- Bookmark
- Share
- CaseIQ
Ladli Construction Company Private Limited v. Punjab Police Housing Corporation Limited And Others
Factual and Procedural Background
The appellant-contractor entered into an agreement with the Punjab Police Housing Corporation for construction of 240 Type II-A houses in Ludhiana, valued at approximately Rs 273.84 lakhs. Clause 2 made time “of the essence.” When the contractor failed to meet the schedule, the Corporation rescinded the contract on 8-5-1991 under Clause 3 and re-allotted the balance work.
Invoking Clause 25-A, the contractor moved the Sub-Judge, Chandigarh, for appointment of an arbitrator. On 13-5-1992 the court appointed the Chief Engineer of the Corporation—the very officer named in Clause 25-A—as sole arbitrator and allowed both parties to lodge claims and counter-claims. The Corporation filed its claim on 15-6-1992; the contractor refused to participate, alleging potential bias, and instead applied on 24-7-1992 for the arbitrator’s removal.
With no stay obtained, the arbitrator proceeded ex parte and made an award on 18-8-1992. The Sub-Judge (8-5-1995) dismissed the contractor’s removal application, made the award rule of court, and passed a decree. Both the District Judge (19-9-1998) and the Punjab & Haryana High Court (25-11-2002) affirmed that order. The present appeal before the Supreme Court arose by special leave under Article 136 of the Constitution.
Legal Issues Presented
- Whether the Chief Engineer of the Corporation, named as sole arbitrator in Clause 25-A, was disqualified by bias—actual or apprehended—and therefore liable to be removed.
- Whether the ex-parte award dated 18-8-1992 suffered from “misconduct” warranting being set aside, particularly on the grounds that (a) the arbitration agreement was not before the arbitrator and (b) amounts not claimed were awarded.
- Consequentially, whether the courts below erred in making the award a rule of court and in dismissing the contractor’s objections.
Arguments of the Parties
Appellant–Contractor
- The Chief Engineer had earlier inspected the work and allegedly instigated termination of the contract, giving rise to a reasonable apprehension of bias.
- Arbitral proceedings were concluded within an unduly short span (49 days), while an application for his removal was pending, demonstrating predisposition.
- The arbitration agreement itself was never placed before the arbitrator, yet he commenced proceedings.
- The award included return of unutilised secured advance that had not been claimed, evidencing partiality.
- Post-award conduct—specifically, the arbitrator contesting the appeal by filing a counter-affidavit—reinforced the charge of bias.
- Reliance placed on Gullapalli Nageswara Rao v. A.P. SRTC (AIR 1959 SC 308) and Bristol Corporation v. John Aird & Co. (1913 AC 241) to underscore the need for impartial adjudicators.
Respondents–Corporation & Executive Engineer
- Supported the concurrent findings of the Sub-Judge, District Judge, and High Court that no valid ground of bias was made out.
- Emphasised that only two points—both already considered by the High Court—were urged, and no fresh grounds could be entertained.
- Pointed out the contractor’s conscious agreement to the arbitration clause and its initial request that the Chief Engineer be appointed.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Gullapalli Nageswara Rao v. A.P. SRTC AIR 1959 SC 308 |
Decision-maker must be free from bias; natural justice. | Court accepted the principle but held the contractor failed to establish any factual basis for bias. |
| Bristol Corporation v. John Aird & Co. 1913 AC 241 (HL) |
A contractor who contractually agrees to arbitration by an engineer is bound, unless real likelihood of bias is shown. | Quoted to reinforce that merely being an employee of one party is insufficient; no “reasonable prospect” of bias was demonstrated. |
| Secy. to Govt., Transport Deptt. v. Munuswamy Mudaliar 1988 Supp SCC 651 |
Named arbitrator will not be removed absent cogent material showing bias; vague apprehensions are inadequate. | Relied on to reject the contractor’s general allegations and uphold the arbitrator’s appointment. |
| International Airports Authority of India v. K.D. Bali (1988) 2 SCC 360 |
Need “reasonable evidence” of a “real likelihood of bias”; whimsical suspicions not enough. | Cited to conclude that the contractor’s fear of bias was speculative and unsupported by evidence. |
| S. Rajan v. State of Kerala (1992) 3 SCC 608 |
When agreement specifies a particular arbitrator, courts must refer disputes to that arbitrator unless he refuses/fails to act. | Used to justify the Sub-Judge’s decision appointing the Chief Engineer and to negate the plea for substitution. |
Court's Reasoning and Analysis
1. Consent to the Arbitrator: Clause 25-A expressly named the Chief Engineer as arbitrator. The contractor, fully aware of the Chief Engineer’s supervisory role, not only signed the contract but also moved for his appointment. No allegation of bias was raised at that stage.
2. Conduct before the Arbitrator: After the Corporation filed its claim, the contractor refused to participate and delayed 26 days before seeking the arbitrator’s removal, yet obtained no stay. In absence of restraint orders, proceeding ex parte was justified.
3. Alleged Grounds of Bias: (a) Prior inspection and formation of opinion on slow progress was held “nothing unusual”; (b) the 49-day duration of proceedings was not per se indicative of hostility; (c) photocopy of the agreement was on record, undermining the claim that the arbitrator acted without seeing it; (d) award of unutilised secured advance was based on evidence and quantified by the District Judge, demonstrating no arbitrariness.
4. Legal Threshold for Bias: Applying the authorities cited, the Court reiterated that only a reasonable apprehension, founded on cogent material, warrants removal. The contractor’s assertions were “vague and general” and failed the objective “reasonable man” test.
5. Post-award Conduct: The arbitrator’s act of filing an affidavit after being impleaded was deemed a legitimate response to allegations, not evidence of predisposition.
6. Conclusion on Misconduct: Finding no procedural impropriety or violation of natural justice, the Court held the award untainted. Concurrent findings of the lower courts were affirmed.
Holding and Implications
Civil Appeal DISMISSED.
The award in favour of the Corporation remains enforceable, and the contractor’s challenge based on alleged bias fails. The decision underscores that parties who contractually designate an in-house official as arbitrator are bound by that choice unless concrete evidence of bias is produced; no new legal principle was created, but existing standards for bias in arbitration were reaffirmed.
R.M Lodha, J.— This appeal, by special leave, arises from the judgment and order dated 25-11-2002 passed by the Punjab and Haryana High Court.
2. The controversy arises in this way. A contract was entered into between the appellant, M/s Ladli Construction Co. (P) Ltd. (hereinafter referred to as “the contractor”), and Respondents 1 and 2, namely, Punjab Police Housing Corporation Ltd. and the Executive Engineer (Civil), Punjab Police Housing Corporation Ltd. (hereinafter referred to as “the Corporation”) for construction of 240 Type II-A houses at Urban Estate, Ludhiana at an estimated cost of Rs 273.84 lakhs. The contract provided in Clause 2 that time was of the essence of the contract and the time allowed for carrying out work as entered in the tender shall be strictly observed by contractor.
3. The contractor could not maintain the time schedule and the progress of the work was not observed. The contractor was directed to push up the progress of work but that also it failed to do. The contractor was notified that if it failed to take any action to show requisite progress by 30-4-1991, action against it under Clause 3 of the agreement would be taken. Still there was no requisite progress in execution of the work by the contractor.
4. On 8-5-1991, the Corporation resorted to action under Clause 3 of the contract, rescinded the contract and adopted further course by giving unexecuted work to another contractor. The disputes thus having arisen between the parties, the contractor moved the Court of the Sub-Judge, First Class, Chandigarh, for appointment of the arbitrator in terms of Clause 25-A of the contract.
5. On the application made by the contractor for appointment of the arbitrator, the Sub-Judge, on 13-5-1992, ordered that the matter in dispute may be referred for arbitration as per Clause 25-A of the agreement and, accordingly, as per the agreement and the statement of the parties, the Sub-Judge ordered the Chief Engineer of the Corporation to act as an arbitrator as provided under Clause 25-A of the agreement. Both the parties were permitted to file claim and counterclaim before the arbitrator.
6. In pursuance of the order dated 13-5-1992, the Corporation lodged its claim against the contractor on 15-6-1992. The arbitrator, the Chief Engineer of the Corporation called upon the contractor to appear before him on 25-6-1992. Thereafter also the arbitrator called upon the contractor to appear before him. The contractor, however, did not appear before the arbitrator and instead sent a letter on 29-6-1992 intimating him that his appointment as arbitrator was not acceptable to it; it did not expect any justice and fair play from him and he must refrain from acting as an arbitrator in the case.
7. Thereafter, on 24-7-1992, the contractor made an application before the Sub-Judge, Chandigarh under Sections 5, 11 and 12 of the Arbitration Act, 1940 (for short “the 1940 Act”) for removal of the arbitrator. The contractor did not appear before the arbitrator. Consequently, the arbitrator proceeded with the arbitration ex parte and passed the award on 18-8-1992. After filing of the award, the contractor submitted objections under Section 30 of the 1940 Act alleging misconduct on the part of the arbitrator and also objected to the award being made rule of the court. The Sub-Judge heard the two applications together: (i) application made by the contractor for removal of the arbitrator and objections under Section 30, and (ii) application for making the award rule of the court, and by a common order dated 8-5-1995 dismissed the application made by the contractor for removal of the arbitrator and made the award dated 18-8-1992 rule of the court and passed a decree in terms thereof.
8. The contractor challenged the common order dated 8-5-1995 passed by the Sub-Judge, Chandigarh in appeal before the District Judge, Chandigarh. The District Judge dismissed the appeal on 19-9-1998. Against these two concurrent judgments, the contractor filed civil revision before the High Court which too was dismissed on 25-11-2002. As noted above, it is from this order that the present appeal, by special leave, has arisen.
9. We have heard Mr Rajeev Sharma, learned counsel for the contractor, and Dr Balram Gupta, learned Senior Counsel for Respondents 1 and 2, Corporation.
10. Mr Rajeev Sharma, learned counsel for the contractor, strenuously urged that the contractor had reasonable apprehension of bias on the part of the arbitrator as the action of cancellation of contract was taken by the Executive Engineer at the behest of the arbitrator as he was the Chief Engineer of the Corporation. He referred to the inspection made by the Chief Engineer along with other engineers of the Corporation on 26-10-1990 and the opinion formed by the Chief Engineer on the basis of the inspection that the work was not being carried out by the contractor in accord with the time schedule. He also referred to the conduct of the arbitral proceedings by the arbitrator, particularly concluding the arbitration proceedings in a short span of about 49 days and that too when the contractor's application for his removal was pending before the court. In support of his submission that the arbitrator was biased against the contractor, the learned counsel also referred to the post-arbitral conduct of the arbitrator in contesting the appeal before this Court and filing counter-affidavit in opposition to the appeal.
11. Mr Rajeev Sharma would highlight two aspects viz. (i) the arbitration agreement was not placed before the arbitrator, yet he commenced and concluded the arbitral proceedings, and (ii) the award relating to unutilised amount of secured advance which was not claimed by the Corporation was passed, to indicate that the arbitrator was biased. In support of his submissions, the learned counsel relied upon a Constitution Bench judgment of this Court in Gullapalli Nageswara Rao v. A.P SRTC AIR 1959 SC 308, 1959 Supp (1) SCR 319 and a judgment of the House of Lords in Bristol Corpn. v. John Aird & Co. 1913 AC 241, (1911-13) All ER Rep 1076 (HL)
12. Dr Balram Gupta, learned Senior Counsel for the Corporation, supported the judgment of the High Court. He submitted that only two submissions were made before the High Court which have been noted and considered and no other point was urged.
13. The arbitration clause in the agreement i.e Clause 25-A, reads as follows:
“25-A. Arbitration, etc.—If any question, difference or objection whatsoever shall arise in any way connected with or arising out of this instrument of the meaning of operation of any part thereof or the rights, duties or liabilities of either party, then save insofar as the decision of any such matter is hereinbefore provided for and has been so decided, every such matter including whether its decision has been otherwise provided for and/or whether it has been finally decided accordingly, or whether the contract should be terminated or has been rightly terminated and as regards the rights and obligations of the parties as the results of such termination shall be referred for arbitration to the Chief Engineer of Punjab Police Housing Corporation, Chandigarh or acting as such at the time of reference within 180 days or in six months from the payment of the final bill to the contractor or from the date registered notice is sent to the contractor to the effect that his final bill is ready for payment and his decision shall be final and binding and where the matter involves a claim for or the payment or recovery or deduction of money, only the amount, if any, awarded in such arbitration shall be recoverable in respect of the matter so referred.”
14. The contractor consciously agreed for the disputes between the parties to be referred for arbitration to the Chief Engineer of the Corporation. The contractor, at the time of agreement, was in full knowledge of the fact that the Chief Engineer is under full control and supervision of all civil engineering affairs of the Corporation, yet it agreed for resolution of disputes between the parties by him as an arbitrator. It is a fact that the Chief Engineer inspected the progress of the work given to the contractor along with other engineers of the Corporation on 26-10-1990. In the course of inspection, the slow progress of the work was brought to the notice of the contractor on that date. There was nothing unusual about it and, as a matter of fact, on the contract being terminated on 8-5-1991, it was the contractor who made an application for appointment of arbitrator in terms of Clause 25-A of the agreement as it was well aware that the inspection by the arbitrator did not disqualify him to be the arbitrator.
15. In the application for appointment of arbitrator, no allegation of any bias or hostility was made against the named arbitrator i.e the Chief Engineer of the Corporation, rather the contractor prayed for appointment of arbitrator in terms of Arbitration Clause 25-A. When the application came up for consideration before the Sub-Judge on 13-5-1992, the advocate appearing for the contractor also submitted for appointment of the arbitrator as named in the agreement. Before the court, no allegation was made that the contract was terminated at the instance or behest of the Chief Engineer. These facts clearly show that no case of bias on the part of the Chief Engineer was pleaded or pressed by the contractor before the court in the proceedings for appointment of the arbitrator. There is nothing to indicate that something happened after 13-5-1992 which prompted the contractor to write to the arbitrator on 29-6-1992 that it had lost faith in him.
16. It is pertinent to notice that on 13-5-1992 while referring the disputes between the parties for arbitration as per Clause 25-A of the agreement, the contractor as well as the Corporation were permitted to file claim and counterclaim before the arbitrator. The Corporation filed its claim against the contractor on 15-6-1992. Upon receipt of the claim by the Corporation, the arbitrator called upon the contractor to appear before him on 25-6-1992. The contractor did not appear and instead sent a letter to the arbitrator on 29-6-1992 intimating him that his appointment as arbitrator was not acceptable. No steps were taken by the contractor for removal of the arbitrator immediately. The application for removal of the arbitrator was made almost after 26 days.
17. Although the contractor prayed before the Sub-Judge for stay of the proceedings before the arbitrator but it was not successful in getting any such order on 24-7-1992, or on the subsequent dates, namely, 30-7-1992, 3-8-1992 and 6-8-1992 from the court. In the absence of any stay order from the court and non-appearance by the contractor, the arbitrator was left with no choice but to proceed ex parte and conclude the arbitral proceedings. Merely because the award came to be passed on 18-8-1992 i.e a day before the next date fixed before the Sub-Judge, it cannot be said that the arbitrator concluded the proceedings hastily or he was biased.
18. The two aspects highlighted by Mr Rajeev Sharma, learned counsel for the contractor, regarding (i) non-availability of the agreement before the arbitrator, and (ii) the award of return of unutilised amount of secured advance by him, as grounds of bias have no merit at all.
19. The order dated 13-5-1992 passed by the Sub-Judge shows that photocopy of the arbitration agreement was produced before the court. AW 1, who was examined by the Corporation, in his deposition before the arbitrator, has stated that photocopy of the agreement was tendered to the arbitrator. Merely because copy of the agreement was not found by the District Judge in the record of the arbitral proceedings, it cannot be assumed that copy of the agreement between the parties was not placed for consideration before the arbitrator.
20. The arbitrator in his award has awarded interest in the sum of Rs 1,40,150 up to 31-12-1991 on the amount of secured advance paid to the contractor for the period the amount remained unutilised although the Corporation had claimed the interest on that count in the sum of Rs 1,69,878. With regard to award of unutilised amount of secured advance, the arbitrator observed in the award that the exact amount of award will depend upon the actual unutilised amount of secured advance till realisation. On ascertaining the total amount of unutilised secured advance, it was found to be Rs 9,63,635.25.
21. The District Judge in the appeal preferred by the contractor in challenging the judgment and decree, held in para 21 of the judgment thus:
“21. … In it unutilised advance of public health items as per statement at p. 243 of the arbitrator file is Rs 5,85,423.75p. The statement of this witness dated 14-8-1992 with statement of interest and principal of the unutilised secured advance of building component is at pp. 283-89 of the arbitration file in which unutilised secured advance of building component is mentioned as Rs 3,73,211.50p. So the total unutilised secured advance on both the counts comes to Rs 9,63,635.25p. The maxim is certum est quod, certum reddi potest (certain is that which can be made certain).
Now, from the perusal of the record the total unutilised secured advance can be ascertained as Rs 9,63,635.25p. Similarly, from the record, the principal amount of the secured advance can also be calculated and on it, interest on the amount of the secured advance paid to the appellant for the period the amount remained unutilised could be calculated. The appellant has not been able to point out that the calculation of this amount as Rs 1,40,150 up to 31-12-1991 was wrong or incorrect. Therefore, it would be naïve to contend that the award was vague, evasive or non-committal.”
The above finding of the District Judge, Chandigarh, was not challenged by the contractor before the High Court as is apparent from the impugned order. Thus, there is no merit, at all, in the submission of the learned counsel for the contractor that the arbitrator awarded unutilised secured advance for which there was no claim. In any case, this hardly leads to any inference of bias of the arbitrator.
22. In Gullapalli Nageswara Rao AIR 1959 SC 308, 1959 Supp (1) SCR 319 this Court restated the principle of natural justice that the authority empowered to decide the dispute must be one without bias towards one side or the other in the dispute. There can hardly be any doubt about this fundamental principle of natural justice. The question is: whether on facts, the contractor has been able to establish that the arbitrator was biased against it? None of the circumstances pointed out by the contractor leads to any inference that the arbitrator had any bias, personal or otherwise. No doubt, bias may be found in a variety of situations and each case, where bias of the adjudicator is alleged, has to be seen in the context of its own facts but a fanciful apprehension of bias is not enough.
23. The observations of Lord Atkinson in Bristol Corpn. 1913 AC 241, (1911-13) All ER Rep 1076 (HL), relied upon by the learned counsel for the contractor, instead of supporting his argument, go fully against the contractor. In Bristol Corpn. 1913 AC 241, (1911-13) All ER Rep 1076 (HL) Lord Atkinson stated thus: (All ER p. 1077 C-E)
“… If a contractor chooses to enter into a contract binding him to submit any disputes which arise between him and the engineer of the persons with whom he contracts to that engineer to arbitrate on, then he must be held to his contract; whether it be wise or unwise, prudent or the contrary, he stipulated that a person who is the servant of the persons with whom he contracted shall be the judge to decide upon matters upon which, necessarily, that engineer or arbitrator has himself formed an opinion. But though the contractor is bound by that contract, still he has a right to demand that, notwithstanding those preformed views of the engineer, that gentleman should listen to argument, and should determine the matters submitted to him as fairly as he can, as an honest man; and if it be shown in fact that there is any reasonable prospect that he will be so biased as not to decide fairly upon those matters, then the contractor is allowed to escape from his bargain, and to have the matters in dispute tried by one of the ordinary tribunals of the land. But he has more than that right. If, without any fault of his own, the engineer has put himself in such a position that it is not fitting, or decorous, or proper that he should act as arbitrator in any one or more of those disputes, the contractor has the right of appealing to a court of law to exercise the discretion which Section 4 of the Arbitration Act vests in them….”
The above observations exposit the legal position that a contractor is bound by the contract if he has agreed to submit the disputes to the engineer for arbitration although he has to deal with such engineer under the contract. It needs no emphasis that once the dispute is referred to such arbitrator, the arbitrator has to act fairly and objectively and the proceedings must meet the requirements of principles of natural justice.
24. Insofar as the facts of the present case are concerned, the contractor moved the court for appointment of the Chief Engineer as arbitrator and then chose not to appear before him. What was the intervening event after the arbitrator was appointed at his instance that prompted him to ask the arbitrator to recuse himself is not stated by the contractor. The contractor was not successful in getting any final or interim order in the proceedings initiated by it for removal of the arbitrator. The award passed by the arbitrator also does not show that he misconducted in any manner in the proceedings. He gave full opportunity to the contractor to appear and put forth its case but the contractor failed to avail of that opportunity.
25. There is no justifiable circumstance on record that enables the contractor to escape from the bargain that it made under the contract and have the disputes resolved through the process other than agreed.
26. In Secy. to Govt., Transport Deptt. v. Munuswamy Mudaliar 1988 Supp SCC 651, AIR 1988 SC 2232 this Court stated:
“11. … When the parties entered into the contract, the parties knew the terms of the contract including arbitration clause. The parties knew the scheme and the fact that the Chief Engineer is superior and the Superintending Engineer is subordinate to the Chief Engineer of the particular Circle. In spite of that the parties agreed and entered into arbitration and indeed submitted to the jurisdiction of the Superintending Engineer at that time to begin with, who, however, could not complete the arbitration because he was transferred and succeeded by a successor. In those circumstances on the facts stated no bias can reasonably be apprehended and made a ground for removal of a named arbitrator. In our opinion this cannot be, at all, a good or valid legal ground. Unless there is allegation against the named arbitrator either against his honesty or capacity or mala fide or interest in the subject-matter or reasonable apprehension of the bias, a named and agreed arbitrator cannot and should not be removed in exercise of a discretion vested in the court under Section 5 of the Act.
12. Reasonable apprehension of bias in the mind of a reasonable man can be a ground for removal of the arbitrator. A predisposition to decide for or against one party, without proper regard to the true merits of the dispute is bias. There must be reasonable apprehension of that predisposition. The reasonable apprehension must be based on cogent materials. (See the observations of Mustill and Boyd, Commercial Arbitration, 1982 Edn., p. 214.) Halsbury's Laws of England, 4th Edn., Vol. 2, p. 282, Para 551 describes that the test for bias is whether a reasonable intelligent man, fully apprised of all the circumstances, would feel a serious apprehension of bias.
13. This Court in International Airports Authority of India v. K.D Bali (1988) 2 SCC 360, AIR 1988 SC 1099, JT (1988) 2 SC 1 held that there must be reasonable evidence to satisfy that there was a real likelihood of bias. Vague suspicions of whimsical, capricious and unreasonable people should not be made the standard to regulate normal human conduct. In this country in numerous contracts with the Government, clauses requiring the Superintending Engineer or some official of the Government to be the arbitrator are there. It cannot be said that the Superintending Engineer, as such, cannot be entrusted with the work of arbitration and that an apprehension, simpliciter in the mind of the contractor without any tangible ground, would be a justification for his removal. No other ground for the alleged apprehension was indicated in the pleadings before the learned Judge or the decision of the learned Judge. There was, in our opinion, no ground for removal of the arbitrator. Mere imagination of a ground cannot be an excuse for apprehending bias in the mind of the chosen arbitrator.”
27. In S. Rajan v. State of Kerala (1992) 3 SCC 608, AIR 1992 SC 1918 this Court stated:
“12. … Thus, this is a case where the agreement itself specifies and names the arbitrator. It is the Superintending Engineer, Buildings and Roads Circle, Trivandrum. In such a situation, it was obligatory upon the learned Subordinate Judge, in case he was satisfied that the dispute ought to be referred to the arbitrator, to refer the dispute to the arbitrator specified in the agreement. It was not open to him to ignore the said clause of the agreement and to appoint another person as an arbitrator. Only if the arbitrator specified and named in the agreement refuses or fails to act does the court get the jurisdiction to appoint another person or persons as the arbitrator. This is the clear purport of sub-section (4). It says that the reference shall be to the arbitrator appointed by the parties.”
(emphasis in original)
28. Where parties enter into a contract knowing the role, authority or power of the Chief Engineer in the affairs relating to the contract but nevertheless agree for him to be the arbitrator and name him in the agreement to adjudicate the dispute(s) between the parties, then they stand bound by it unless a good or valid legal ground is made out for his exclusion.
29. Except raising the vague and general objections that the arbitrator was biased and had predisposition to decide against the contractor, no materials, much less cogent materials, have been placed by the contractor to show bias of the arbitrator. No sufficient reason appears on record as to why the arbitrator should not have proceeded with the arbitral proceedings. The test of reasonable apprehension of bias in the mind of a reasonable man is not satisfied in the factual situation.
30. We may now deal with the submission of the learned counsel for the contractor that bias on the part of the arbitrator is also reflected from the fact that he has contested the present appeal and filed the affidavit in opposition. What would have the arbitrator done when he has been personally impleaded as the respondent in the appeal and the allegations of bias have been made against him. He was left with no choice but to rebut the allegations by filing his affidavit. The arbitrator did what any other person in his place would have done in the circumstances.
31. The view taken by the High Court does not suffer from any infirmity justifying interference by us in our jurisdiction in appeal under Article 136 of the Constitution of India. The civil appeal is dismissed with no order as to costs.
Alert