B.S.N Joshi And Sons Limited v. Ajoy Mehta And Another
Factual and Procedural Background
Maharashtra State Power Generation Co. Ltd. (“Mahagenco”) floated a tender for coal liaisoning, quantity and quality supervision for its thermal power stations. One essential condition required a bidder to have handled a minimum of five million metric tonnes of coal per year for each of the preceding five financial years, and a total of ten million tonnes in any one of those five years.
B.S.N. Joshi & Sons Ltd. (“the petitioner”) was rejected on the ground that it allegedly failed to meet this volume requirement. After an unsuccessful writ petition before the Madhya Pradesh High Court, the petitioner obtained special leave and succeeded in Civil Appeal No. 4613 of 2006 (Nair Coal case, (2006) 11 SCC 548). In that judgement dated 31-10-2006, the Supreme Court directed Mahagenco to reconsider the petitioner’s offer and, if it satisfied the essential tender conditions, to award a one-year contract effective one month after execution, allowing existing contractors time to wind up.
When Mahagenco did not award the contract and instead floated a new tender that again favoured the earlier bidders—despite the Court’s finding that those bidders had formed a cartel—the petitioner initiated the present contempt proceedings against Mahagenco’s Managing Director (Respondent 1) and another officer (Respondent 2) for wilful disobedience of the 31-10-2006 order.
Legal Issues Presented
- Whether Respondents 1 and 2 wilfully disobeyed the Supreme Court’s order dated 31-10-2006 by failing to reconsider the petitioner’s eligibility in accordance with that order and by refusing to award the contract.
- Whether their interpretation of “preceding five years” (calculating from the date of the judgment rather than the date of the tender) constituted a bona fide mistake or a contumacious act amounting to contempt of court.
Arguments of the Parties
Petitioner’s Arguments
- Mahagenco impermissibly treated the five-year period as commencing from the Supreme Court’s judgment, thereby twisting the order.
- Reliance on the Supreme Court’s interim order to deny the contract was unjustified because that interim order had merged into the final judgment.
- Mahagenco introduced a subsequent, irrelevant consideration—an adverse letter dated 20-2-2007 from another power station—to avoid awarding the contract.
- These acts amount to gross and wilful contempt.
Respondents’ Arguments
- Any non-compliance resulted from a misunderstanding of the Court’s order, not from deliberate disobedience.
- Even on the petitioner’s data, the “financial year” interpretation meant the essential quantity condition was still not met.
- Respondents expressed readiness to obey any further directions of the Court, including awarding the contract if so directed.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Nair Coal Services Ltd. v. Mahagenco, (2006) 11 SCC 548 | Directed Mahagenco to reconsider the petitioner’s bid and, if eligible, award a one-year contract; recognised cartel formation among other bidders; permitted employer’s “general power of relaxation” if essential terms were substantially satisfied. | Formed the very order alleged to have been disobeyed; its interpretation and implementation lay at the heart of the contempt inquiry. |
Court's Reasoning and Analysis
The Court noted that continuous coal supply is critical for power generation and that its earlier orders—both interim and final—were designed to avoid disruption. Key analytical steps were:
- Error in interpreting time frame: Respondents wrongly computed the five preceding years from the date of the 2006 judgment rather than from the tender date. The judgment nowhere authorised such a calculation.
- Merger of interim order: The interim permission granted on 27-3-2006 had merged into the final judgment; relying on it to refuse the contract was impermissible.
- Irrelevant subsequent events: The respondents’ reliance on a 20-2-2007 letter from Sanjay Gandhi Thermal Power Station was irrelevant to compliance with the Court’s mandate.
- Cartel issue ignored: Despite acknowledging cartelisation in internal notes, Mahagenco still awarded contracts to the cartel members, contrary to corporate governance principles highlighted in the 2006 judgment.
- Mens rea for contempt: Although the Court considered the misconstruction “a serious error,” it ultimately accepted the respondents’ apology, noting their undertaking to comply forthwith.
Holding and Implications
DISPOSED OF — The contempt petition was disposed of after the Court:
- Accepted the respondents’ apology and expression of willingness to comply.
- Directed Mahagenco to award the one-year contract to the petitioner in strict conformity with the 31-10-2006 judgment.
- Censured Mahagenco for encouraging cartel formation and urged public sector undertakings to curb such practices to protect public funds and keep electricity tariffs reasonable.
The decision directly compels performance of the earlier judgment but sets no new legal precedent beyond reinforcing that interim orders merge into final orders and that misinterpretation cannot shield officials from contempt liability.
S.B Sinha, J.— This contempt proceeding has been initiated against Respondents 1 and 2 for alleged wilful disobedience of this Court's order dated 31-10-2006 (2006) 11 SCC 548, the operative portion whereof reads as under: (Nair Coal case (2006) 11 SCC 548)
“70. … We, therefore, intend to give another opportunity to Mahagenco. It shall consider the offer of the appellant upon consideration of the matter afresh, as to whether it even now fulfils the essential tender conditions. If it satisfies the terms of the tender conditions, the contract may be awarded in its favour for a period of one year; but such contract shall take effect after one month from the date of the said agreement so as to enable the private respondents herein to wind up their business. This order is being passed in the interest of Mahagenco as also the private respondents herein.”
2. Maharashtra State Power Generation Co. Ltd. (for short “Mahagenco”) issued a notice inviting tender, inter alia, for coal liaisoning, quality and quantity supervision of its thermal power station. One of the conditions laid down therefor is as under: (Nair Coal case (2006) 11 SCC 548)
“8. … ‘1.5(ii) The bidder should have executed the work of total minimum quantity of 5 (five) million metric tons per year for preceding 5 years. Besides this, bidder should have executed the work of total quantity of 10 (ten) million MTs in any of the preceding 5 (five) years. Above execution of work should be on behalf of the State Electricity Board and/or NTPC and/or other State or Central undertakings and/or the private power generating companies as their liaison agent/coal agent, with regard to receipt and supply of the coal including supervision on dispatch, loading, movement of the coal up to destination by railway only.”
The term “year” occurring therein is said to be the financial year. The petitioner along with various others submitted its tender, inter alia, on the premise that the petitioner did not fulfil the essential conditions of having transported the quantity of minimum five lakh tonnes of coal for the preceding five years; its offer was not accepted.
3. A writ petition was filed before the Madhya Pradesh High Court, which having been dismissed, civil appeal bearing No. 4613 of 2006 was preferred by the petitioner upon obtaining special leave.
4. One of the questions which arose for consideration before this Court was as to whether Mahagenco committed a serious error in not taking into account the quantity of coal supplied by the petitioner to Andhra Pradesh Power Generation Corpn. Ltd., as it appears from its letter dated 15-6-2005 that the petitioner had supplied the following quantity of coal: (Nair Coal case (2006) 11 SCC 548)
“Sl. No. Period Name of colliery Quantity in MT 1. 11-9-2003 to March 2004 M/s MCL, Talcher 31,72,750.00 2. 1-10-2003 to 31-3-2004 M/s MCL, Ib Valley Area 3,16,930.00 34,89,680.00 3. 1-4-2004 to 10-9-2004 M/s MCL, Talcher 27,74,455.00 4. 1-4-2004 to 30-9-2004 M/s MCL, Ib Valley Area 3,89,732.00 31,64,187.00”
5. By a judgment and order dated 31-10-2006 (2006) 11 SCC 548 this Court held: (Nair Coal case (2006) 11 SCC 548)
“26. … It is, therefore, evident that total quantity of 62,64,135 metric tonnes of coal had been handled by the appellant for them.
27. The intention of introduction of the said clause becomes self-evident from the aforementioned note. It may be true, as was observed by the High Court, that the respondents in the tender documents did not categorically state that the block of 365 days in respect of handling of coal by the tenderers shall be taken into consideration. It is also true that the Corporation must be held to be aware as to what the true intent and purport of the said term was.”
It was, however, found that other tenderers viz. M/s Nair Coal Services Ltd., Nagpur, M/s Nareshkumar & Co. Ltd., Nagpur and M/s Karamchand Thapar & Bros. Ltd., Mumbai had formed a cartel.
6. Alleged contemnor, Shri Ajoy Mehta, Managing Director of Mahagenco (Respondent 1 herein) in a note dated 19-8-2005 stated as under: (Nair Coal case (2006) 11 SCC 548)
“32. … On perusal of rates of M/s Nair Coal Services Ltd., Nagpur, M/s Nareshkumar & Co. Ltd., Nagpur and M/s Karamchand Thapar & Bros. Ltd., Mumbai, it is apparent that they have formed a cartel. The rates quoted by these firms are nearly Rs 51 crores to Rs 52 crores more than quoted by LI. As a goodwill gesture the above parties were called for negotiations. However, they have refused to match the LI rates.
In view of the above, it is in public interest and in the interest of Mahagenco, a government-owned public utility that the work is allocated to the lowest qualified bidder, namely, M/s B.S.N Joshi & Co.”
Ultimately, however, the said proposal was not accepted.
7. Despite the fact that a cartel was formed, the contract was awarded to the members thereof. In the aforementioned context, this Court observed: (Nair Coal case (2006) 11 SCC 548)
“69. While saying so, however, we would like to observe that having regard to the fact that huge public money is involved, a public sector undertaking in view of the principles of good corporate governance may accept such tenders which are economically beneficial to it. It may be true that essential terms of the contract were required to be fulfilled. If a party failed and/or neglected to comply with the requisite conditions which were essential for consideration of its case by the employer, it cannot supply the details at a later stage or quote a lower rate upon ascertaining the rate quoted by others. Whether an employer has power of relaxation must be found out not only from the terms of the notice inviting tender but also the general practice prevailing in India. For the said purpose, the court may consider the practice prevailing in the past. Keeping in view a particular object, if in effect and substance it is found that the offer made by one of the bidders substantially satisfies the requirements of the conditions of notice inviting tender, the employer may be said to have a general power of relaxation in that behalf. Once such a power is exercised, one of the questions which would arise for consideration by the superior courts would be as to whether exercise of such power was fair, reasonable and bona fide. If the answer thereto is not in the negative, save and except for sufficient and cogent reasons, the writ courts would be well advised to refrain themselves in exercise of their discretionary jurisdiction.”
It was on the aforementioned premise, the civil appeal was allowed by this Court.
8. Mr Vikas Mehta, learned counsel appearing on behalf of the petitioner, in support of the contempt petition, would argue:
(i) The alleged contemnors had from the very beginning gave a twist to the said order insofar as it proceeded on the basis that the five years’ period should be calculated from the date of the order of this Court.
(ii) Mahagenco refused to grant a contract in favour of the petitioner relying on or on the basis of the interim order passed by this Court.
(iii) A different stand is being taken now that the petitioner should not be allotted any contract in view of a subsequent event viz. the letter dated 20-2-2007 issued by Sanjay Gandhi Thermal Power Station.
On the aforementioned premises, the learned counsel would submit that the alleged contemnors must be held to have committed gross contempt of this Court.
9. Mr Altaf Ahmed, learned Senior Counsel appearing on behalf of the alleged contemnors, on the other hand, would contend that:
(i) The alleged contemnors might have committed a mistake in properly understanding the order of the Court, but the same would not mean that they have committed contempt of court.
(ii) The term “year” having been found by this Court to mean a financial year, even if the figures supplied by the petitioner are taken into consideration, it cannot be said to have satisfied the essential conditions for grant of contract of transportation of coal.
In any event, the learned Senior Counsel would submit that the alleged contemnors are ready and willing to abide by any direction which may be issued by this Court.
10. Supply of coal and that too good quality of coal is essential for running of a thermal power station. It was with that intent in mind that this Court, either at the interim stage or final stage, did not intend to pass any order which would hamper transportation of coal resulting in stoppage of the functioning of the thermal power station.
11. The alleged contemnors, in our opinion, misconstrued the order of this Court for which there was no basis that they were bound by the interim order passed by this Court. For the sake of clarity, we may notice the interim order dated 27-3-2006 which reads as under: (as quoted in Nair Coal case (2006) 11 SCC 548)
“20. … Learned counsel for the petitioner submits that the main petition is coming up for final hearing on 17-4-2006. Learned counsel appearing for Respondents 2 and 3 submits that for purposes of generating power, coal supplies have to be continued to the respondents failing which the entire generation of electricity shall come to a standstill. Keeping in view this fact, the respondents are permitted to go ahead with their tender process including award of contract. They are free to make whatever arrangement they want to make in this behalf to ensure continued supply of coal to them. It is, however, made clear that whatever arrangement is made by the respondents the same will be subject to the final decision of this special leave petition.”
(underlining is ours for emphasis)
We, therefore, fail to understand as to how a fresh tender was floated to allot the work of liaisoning of coal and the same companies who had formed a cartel were allowed to carry on the contract job. We may, however, place on record that the contracts were awarded on the condition that the same would be subject to the final outcome and decision of this Court.
12. Our attention has been drawn to the fact that the petitioner was asked to file additional documents in support of its contention that it fulfilled the essential conditions of contract, if it so intended to do. It was, however, wholly unnecessary as only a fresh look was required to be given in regard to the eligibility of the petition for the purpose of awarding the contract wherefor the Scrutiny Committee was required to form an opinion as to whether the petitioner had substantially complied with the tender conditions, subject, of course, to the fulfilment of essential conditions.
13. The alleged contemnors, in our opinion, committed a serious error in calculating the quantity of coal transported for preceding five financial years from the date of the judgment. The date of the judgment was not at all relevant for the aforementioned purpose. The alleged contemnors did not explain how they have understood the order of this Court wrongly as they had also proceeded on the basis that the five financial years should be counted from the date of calling for the tender and the date of the judgment separately. If they had any difficulty in understanding the direction of the Court, they should have approached this Court for clarification but could not have arrived at such an absurd conclusion that what was necessary to be considered is handling of coal by the petitioner for the preceding five years from the date of passing of the judgment by this Court. What was necessary for them to consider was implementation of the directions issued by this Court in the backdrop of the events noticed by this Court. This Court in its judgment had not only taken into consideration the contentions raised by Mahagenco in regard to non-fulfilment of the essential conditions on the part of the petitioner but also implications thereof at some details.
14. The alleged contemnors furthermore sought to take into consideration a purported subsequent event viz. the letter dated 20-2-2007 issued by Sanjay Gandhi Thermal Power Station, which was neither relevant nor decisive.
15. The alleged contemnors, therefore, in our opinion, did not read the directions of the Court in their proper perspective. We say so:
(i) Because they could not have considered the directions contained in the interim order passed by this Court. The interim order merged into the final order. In any event, even the said interim order was subject to the decision of the Court and, thus, we fail to understand as to how the interim order was found to be continuing despite passing of the final order.
(ii) As the matter was required to be considered afresh and the purpose of considering the eligibility of the petitioner is concerned, they committed a serious error insofar as the eligibility criteria were applied from the date of the judgment.
(iii) They furthermore could not have ignored the note of the alleged Contemnor 1 that the other respondents in the civil appeal had formed a cartel. They furthermore did not notice that having regard to the overall situation and particularly, in view of the opinion of the Scrutiny Committee that the petitioner had substantially complied with the conditions and, thus, the general power of relaxation should have been used.
It is, therefore, not a case where two interpretations of the judgment of this Court were possible.
16. Before us an additional affidavit has been filed by Shri Ajoy Mehta, Contemnor 1, stating:
“17. I, therefore, respectfully submit that we have not flouted the orders passed by the Hon'ble Court and we shall abide by all directions given by this Hon'ble Court including awarding of the contract to M/s B.S.N Joshi & Sons Ltd., the petitioner herein, if this Hon'ble Court so directs.”
Keeping in view the aforementioned statement made before us, we accept the apology tendered by the alleged contemnors for the time being and direct that the contract for a period of one year be granted to the petitioner in terms of our judgment dated 31-10-2006 (2006) 11 SCC 548.
17. We are distressed to see that Mahagenco had been encouraging formation of a cartel and, thus, allowing the rate of transportation of coal to go high up. Unless a power generating company takes all measures to cut down such malpractices, the generation cost of electricity is bound to go higher and ultimately the same would be passed on to the consumers of electricity. We hope a public sector undertaking would take adequate and appropriate measures to meet the said contingency in future.
18. The contempt petition is disposed of with the aforementioned directions.