.
The Court clarified that since the election of the new Pradhan was not challenged in this writ petition, no order was made regarding the election, and the petitioner remains free to challenge the election in separate proceedings if entitled by law. The writ petition was allowed without any order as to costs.
No new precedent was established; the decision strictly enforces mandatory compliance with statutory procedural provisions under the West Bengal Panchayat Act, emphasizing the importance of adherence to timelines and statutory bars in motions for removal of elected Panchayat office bearers.
IN THE HIGH COURT AT CALCUTTA
CONSTITUTIONAL WRIT JURISDICTION
APPELLATE SIDE
Present: The Hon'ble Justice Samapti Chatterjee WP 20150 (W) of 2015
Jinnatun Khatun
Vs
The State of West Bengal & Others
For the Petitioner : Mr. Piyush Chaturvedi, LearnedAdvocate Mr. Ardhendu Sekhar Biswas, Learned Advocate Mr. Saikat Banerjee, Learned Advocate
For the respondent No.8
to 18 : Mr. Arindam Chatterjee, Learned Advocate Mr. N.K. Singh, Learned Advocate
For the State : Mr. Subhabrata Datta, Learned Advocate Mr. Tapas Kumar Mondal Mondal, Learned Advoate Heard on : December 1, 2015
Judgment on : January 27, 2016.
Samapti Chatterjee, J.
1. The petitioner has filed the present writ petition challenging the impugned order under Memo dated 14thJuly, 2015 passed by the Prescribed Authority & BDO, Hemtabad Development Block, Hemtabad, Uttar Dinajpur whereby the order issued by the said Prescribed Authority & BDO speaks as follows :-
1
"That in conformity with the statutory provision as laid down in sub- section (4) of section (9) of the West Bengal Panchayat Act as amended up to date, Upa-Pradhan of Bishnupur G.P. Sri Saki Mohammad shall exercise the powers, perform functions and discharge the duties of the Pradhan until further order."
2. Mr. Piyush Chaturvedi, learned Advocate appearing for the petitioner submitted that the impugned order dated 14thJuly, 2015 was actually given effect to on 17thAugust, 2015 as the appeal preferred by the private respondents was disposed of on 10thAugust, 2015 by holding, inter alia as follows :-
"We have considered the fact and circumstances of the case. On e the decision to remove the Pradhan became effective the original cause of action of the writ petitioners ceased to exist on the basis of the original writ petition. The petitioners were not in a position to get any relief because the order for removal had already been passed. So long as that order is not set aside, the order passed on 2nd January, 2015 cannot also be made operative once again. Therefore, the order under challenge is patently bad and is set aside."
2
In the said order, Their Lordships were pleased to grant leave to the petitioners only to the effect that 'this will not, however, preclude the writ petitioners from challenging the order of removal if they are entitled in accordance with law.'
With this liberty, the petitioner immediately thereafter, filed the present writ petition challenging the impugned order under Memo dated 14thJuly, 2015 which was actually given effect to from 17thAugust,
2015.
3. Mr. Chaturvedi further submitted that this impugned order is bad in law since it has not been issued within the period as prescribed under sub-section (10) of Section 12 of the West Bengal Panchayat Act, 1973. Sub-Section (10) of Section 12 of the said Act is set out hereunder
:
"S.12. *******
(10) On receipt of the minutes of the meeting and the report under sub-section (9), the prescribed authority shall, within next five working days, take such action, as he may deem fit and the entire process commencing from submission of motion to the prescribed
3
authority up to the action finally taken by him shall be completed within thirty days"
It is however, submitted by Mr. Chaturvedi that as per sub-section
(10) of Section 12 of the said Act, the entire process would be completed within thirty days. Mr. Chaturvedi further contended that the entire process under sub-section (10) of Section 12 postulates from removal of the Pradhan upto appointment of the new Pradhan in place and stead of the earlier Pradhan. Mr. Chaturvedi further drew my attention to sub- section (11) of Section 12 of the said Act where it prescribes as follows :
"S.12.***********
(11) If the motion is not carried by the majority of its existing members or the meeting cannot be held for want of quorum, not notice of any subsequent motion for the removal of the same office bearers shall be taken into cognizance within a period of one year from the date appointed for such meeting"
4. Mr. Chaturvedi further emphasized that since the earlier motion, which is the subject matter of the earlier writ petition being W.P. 28680 (W) of 2014 is still pending for final adjudication, therefore, the
4
Prescribed Authority is barred from taking further motion in respect of the same cause of action.
The aforesaid submission is vehemently opposed by Mr. Arindam Chatterjee, learned Advocate appearing for the respondents.
6. Mr. Chaturvedi further contended that the meeting was fixed on 6thJanuary, 2014. Notice of meeting was quashed on 14thOctober, 2014. Against that order appeal preferred by the State Authority where the Division Bench observed as follows:
On 19thDecember, 2014 second notice was issued. The Authority conveyed a meeting on 2ndJanuary, 2015 and the petitioner moved a writ petition before this Court obtaining interim order of stay of operation of the notice for a limited period of 30 days. Matter was dismissed for default subsequently on 22ndJune 2015 and an application for restoration of the said matter was filed on 13thJuly, 2015 and on 14th July, 2015 the prescribed authority directed the petitioner to handover the charge.
7. Mr. Chaturvedi further vehemently urged that the conduct of the prescribed authority is very unfair as the prescribed authority failed to comply the provision of the law.
5
8. Mr. Chaturvedi further contended that as per sub-section 10 of Section 12 the entire process should be completed within 30 days but it was not completed within 30 days by the Prescribed Authority. More so, Mr. Chaturvedi also submitted that 30 days starts from submission of the "Motion". The second "Motion" was submitted on 19thDecember, 2014. Not only that earlier notice issued on 24thSeptember, 2014 which is still alive. Therefore, sub-section 11 of Section 12 is a statutory bar since the earlier "Motion" is still pending for adjudication.
9. Mr. Chaturvedi further vehemently urged that provision of Section 12 is mandatory in nature. Therefore, any action taken on the basis of the earlier "Motion" should be set aside. In support of his contention Mr. Chaturvedi relied on a decision reported in 2005 (4) CHN Page 159 Paragraph-6 (Rasul Mohammad & Ors vs State of West Bengal & Ors) which is quoted below :
"Para-6-It further appears from the said notice that the Pradhan was requested to convene a meeting for the said purpose within 16.5.2005 which is contrary to the scheme as contained in section 16 of the West Bengal Panchayat Act, 1973 which provides that in the event such a request is made by the requisitionists, the Pradhan is required to convene a meeting within 15 days from the date of
6
receipt of such request failing which the requisitionists themselves can call a meeting for the said purpose."
Mr. Chaturvedi also relied on a decision reported in 2001 (1) CLJ Page-647 (Raghunath Manna & Anr vs State of West Bengal & Ors)Paragraphs-5-10.
10. Mr. Chaturvedi also submitted that second "Motion" on 19th December, 2014 is bad, illegal, arbitrary and contrary to law as it was within the period of one year as the first "Motion" was taken on 24th September, 2014 and second "Motion" was taken on 19thDecember,
2014.
11. Mr. Chaturvedi also vehemently urged that from 2ndJanuary, 2015 till 30thMarch, 2015 interim order was continuing. Only on 22nd June, 2015 the matter was dismissed for default. Therefore, that period of interim order i.e.from 1stJanuary, 2015 till 30thMarch, 2015 should be excluded from the 30 days which starts from 19thDecember, 2014 as the order of removal issued on 14thJuly, 2015 beyond 30 days as per statute, therefore the same is vitiated.
7
12. Mr. Arindam Chatterjee, learned Advocate appearing for the private respondents submitted that the impugned notice was issued within the stipulated period as indicated under sub-section (10) of Section 12 of the West Bengal Panchayat Act, 1973. Mr. Chatterjee further submitted that there is no violation of the sections as has been submitted by Mr. Chaturvedi learned Advocate for the petitioner. Mr. Chatterjee further contended that the Court should look into the order passed by the Appeal Court on 10thAugust, 2015 which appears at page 67 of the writ petition.
Mr. Chatterjee also submitted that by virtue of the order passed by the Hon'ble Division Bench, it is clear that once the decision to remove the Pradhan became effective, the original cause of action of the writ petitioner ceased to exist on the basis of the original writ petition. Therefore, Mr.Chatterjee contended that the removal of the petitioner has already been accepted according to the Division Bench order dated 10th August, 2015 which was, however, disputed by Mr. Chaturvedi learned Advocate for the petitioner and Mr. Chaturvedi submitted that the Hon'ble Division Bench has given liberty to the petitioner to challenge the removal order.
8
Therefore, the action taken by the Prescribed Authority to hold election in respect of the new Pradhan which was held on 01.12.2015 at 11:30 is bad in law as the removal of the petitioner is under challenge. If the appointment of the new Pradhan is given effect to then the writ petition will become infructuous.
14. Per contra, Mr. Subhabrata Dutta learned Advocate appearing for the State submitted that it is not correct that sub-section 11 of Section 12 was not complied with as in the present case provision under sub-section 11 of Section 12 has been complied by the authority.
15. Mr. Dutta further contended that out of total 17 members 11 members on 24thSeptember, 2014, expressed their lack of confidence on the petitioner as Pradhan and took decision for removal of Pradhan by putting their signatures and thereby requested the Prescribed Authority and Block Development Officer , Hemtabad Block to take decision on that issue. Thereafter on 24thOctober, 2014 the Prescribed Authority upon satisfaction of the requisition notice of the requisitionists issued notice for convening meeting for consideration of "Motion" for removal of the Pradhan on the ground of lack of confidence and for taking decision in the said meeting scheduled on 16thOctober, 2014 at the office of the Bishnupur Gram Panchayat at 11.30 A.M.
9
Challenging the said notice on 14thOctober, 2011 the petitioner moved a writ petition being W.P No.28680 (W) of 2014 and the Hon'ble Court was pleased to quash the notice dated 25thOctober, 2014 with the observation that the said order will not prevent the members of the Gram Panchayat or making new requisition for removal of the Pradhan and the Prescribed Authority shall act on such requisition in accordance with law. Against that order the requisitionists (respondent no.8 to 18) filed a Mandamus Appeal and on 13thNovember, 2014 the Hon'ble Division Bench held that the notice ought not to have been quashed for want of compliance of sub-section 4 of Section 12 of the Act. Therefore, the impugned order was set aside and the matter was placed before the Learned Single Judge for final disposal.
16. Mr. Dutta further contended that 11 members out of total members of 17 expressed their lack of confidence on the Pradhan and took decision for removal of the Pradhan by putting their signatures on 19thDecember, 2014 under Section 12 sub-section 3 of the West Bengal Gram Panchayat (Amendment) Act, 2010. On 24thDecember, 2014 the Prescribed Authority upon satisfaction of the requisitionists issued notice on the same date for convening meeting for consideration of the "Motion"
for lack of confidence against the Pradhan and for taking decision which was scheduled on 2ndJanuary, 2015.
10
17. Challenging the said notice the petitioner filed a writ petition being W.P. No.4439 (W) of 2015 and obtained an interim order on 1st February, 2015. On 22ndJune, 2015 the writ petition was dismissed for default and on 16thJuly, 2015 the Prescribed Authority passed order thereby accepting resolution dated 16thJanuary, 2015 adopted by majority member and also passed order for removal of the Pradhan. Only on 22ndJuly, 2015 the Learned Trial Judge after restoring the writ petition passed an order of extension of interim order for a period of eight weeks against which the authority preferred appeal and on 10th August, 2015, the Hon'ble Division Bench by an order dismissed the writ petition being W.P. No.34449 (W) of 2014. Before parting with his submission Mr. Dutta submitted that the present writ petition does not deserve any interference of this Hon'ble Court.
In support of his contention Mr. Dutta relied on a Supreme Court decision reported in 2010 (12) SCC Page-1 (Bhanumati & Others vs State of Uttar Pradesh Through Its Principal Secretary & Others)
Paragraph-58 which is quoted below :
" Para-58-These institutions must run on democratic principles. In democracy all persons heading public bodies can continue provided they enjoy the confidence of the persons who comprise such bodies. This is the essence of democratic republicanism. This explains why
11
this provision of no-confidence motion was there in the Act of 1961 even prior to the Seventy-third Constitution Amendment and has been continued even thereafter. Similar provisions are there in different States in India."
Mr. Dutta also relied on an unreported Division Bench decision of this Hon'ble High Court passed on 3rdMarch, 2014 in M.A.T. No.2098 of 2014 with C.A.N. No.11741 of 2014 (Minara Bibi & Others vs Muslima Bibi & Others). Some protion of the said unreported decision relied by Mr. Dutta is quoted below :-
"Therefore, we do not find any reason why the elected members of the gram panchayat should be prevented from electing a new Pradhan in accordance with law. Accordingly, we direct the prescribed authority namely, the respondent no.5 to take immediate necessary steps for electing the new Pradhan in respect of Kushmore-I Gram Panchayat without any further delay in accordance with law and upon strictly observing the prescribed procedures under the statute.
Needless to mention that after election of the new Pradhan, the Upa Pradhan will hand over the charge to the Pradhan so that the said Pradhan can run the affairs of the gram panchayat in accordance with law.
12
With the aforesaid observations and directions, we set aside the impugned order under appeal passed by the learned single Judge and dispose of both the application as well as the appeal upon treating the said appeal as on day's list." Mr. Dutta also relied on decision reported in 2007 (4) CHN Page- 605 (Upananda Chatterjee vs State of West Bengal & Orthers)
Paragraph-21 which is quoted below :-
"Para-21-In our view, the provisions of giving seven clear days' notice as mentioned in the second proviso to section 16 of the Act is a directory provision and not a mandatory one as rightly held in the case of Aloke Pramanik (supra) while construing a similar provision of the same statute. It is now settled by the Apex Court that if a particular statutory provision is a procedural one, even the use of the word "shall" in such provision will not make it mandatory unless consequence of disobedience has been indicated in the statute. The exceptions to the previously mentioned rule of interpretation are in the cases where there is either "no notice", or "no opportunity" or "no hearing". In this connection, we may refer to the following observations of the Supreme Court in the case of State Bank of India vs S.K. Sharma, reported in AIR 1996 SC 1669 at
1683..
13
"A substantive provision has normally to be complied with as explained hereinbefore and the theory of substantial compliance or the test of prejudice would not be applicable in such a case. In the case of violation of a procedural provision, the position is this procedural provisions are generally meant for affording a reasonable and adequate opportunity to the delinquent officer/employee. They are, generally speaking, conceived in his interest. Violation of any and every procedural provision cannot be said to automatically vitiate the enquiry held or order passed. Except cases falling under 'no notice', 'no opportunity' and 'no hearing' categories, the complaint of violation of procedural provision should be examined from the point of view of prejudice viz, whether such violation has prejudiced the delinquent officer/employee in defending himself properly and effectively."
18. Considering the submissions advanced by the learned Advocate of the respective parties and after perusing the record I find that an interim order was passed by this Hon'ble Court on 2ndJanuary, 2015 by directing the prescribed authority and Block Development Officer, Hemtabad Development Block, Hemtabad, District-Uttar Dinajpur to the effect that if any meeting for no confidence/removal against the petitioner has already been held that should not be given effect to for a limited period of two weeks from date and the said order was time to time extended till 30thMarch, 2015. From 30thMarch, 2015
14
till the date of issuance of the impugned order dated 14thJuly, 2015 the petitioner was allowed to function as Pradhan of the concerned Panchayat.
I also find that during that period by the letter dated 9thMarch, 2015 and affidavit dated 27thFebruary, 2015 majority of the members of the said Gram Panchayat withdrew their consent for removal of the petitioner in writing and submitted such desire before the prescribed authority and Block Development Officer concerned. Furthermore, prior to passing of the interim order dated 14thJuly, 2015 the Block Development Officer should have considered the withdrawal of consent submitted by some members of the said Panchayat.
19. I also find that the authority conveyed a meeting on 2nd January, 2015 and the petitioner moved before this Hon'ble Court and obtained interim order for 30 days though the said writ petition was dismissed for default on 22ndJune, 2015. Restoration application also filed on 13thJuly, 2015 and on 14thJuly, 2015 the petitioner was directed to handover the charge by the authority. In my view that action of the prescribed authority and the B.D.O was not in accordance with law. Admittedly it was not done within 30 days as per Section 12 Sub Section 11 as discussed above. Not only that the interim order was restored on 22ndJuly, 2015. Sub-Section 10 of the Section 12 of the said
15
Act prescribed that entire process should be completed within 30 days but in the present case it was done by the authority beyond 30 days. It is also evident from records that 30 days starts from submission of Motion, admittedly on 19thDecember, 2014 2ndMotion was submitted and it is also an admitted fact that earlier notice was issued on 24th September, 2014 and the same is still alive as per sub-Section 11 of Section 12 of the said Act, the second notice is thus statutorily barred, since the earlier Motion was still pending for adjudication.
20. I cannot overlook that the provision of Section 12 is mandatory in nature. Therefore any subsequent action taken on the basis of the notice dated 24thNovember, 2014 should be set aside
21. I also cannot ignore the fact that the 2ndMotion dated 19th December, 2014 was issued within the period of one year, therefore, the 2ndMotion is bad in law as the 1stMotion was issued on 24thSeptember, 2014 and the 2ndMotion was issued on 19thDecember, 2014 which is not permissible in law.
22. It is also cannot ignored that from 2ndJanuary, 2015 till 30th March, 2015 interim order passed by this Hon'ble Court was very much in force, therefore, that period should have been excluded from 30 days which starts from 19thDecember, 2014. That being the scenario the
16
impugned removal order passed on 14thJuly, 2015 beyond 30 days as per statute cannot be sustained in the eye of law and stands vitiated.
23. I have considered the citation relied on by Mr. Dutta that decision adopted by the majority should be accepted. But the situation of the case in hand is something otherwise. The Court has to only concentrate on the issue whether sub-Section 10 and 11 of Section 12 of the said Act has been complied with or not. Admittedly, the provisions of sub-Section 11 of Section 12 has not been complied with in the present case by the authority at the time of passing the removal order. Sub- Section 11 of Section 12 of the said Act clearly provides that no meeting for the removal of Pradhan or the Upa-Pradhan under Section 12 shall be conveyed within a period of one year from the date of election of the Pradhan or the Upa Pradhan.
24. On the basis of the above discussions I am of the view that the impugned memo dated 14thJuly, 2015 passed by the prescribed authority and Block Development Officer, Hemtabad Development Block, Hemtbad, Dist-Uttar Dinajpur thus accepting the resolution of the meeting for removing the petitioner from the office of the Pradhan of Bishnupur Gram Panchayat and thereby to declare the office of Pradhan stands vacated with immediate effect cannot be sustained in the eye of law.
17
25. Accordingly the impugned order dated 14thJuly, 2015 passed by the prescribed authority and B.D.O is set aside and quashed. Needless to mention that since the election of new Pradhan is not a subject matter of challenge before this Court and also the Hon'ble Division Bench by order dated 10thAugust, 2015 passed in A.S.T No.220 of 2015 and A.S.T.A No.132 of 2015 only directed the petitioner to challenge the removal order in a separate proceedings in accordance with law. Therefore, in the present writ petition Court cannot pass any order in respect of election of new Pradhan, but that will not preclude the writ petitioner from challenging the election of new Pradhan in a separate proceedings in accordance with law if she is entitled to.
26. With this direction this writ petition is allowed without any order as to costs.
18
27. Urgent photostat certified copy of this judgment, if applied for, be supplied to the parties after fulfilling all the formalities. (Samapti Chatterjee, J)
19