Hotel Satkar Pvt. Ltd. v. Bihar State Electricity Board & Others

Patna High Court
Sep 7, 1979
Smart Summary (Beta)

Structured Summary of the Opinion — S.K. Jha & R.P. Mandal, JJ.

Factual and Procedural Background

This writ application under Articles 226 and 227 of the Constitution challenges a demand-cum-notice dated 10th/12th May, 1979 (Annexure‑1) issued by Respondent No.1, the Bihar State Electricity Board ("the Board"), threatening disconnection after seven clear days for alleged unpaid electrical charges amounting to Rs. 3,01,449.30 up to March 1979.

The petitioner is a 5‑Star hotel whose premises were energised and supplied electrical energy by the Board from October 1976. Supply began after the petitioner submitted two "green cards" showing installations certified by engineers/contractors; a tri-sector meter (combining maximum demand indicator, kva meter and unit meter) was installed.

There is factual controversy about whether a formal agreement for supply (high-tension agreement) was ever executed by the Board. The petitioner says it signed and forwarded a fresh agreement (allegedly showing 100 kva maximum demand) while the Board denies any executed agreement. Billing disputes arose concerning whether charges should be based on actual recorded maximum demand (generally about 86–88 kva) or on 75% of an asserted 315 kva maximum demand (approximately 236.5 kva).

The petitioner protested inflated/faulty bills on multiple occasions. A Technical Committee of the Board examined the meter and calculations and, by its report dated 12.3.78 (Annexure‑6), revised bills for April–September 1977 to amounts based on actual recorded demand (86–88 kva). Despite some periods when billing was on actual demand (October 1977–March 1978), from April 1978 to March 1979 bills were again issued on the 75% of 315 kva basis, precipitating the impugned demand/notice under Section 24(1) of the Indian Electricity Act, 1910.

The petitioner filed this writ seeking quashing of the notice and protection from disconnection; the bench was called upon to determine the true scope of Section 24(1) (first part) of the Act and whether the threatened disconnection was tainted with illegality given the existence of a bonafide dispute.

Legal Issues Presented

  1. What is the true content and scope of Section 24(1) (first part) of the Indian Electricity Act, 1910, in the circumstances of this case?
  2. Whether the threat of disconnection after giving seven clear days' notice (as in Annexure‑1) is illegal or consonant with Section 24(1) when there exists a bonafide dispute between a licensee and a consumer.
  3. If a bonafide dispute exists regarding (a) the existence/terms of an agreement between licensee and consumer or (b) the correct mode of computation of maximum demand/consumption, can the consumer be said to have "neglected to pay" and thereby lawfully subjected to disconnection under Section 24(1)?

Arguments of the Parties

Petitioner's Arguments (Mr. A.K. Sen)

  • The present case is one in which the bonafide of the dispute is clear from the materials on record.
  • The petitioner contends that it had executed and forwarded a fresh agreement (alleged to fix maximum demand at 100 kva) and that the bills served on the basis of 75% of 315 kva are inflated and inconsistent with actual recorded consumption.
  • The petitioner repeatedly protested the bills by letters (Annexures‑11, 13, 18, 18A, 18B) asserting faulty and inflated billing and seeking rectification; the Board did not respond to these protests.

Respondents' Arguments (Mr. Dinesh Charan)

  • The respondents (Board) initially contended there was no bonafide dispute and sought to argue that a concluded agreement or contract could be inferred from correspondence; that attempt was later abandoned.
  • The Board's pleaded position in the counter‑affidavit is that no agreement was ever executed in favour of the petitioner; a letter of the Resident Engineer (11.3.78; Annexure‑17 to rejoinder) expressly requested execution of a fresh agreement.
  • The respondents relied on applicable tariff rules (Bihar State Electricity Board Tariff, 1975) which provide that for the first twelve months to a new point of supply the maximum demand charge will be based on actual maximum demand, implying that thereafter other rules (such as 75% of applied demand) could apply if an agreement exists.
  • When confronted with inconsistent billing by the Board (actual billing for Oct 1977–Mar 1978 despite their asserted position), learned counsel suggested this may have been due to a gross mistake by Board officers rather than a deliberate departure from tariff rules.
  • At the Bar the respondents' counsel conceded that if there is a bonafide dispute between licensee and consumer, Section 24(1) (first part) will not apply unless the controversy is resolved at a proper forum in accordance with law.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court in this Opinion
Mayor & Co. of Westminster v. London and North Western Railway Company (1905) A.C. 426 (Lord Macnaghten) Public/statutory bodies must act in good faith, within limits of authority and must not exceed or abuse statutory powers. Cited to underline that the statutory Board must act in good faith and within its authority when exercising power to disconnect or demand payment; supports scrutiny of Board's conduct in this case.
Corporation of the City of Nagpur v. The Nagpur Electric Light and Power Company Ltd. (A.I.R. 1958 Bombay 498) Authority for the proposition that where there is a reasonable belief or justifiable reason leading to a bonafide dispute between licensee and consumer, the first part of Section 24(1) should not be applied to effect disconnection. Relied on by the petitioner and accepted by the Court as one of the decisions affirming that a bonafide dispute prevents summary disconnection under Section 24(1); used to support quashing the notice.
Maharashtra State Electricity Board v. Madhusudandas and Brothers (A.I.R. 1966 Bombay 160) Same principle: existence of bonafide dispute excludes the operation of Section 24(1) first part for disconnection. Relied upon to show consistent judicial view that disconnection is not lawful where a bonafide dispute exists; assisted the Court's conclusion to grant relief to the petitioner.
Hindustan Aluminium Corporation Ltd. v. The U.P. State Electricity Board (A.I.R. 1973 Allahabad 263) Same principle: recognition that a reasonable bonafide dispute bars application of Section 24(1) first part for immediate disconnection. Referenced as supporting authority for the Court's approach that a bonafide dispute defeats the characterization of the consumer as having "neglected to pay" for the purposes of Section 24(1).
Orissa Fibre v. The Orissa State Electricity Board (A.I.R. 1973 Orissa 104) Same principle: where bonafide dispute exists between licensee and consumer, disconnection under the first part of Section 24(1) is not appropriate. Used to demonstrate consistent High Court authority endorsing protection for consumers facing disputed bills; formed part of the precedential foundation for quashing the impugned notice.

Court's Reasoning and Analysis

The Court proceeded by identifying the precise legal question: whether the threat of disconnection after giving seven clear days' notice (Section 24(1), first part) as in Annexure‑1 was tainted by illegality when a bonafide dispute existed between licensee and consumer.

At the outset the Court recorded that learned counsel for the respondents conceded that if a bonafide dispute exists between a licensee and a consumer Section 24(1) (first part) would not apply unless the dispute were resolved at a proper forum and in accordance with law. The Court therefore focused on whether such a bonafide dispute existed on the material before it.

The Court examined uncontested facts and documentary material (or absence thereof): (a) supply commenced in October 1976 after submission of green cards and installation of a tri‑sector meter; (b) an application dated 19.11.1975 and a high tension agreement form signed by the petitioner were produced but the Board did not execute the agreement; (c) the billing history showed periods billed on actual recorded demand (86–95 kva) and other periods when bills were raised on 75% of 315 kva (236.5 kva), with disputes and protests being made by the petitioner; (d) the meter experienced defects and was changed several times; and (e) the Technical Committee examined the matter and revised bills for April–September 1977 to actual recorded demands (Annexure‑6).

The Court emphasised the factual inconsistencies in the Board's billing practice (for example, billing on actual demand for Oct 1977–Mar 1978, then reverting to inflated billing from Apr 1978–Mar 1979) and the Board's inability to give a satisfactory explanation other than to suggest officer error. The Court concluded that there was an irresistibly reasonable inference that the petitioner had a bonafide belief that the bills for April 1978–March 1979 were not in accordance with law (whether due to miscalculation, erroneous presumption of an agreement for 315 kva, or other reasons).

To address whether the petitioner had "neglected to pay" as required to trigger Section 24(1), the Court analysed the ordinary meaning of "neglect" and "negligence" (referencing Stroud's Judicial Dictionary) and held that neglect presupposes breach of a duty or obligation. Given the bonafide dispute about liability and billing, the Court found there was no neglect or default on the part of the petitioner.

The Court further relied on the settled principle that statutory bodies must act in good faith and within the limits of their authority (citing Lord Macnaghten in Mayor & Co. of Westminster v. LNWR) and on several High Court decisions that uniformly hold that where a bonafide dispute exists between licensee and consumer the first part of Section 24(1) does not apply to justify summary disconnection.

On this legal and factual matrix the Court concluded that a bonafide dispute existed and that application of the first part of Section 24(1) to disconnect the petitioner's supply would be impermissible.

Holding and Implications

APPLICATION ALLOWED — NOTICE QUASHED; WRIT OF MANDAMUS ISSUED.

Holding (core ruling): The Court allowed the writ application, quashed the demand/notice dated 10th/12th May, 1979 (Annexure‑1) which threatened disconnection under Section 24(1) of the Indian Electricity Act, 1910, and issued a writ of mandamus restraining the respondents from disconnecting the petitioner's electricity supply so long as a bonafide dispute remained unresolved by a court of competent jurisdiction or otherwise resolved according to law.

Immediate consequences for the parties:

  • The respondents are commanded not to disconnect the petitioner's electricity supply while the bonafide dispute persists and remains unresolved by lawful process.
  • Until such dispute is resolved, and in the absence of any express contractual provision to the contrary or tariff changes, the petitioner shall be liable to be charged only on the basis of actual consumption as indicated by the maximum demand indicator (i.e., the readings recorded by the meter or as adjusted by the Technical Committee).
  • No order as to costs was made by the Court.

Broader implications: The Court applied established principles (including those cited decisions) that protect consumers from summary disconnection under Section 24(1) where a reasonable, bonafide dispute exists regarding liability or computation of charges. The opinion reinforces that statutory licensees must act in good faith and within authority when enforcing payment and disconnecting supply. The Court did not purport to create new law but applied existing authorities to the facts before it.

Application allowed.
Show all summary ...

S.K Jha & R.P Mandal, JJ.:— In this application under Articles 226 and 227 of the Constitution of India, the plain and simple question Involved is as to the true content and scope of Section 24(1) (first part) of the Indian Electricity Act, 1910 (Act 9 of 1910) hereinafter to be referred to as the Act. Respondent No. 1 the Bihar State Electricity Board (to be called “the Board” hereinafter) is a statutory body and a licensee under the provision of the Electricity (Supply) Act, 1948 (Act 54 of 1948) read with the Act and the other respondents are its officers. The petitioner is a consumer of electrical energy supplied to it, electrical installations having been set up and energised in the premises of the petitioner from the month of October, 1976. The prayer made in this writ application is for the issuance of an appropriate writ direction quashing the notice served by the licensee Board, respondent No. 1 on the petitioner by a letter-cum-notice dated 10th/12th May, 1979, a copy whereof has been incorporated in Annexure 1 to the writ petition.

2. The only question which calls for our decision in this case is as to whether the threat of disconnection after giving 7 clear days' notice as contained in Annexure-1 served by respondent No. 1 on the petitioner is tainted with illegality or can be said to be in consonance with the provisions of Section 24(1) (first para) of the Act. At this place, in view of the submissions made at the Bar, it would be proper for us to indicate at the outset that learned counsel for the respondents did not contest rather conceded that, if there was a bonafide dispute between a licensee and a consumer of electrical energy, then the provisions of Section 24(1) (first part) of the Act will not apply, unless the controversy or the dispute is resolved at a proper forum and in accordance with law.

3. While, on the one hand, Mr. A.K Sen, learned counsel for the petitioner, has confined his submission only to one legal aspect Involved; namely; that the instant case is one of those cases in which the bonafide of the dispute is writ large on the materials on record, on the contrary, Mr. Dinesh Charan, learned counsel for the respondents, has tried to persuade us to hold that there was no bonafide dispute at all. Indeed, learned counsel for the respondents at one stage wanted us to go a step further and hold that on the facts and in the circumstances of the case there was a concluded agreement or contract between the parties (namely the petitioner and respondent no. 1), the terms of which can be called from pieces for correspondence. He also fairely admitted that the so-called pieces of correspondence were only unilateral, namely, letters sent by way of protest from the petitioner from time to time of which we shall take notice at an appropriate and apt place.

4. The submission of learned counsel for the respondents as aforesaid with regard to an inference of a concluded agreement to be drawn from the pieces of correspondence available on the record seems to have been rightly abandoned in this proceeding. This we say on account of the admitted fact that in the counter affidavit the stand taken by the respondent Board is that there was no agreement entered into at any time between the parties over since the date of the energisation of the installations in the petitioner's premises. A letter written by the Resident Engineer of the Patna Electric Supply Undertaking, which is a unit of the Board, dated 11th March, 1978, a copy whereof has been marked annexure-17 to the petitioner's rejoinder to the counter affidavit filed on behalf of the respondents, clearly states in express terms that the petitioner must execute “a fresh agreement in the prescribed form as required to be executed vide para-6-164 of the Board's Financial And Accounts Code, Chapter VI”. Whereas the petitioner's stand is that it had done its part of the job by signing the agreement and handing it over to an officer who was duly authorised in that behalf by the Board, that fact has been expressly controverted in the counter affidavit. But that is a later part of the story.

5. To begin at the beginning, first we are confining ourselves to the non-controversial facts. These can shortly be stated thus. The petitioner, a 5-Star Hotel, having been set up with the financial help of the Bihar State Financial Corporation and sponsored by the Department of Tourism of the Government of India, after completion of the building, sent two green cards for the purpose of making an application to the licensee requiring it to supply electrical energy in accordance with the legal formality. The two green cards, which have not been placed on the record of this case, have been shown to us, after permission was accorded to learned counsel for the respondents to produce them before us, to indicate that both the green cards after the installation of the electrical appliances duly energised were certified by the competent engineers and contractors, K.K Gupta and Company. On the basis of the two green cards submitted, as we have already stated earlier, the petitioner's premises began to be supplied electrical energy and a trisector meter was installed in its premises by the licensee Board and the supply started from October, 1976. A trisector meter admittedly, is a combination of 3 meters performing 3 distinct functions:—

(i) a maximum demand indicator,

(ii) a meter which reads the maximum load availed of in terms of kilovolt ampere (kva) and

(iii) the actual units of electrical energy consumed.

6. Admittedly, although the supply started from October, 1976, an application filed by the petitioner to the Resident Engineer of the Patna Electric Supply Undertaking, unit of the Board, on 19th November, 1975. This application has also not been produced before us by learned counsel for the respondents and does not form part of the record. The fact, however, that on that date such an application had been filed is accepted by the petitioner also. Subsequent to the application, an agreement duly filled up and signed on behalf of the petitioner by persons authorised in that behalf was sent to the Board, but it now transpires, as learned counsel for the respondents himself has stated, that the agreement was never executed by or on behalf of the licensee. The high tension (H.T) agreement form duly signed by persons authorised to do so on behalf of the petitioner has also been produced by learned counsel for the petitioner before us. It would have been more formal a ad factual if those documents, for whatever worth they are, would have been annexed to the counter affidavit of the respondents after laying down the foundational facts for such annexures to be so appended in the recitals or contents of the counter affidavit itself. We ordinarily and generally feel reluctant to look to any document which does not form part of record of the case. In this case, however, since it would be merely piling unreason upon technicality if we insist upon such a technicality and specially on account of the fact that Mr. Sen did not object to learned counsel for the respondents producing these documents for our perusal, we have taken note of them. In nutshell, in July, 1976 green cards by competent electrical engineers were filed, the application of the petitioner to the licensee was filed on 19th November, 1975 and an agreement was to be executed thereafter which, it seems, was never executed at all. And, yet, in the meantime, the licensee Board respondent No. 1 energised the petitioner's premises and began to feed it with electrical energy from the month of October, 1976. That is the first chapter of this case.

7. Admittedly again any variation either due to the defective functioning of the meter resulting in a worng reading of the kva indicated by the maximum demand indicator as well as the load factor availed of on any particular day of month is bound to culminate in a variation of the electrical energy consumed by any consumer. For the period-from October, 1976 to March, 1977 every monthly bill was served on the petitioner on the basis of the actual kva consumed by the petitioner as shown and recorded in the trisector meter installed in us premises by the licensee Board. The actual demand as registered by the meter varied between 86 and 95 kva with exceptions with regard to a few months, which are not material for the purpose of the issue at hand. To continue the narration for April and May, 1977 the original bills were sent to the petitioner on the basis of 75 per cent of 315 kva which would come to about 2365 kva. This was on an assumption by the licensee respondent that there had been an agreement between the parties for a maximum demand of 315 kva although, in fact, as we have already indicated earlier, there has been no agreement whatsoever. The petitioner objected to the bills for these two months and on such an objection the bills were revised and the amount of demand reduced, as the petitioner had requested, on the basis of actual consumption in terms of kva as registered by the meter. Again, for the months of June, August, September, October and November, 1977 (i.e from May, 1977 to November, 1977 excepting July) the petitioner was served with bills on the basis of 75 percent of the maximum demand of 315 kva. But, curiously enough, for the month of July the bill was submitted on the basis again of actual consumption recorded by the meter at about 88 kva. The petitioner again protested and as a result of such protest the Technical Committee of the licensee respondent No. 1, which goes into such questions wherever there is a protest on the ground of wrong billing on account of either wrong functioning of meter or otherwise was mobilised and on 12.3.78 it passed an order which is incorporated in Annexure 6 to the writ application. Paragraph 10 of the document marked Annexure 6 presents an interesting reading which is quoted below:—

“10. From the above observations as well as from detailed calculations made from the hours of working of the airconditioning plant (obtained from the log book maintained at the installation), the energy recorded and the average power factor, the Maximum Demands at the installation during the disputed period, i.e From April, ’77 to September, ’77 have been revised as follows:—

April, ’77 86 KVA May, ’77 86 KVA June, ’77 86 KVA July, ’77 86 KVA August, ’77 88 KVA September, ’77 88 KVA

It may be mentioned at this stage that error in Maximum demand indicator of the first three combined meters which were primarily due to defect in the timing mechanism of the meter had no bearing on the unit consumptions recorded in the meters. Only in April, ’77 there had been a mis-calculation of unit consumption as stated in para 5 above, which has already been taken into consideration. In the circumstances explained above, you will appreciate that there is no further scope for adjustment in your bills; as demanded.”

8. That explains how the bills for the period April, 1977 to September, 1977—were revised on the basis of actual consumption. The recitals of this document further show that the meter which had been installed at the petitioner's premises was defective. It is admitted that the meter installed had to be changed three months by the licensee every time when it was pointed out to the licensee, respondent No. 1, by the petitioner that the meter was not functioning properly. But that is neither here nor there. The bone of contention between the parties is as to whether, since the petitioner in its application dated 19th November, 1975, mentioned earlier, had shown the total consumption load applied for at 315 Kva, the petitioner was liable to be charged at the rate of 75 per cent of 315 Kva or at the rate of actual consumption or, as had been done, as already stated earlier, up to March, 1977 and again as the rectified bill of April, 1977 shows. This was the main point of controversy although the defective reading of the meter was also pointed out and hence the Technical Committee of the respondent licensee having examined the matter thoroughly in its report order dated 12.3.78 (Annexure-6) revised the bills for the months of June, August and September, 1977 and reduced the monthly bills as submitted at the rate of 75 percent of 315 kva to the actual consumption recorded or calculated by the technical staff, which came to 86 or 88.

9. The controversy begins now. Whereas the petitioner says that at the Instance of the Resident Engineer, to whose letter dated 11.3.78 a reference has been made earlier, namely, annexure-17 to the petitioner's rejoinder, insisting that the petitioner do enter into a fresh agreement, the petitioner had actually filed a fresh agreement whereto the maximum demand of supply was agreed at the figure 100 kva, the stand taken by the respondents in the counter affidavit is that there was no such agreement in existence. We, therefore, proceed upon the assumption, without any prejudice to the rights of the parties to raise the question of existence or otherwise of any agreement entered into between the parties either in a formal document or through correspondence before a proper forum, that there was no such agreement in existence. The respondents say that under the relevant tariff rules as applicable at the relevant time, namely, the Bihar State Electricity Board Tariff, 1975 (published in the Bihar Gazettee Extras ordinary no. 842 dated 25th July, 1975) it is stated at page 36 in the Explanation:—

“For the first twelve months of service to a new point of supply of the maximum demand charge for the month will, however, be based on the actual maximum demand for that month.”

10. It would also be not out of place to mention here that admittedly the petitioner is covered by the term ‘High Tension Service’ and Tariff applicable for the purpose of billing of the petitioner's consumption would be symbol H.T.G-1 as described at page 23 of the 1975 Tariff. It would also be pertinent to state that admittedly the petitioner is availing of 50 cycles A.C (alternate current) and 3 phase service at 6.6 kv (6,600 Volts). The point, therefore, that the petitioner is liable to be charged at the tariff prescribed for symbol H.T.G-1 at page 23 of the 1975 Tariff is not debatable. The stand of the respondents is that in accordance with the Explanation extracted above at page 36 of the Tariff, the bills for the first 12 months on the basis of the actual consumption had to be revised whenever the bills had been submitted originally on the basis of 315 kva maximum demand, 75 per cent of which came to 236.5 kva or so. This being the specific case of the respondents, it is curious as to how even for the months after September, 1977 the respondents submitted bills to the petitioner right upto the month of March, 1978 on the basis of actual consumption showed in terms of kva by the maximum demand Indicator. The revised bills for the months of June to November, 1977 excepting July, which was originally already served on the basis of the actual consumption, have been marked annexures 7 series to the application whereas the original faulty bills have been marked annexure-4 series. But for the period from December, 1977 to March, 1978 the original bills submitted to the petitioner by the licensee board were on the basis of the actual consumption recorded by the trisector meter which was generally and ordinarily in the neighbourhood of 86 to 88 kva excepting during one month or two months wherein, for whatever reason it may be, the meter showed a lesser consumption in terms of kva as indicated by the maximum demand indicator. When we confronted learned counsel for the respondents with a query as to how, when on their admitted case the petitioner was being billed and was liable to be billed for the period of first 12 months on the basis of the actual consumption whereafter for the subsequent period in accordance with an agreement which never came into existence, were the bills sent to the petitioner for the months of October, 1977 to March, 1978 on the basis of the actual consumption recorded, learned counsel was not able to give us any satisfactory explanation. All that he contended was that it may have been on account of gross mistake on the part of the officers/employees of the Board. All on a sudden, from the month of April, 1978 upto the month of March, 1979 again bills were sent to the petitioner on the basis of 75 percent of 315 kva maximum demand. As has already been stated earlier, according to the petitioner's case, a fresh agreement had already been entered into or at least executed on its own part in August, 1978 and sent to the Board, but the Board has come with a definite stand that there is in existence no such agreement. If that be so, and if there was never any agreement entered into between the parties, we fail to appreciate as to how and on what basis the bills from April, 1978 upto March, 1979 were Inflated from the neighbourhood of 86 to 88 kva maximum demand to 236.5 kva equal to 75 percent of 315 kva. Learned counsel for the respondents tried to persuade us to hold that the petitioner having applied on 19th November, 1975 had shown that it required supply of load factor at 315 kva, it should be presumed that there was a tacit understanding between the parties that the petitioner would be liable to be charged after the period of first 12 months from that date at the rate of 75 per cent of 315 kva. This again is Irreconcilable with the bills submitted to the petitioner for the months of October, 1977 to March, 1978. Obviously, therefore, to say the least—and we may not be deemed to have decided the question in any manner finally—there was some mistake somewhere on the part of the licensee Board in the matter of calculation whatever be the basis for such method of computation. But, as we were saying, there is little scope for doubt for this Court to come to a conclusion that there was a bonafide belief in the mind of the petitioner that it was liable to be charged even after the month of September, 1977 upto the month of March, 1979 at the rats of actual recording registered by the trisector meter in so far as maximum demand indicator is concerned. Learned counsel for the respondents, although half-heartedly, submitted, as already hinted at earlier, that the act of parties shows that the petitioner had been given the electrical energy on a tacit understanding that it was to be charged at 75 percent of 315 kva maximum demand. In support of our conclusion that there was and is such a bonafide dispute, there are some more materials on the record which are worth mentioning. In spite of the stand of the respondents in the counter affidavit that there was no fresh agreement entered into between the pasties and duly executed by them in August, 1978, the letters dated 10.8.78, 20.3.79, 16.9.78, 26.9.78 and 22.1.79 the first to marked respectively Annexures-11 and 13 to the original writ application and the last three respectively appended as Annexure-18, 18A and 18B to the petitioner's rejoinder to the counter affidavit filed on behalf of the respondents, all point to one single fact that the petitioner was all along crying hoarse from the housetop that it was being served with faulty and inflated bills which were not in consonance with the fresh agreement sent by it (petitioner) in August, 1978 (which was for 100 kva maximum demand) at the rate of 75 per cent of 315 kva. The respondent licensee or any of its officers respondents never chose to send any reply to any of the letters of protest or complaint or grievance sent by the petitioner as contained in Annexure 11 and 13 to the original writ application and those marked Annexures-18, 18A and 18B to the petitioner's rejoinder.

11. Then came the impugned letter of demand-cum-notice purported to have been served under Section 24(1) (first part) of the Act. In the Impugned letter/notice addressed by the respondents to the petitioner accumulated arrear to the tune of Rs. 3,01,449.30 paise upto March, 1979 has been billed for and the petitioner has been requested or directed to clear off the dues within 7 days of the issue of the letter dated 10/12.5.79, falling which the supply of energy to the petitioner's installation will be disconnected without any further reference to the Board. We have already held that there is a bonafide dispute with regard either (i) to the existence of an agreement or a concluded contract between the parties (ii) to the method or mode of computation of consumption of electric energy in terms of kva with its concomitant and resultant variation in the figure showing consumption of electrical energy by the petitioner. The relevant part of Section 2(1) of the Act reads thus:—

“24(1) Where any person neglects to pay any charge for energy or any sum; other than a charge for energy, due from him to a licensee in respect of the supply of energy to him, the licensee may, after giving not less than seven clear days' notice in writing to such person and without prejudice to his right to recover such charge or other sum by suit, out of the supply—”

12. The question is: if there is a bonafide dispute with regard to either of the two matters aforesaid, can it be said that the petitioner is a person who has neglected to pay any charge for the energy? The answer, in our view, is obviously in favour of the petitioner that there has been no such neglect. ‘Neglect’ or ‘default’ connotes something like the breach of a duty or legal obligation existing at the time (vide Stroud's Judicial Dictionary, Vol. 3. Third Edition, page 1880), and ‘negligence’, not being an affirmative word, connotes “the absence of such care, skill and dellgence, as it was the duty of the person to bring to the performance of the work which he is said not to have performed “or” negligence is the omitting to do something that a reasonable man would do, or the doing something which a reasonable man would not do” (ibid page-1881). From the conduct of the parties-more from the conduct of the respondents themselves—it is abundantly clear and an inference is Irresistible that there is a bonafide belief in the mind of the petitioner and, justifiably, so that the billings for the period from April, 1978 to March, 1979 have not been made in accordance with law, whether on account of miscalculation or on account of illegal or unfactual presumption of an agreement for 315 kva maximum demand supply or for some other reason best known to the respondents. The respondent Board being a statutory body, it is well settled that it must take care, like all public bodies invested with statutory power, not to exceed or abuse its powers and it must keep within the limits of authority committed to it. It has been repeatedly—stated and it is trite law by now—that it must act in good faith and reasonable—refer to Lord Macnaughten in Mayor, & Co. of Westminister v. London and North Western Railway Company (1905) A.C 426 at p. 430. Decisions of various Courts of law are all one sided in favour of the petitioner. The decisions relied upon by learned counsel for the petitioner are those in the cases in (1) Corporation of the City of Nagpur v. The Nagpur Electric Light and Power Company Ltd. (A.I.R 1958 Bombay 498). (2) Maharashtra State Electricity Board v. Madhusudandas and Brothers (A.I.R 1966 Bombay 160), (3) Hindustan Aluminium Corporation Ltd.… v. The U.P State Electricity Board…. (A.I.R 1973 Allahabad 263) and (4) Orissa Fibre v. The Orissa State Electricity Board (A.I.R 1973 Orissa 104); the two decisions of the Bombay High Court and that of the Orissa High Court are the Bench decisions were as the Allahabad decision is that of a single Judge. There is absolutely no doubt expressed in any of these decisions that; where there is a reasonable belief or justifiable reason or cause leading to a bonafide dispute between the licensee and the consumer, there is any scope for application of the first part of Section 24(1) of the Act. These decisions have rightly been pressed into service by learned counsel for the petitioner.

13. In the result, therefore, we are constrained to allow this application and quash the notice of demand and threat of disconnection as contained in the impugned letter/notice (Annexure-1) and the respondents are commanded by a writ of mandamus not to disconnect the electricity supply line of the petitioner so long as the bonafide dispute is not resolved by a court of competent jurisdiction or resolved in any other legal manner which the respondents may choose to resort to. It is further directed that till such a dispute is resolved and in the absence of any express stipulation in an express agreement to the contrary and due to any Increase in the tariff rates the petitioner shall be liable to be charged only on the basis of actual consumption in terms of the maximum demand indication. In the circumstances of the case, however, we shall make no order as to cost.

Application allowed.