Ircon International Limited v. Krishna Trading Co. & Anr
Factual and Procedural Background
This opinion arises out of a commercial contract for the supply of stone boulders by the respondent to a Government of India undertaking (the petitioner) for delivery to Bangladesh. The procurement process began with a tender floated in September 1999; the respondent's tender was opened on 24.9.1999, followed by renegotiations, a revised offer dated 12.10.1999 and the petitioner's acceptance by letter dated 6.11.1999. A formal contract was executed on 7.12.2000.
The respondent performed supplies, but the petitioner alleged deficiencies in quantity and quality and retained Rs. 8,40,735 from an asserted claim of Rs. 25,22,772.48, paying Rs. 16,82,037.48. Clause 31.0 of the contract provided for arbitration; a sole arbitrator, Mr. Rajendra Nath, was appointed by IRCON's Managing Director.
The petitioner filed an application under Section 16 of the Arbitration and Conciliation Act, 1996 (seeking to challenge the arbitrator's jurisdiction), which was decided against the petitioner on 28.4.2005. An arbitral award was passed on 21.7.2006 in favour of the respondent for the disputed amount with interest. The petitioner then filed the present petition under Section 34 challenging both the Section 16 order and the award, but the petition effectively challenged only the Section 16 order (as conceded by the petitioner's counsel).
Legal Issues Presented
- Whether the communications between the parties (notably the petitioner's letter dated 30.4.2003, the respondent's faxes dated 12.5.2003 and 15.5.2003, the "No Demand Certificate" of May 2003, and the subsequent payment by draft dated 9.6.2003) amounted to a full accord and satisfaction that precluded the respondent from raising further claims and, consequently, barred reference to arbitration.
- Whether the arbitrator correctly concluded that the fax dated 12.5.2003 was genuine (in light of the fax transmission report and the petitioner's failure to produce the original) and whether that finding was susceptible to interference by this Court under Section 34 of the Arbitration and Conciliation Act, 1996.
- Whether the arbitrator's procedure (reliance on documentary evidence and refusal to record affidavit/oral testimony as insisted by the petitioner) was permissible and whether any procedural lapse warranted interference with the award under Section 34.
- Whether the petitioner could successfully challenge the order under Section 16 (on grounds of arbitrator's jurisdiction) before this Court in the manner advanced.
Arguments of the Parties
Petitioner's Arguments
- The petitioner contended that the communications (particularly the fax of 15.5.2003 and the No Demand Certificate) recorded a full accord and satisfaction of the respondent's claims, so that the respondent could not legitimately raise further claims or refer disputes to arbitration.
- The petitioner challenged the arbitrator's acceptance of the fax dated 12.5.2003 as genuine and argued that the arbitrator's finding in this regard was perverse and liable to be set aside.
- The petitioner complained that the arbitrator did not record oral evidence or affidavits and instead relied largely on documents, which the petitioner suggested was a procedural deficiency warranting interference.
Respondent's Arguments
- The respondent maintained that the documents must be read in context: the petitioner's letter dated 30.4.2003 demanded both consent to the payment figure and a No-claim Certificate, and the respondent's communications (fax & certificate) were in response to that demand.
- The respondent asserted that the No-claim Certificate was sent "under protest" (as indicated in the fax of 12.5.2003) and that the later fax of 15.5.2003 reflected a constrained, transactional acceptance made to secure payment, not an unequivocal surrender of rights.
- The respondent relied on the fax transmission report and the petitioner's own fax register entry to support the genuineness of the 12.5.2003 fax; the arbitrator drew an adverse inference when the petitioner failed to produce the original fax allegedly destroyed during shifting of premises.
- The respondent argued that the arbitrator was entitled to adopt his own procedure and to decide the matter on documentary evidence; the respondent also pointed to the passage of time (the respondent sought arbitration only on 27.10.2003) and the substantive case on merits considered by the arbitrator.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Pandit Construction Company v. Delhi Development Authority and Anr, 2007 (3) ALR 205 (Delhi) | That a settlement must be recorded in clear and unambiguous terms; endorsements such as "accepted in full and final" require explicitness to constitute a complete settlement. | The Court relied on this judgment (which itself relied on Supreme Court authority) to emphasize that a no-claim or final acceptance must be unequivocal before it can be treated as an accord and satisfaction. |
| Bharat Coking Coal Ltd. v. Annapurna Construction, 2003 (3) R.A.J 44 (SC) | The Supreme Court observed that mere acceptance of the final bill does not automatically preclude further claims; for a claim to be deemed fully settled it must be unequivocally stated that no further claim would be raised. | The Court cited this authority as foundational for the principle that an unequivocal declaration is necessary to extinguish further claims and that mere notation or acceptance may not suffice. |
| Chairman & M.D., NTPC Ltd v. Reshmi Constructions, (2004) 2 SCC 663 | Observed that rights/obligations under a contract may continue and disputes can still be referred to arbitration; recognized the commercial reality that contractors may sign no-demand certificates under compulsion to secure payment. | The Court invoked the passages (paras 27–28) to support the view that a no-demand certificate given under pressure (necessitas non habet legem) must be assessed on facts and does not automatically bar arbitration. |
| Ravindra Anant Deshmukh v. City & Industrial Development Corporation of Maharashtra Ltd., AIR 1997 Bombay 284 | Held that a no-demand certificate obtained as a condition precedent for scrutiny of a bill cannot constitute accord and satisfaction and cannot be a cause for refusing to refer disputes to arbitration. | The Court relied on this line to support the proposition that conditioning payment on a no-demand certificate does not ipso facto extinguish claims or preclude arbitration. |
| Jiwani Engineering Works (P) Ltd v. Union of India, AIR 1981 Calcutta 101 | Recognized the practical reality that payment of final bills is often conditional on a contractor issuing a no-claim certificate. | The Court referenced this decision to acknowledge the commercial pressure and context in which no-claim certificates are obtained, weighing that context against a finding of true accord and satisfaction. |
| Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd., AIR 2003 SC 2629 | Defines the scope of judicial scrutiny under Section 34(2) of the Act and limits the Court's role to narrow grounds of interference, not to reappraise evidence as an appellate forum. | The Court applied the principle to refuse to reappraise the arbitrator's factual conclusions and to emphasize that it could not sit as an appellate tribunal to derive different conclusions from the same material. |
Court's Reasoning and Analysis
The Court structured its analysis around whether the documentary record and conduct of the parties amounted to a binding accord and satisfaction and whether the arbitrator's factual findings and procedure were sustainable under the limited scope of judicial review in Section 34.
Key aspects of the Court's reasoning (as recorded in the opinion) are:
- The petitioner's case rested on the contention that the parties had reached a full settlement at a meeting on 6.3.2003 and that subsequent documents (the petitioner's letter of 30.4.2003, the respondent's communications, the No Demand Certificate, and the payment) evidenced an accord and satisfaction extinguishing further claims.
-
The Court closely examined the documentary sequence:
- The petitioner's fax/letter dated 30.4.2003 proposed payment of Rs. 16,82,037 as "full and final settlement" and requested the respondent's consent plus a No-claim Certificate.
- The respondent's fax dated 12.5.2003 purportedly enclosed a "No claim certificate" "under protest."
- The respondent sent a subsequent fax dated 15.5.2003 stating readiness to accept Rs. 16,82,037 and that it would have no claim from IRCON in future, and asked for payment by demand draft.
- The petitioner thereafter sent a draft by letter dated 9.6.2003 as "full and final payment."
- The respondent only sought arbitration on 27.10.2003 about the balance amount claimed.
- Regarding the genuineness of the fax dated 12.5.2003, the arbitrator had before him the fax transmission report and the petitioner's fax register which had an entry corresponding to a fax received. The arbitrator requested the original fax; the petitioner failed to produce it, citing loss during shifting of premises. The arbitrator drew an adverse inference and accepted the fax as genuine. The Court found no basis to reappraise that factual finding, observing that such an exercise would amount to appellate review not permitted under Section 34.
- Even if further scrutiny were permitted, the Court concluded that the arbitrator's reliance on the fax plus transmission report and the petitioner's register entry was reasonable and that the petitioner’s failure to produce the original supported the arbitrator's conclusion.
- The Court then analyzed whether the subsequent fax dated 15.5.2003 constituted an unequivocal accord and satisfaction. The Court emphasized authorities (Pandit Construction and Bharat Coking Coal / Annapurna Construction) requiring clarity and unambiguity for a final settlement to extinguish claims. The Court also relied on NTPC v. Reshmi Constructions and other authorities to recognize the commercial reality that contractors often sign no-demand certificates under pressure to secure payment.
- Applying these principles to the facts, the Court found that the petitioner's demand (letter dated 30.4.2003) required both a consent to the payment figure and a No-claim Certificate as a condition precedent to payment, and that the respondent's communications (including the No Demand Certificate said to be "under protest" and the 15.5.2003 fax) were made in that commercial context.
- The Court concluded that, on the facts, the respondent had not unequivocally surrendered its right to claim the balance amount and therefore had not, as a matter of law, effected an accord and satisfaction that would preclude arbitration or subsequent claims.
- The Court rejected the petitioner's procedural objection that the arbitrator did not record affidavits or oral testimony, noting that an arbitrator may adopt his own procedure—particularly where communications are documentary (letters/faxes). The parties themselves had certified (by letters to the arbitrator in April 2005) that they had been given full opportunity to present their case under Section 16 and had nothing further to add.
- The Court reiterated the limits of judicial review under the expanded scrutiny following the Saw Pipes decision, observing that it could not supplant the arbitrator's findings with its own or act as an appellate body.
Holding and Implications
Holding: The petition under Section 34 was dismissed. The Court upheld the arbitrator's findings on the issues challenged and refused to set aside the order under Section 16 or the arbitral award on the grounds advanced by the petitioner.
Consequences and Implications:
- The direct effect is that the award in favour of the respondent (dated 21.7.2006) stands, and the petitioner's challenge in this Court fails. The parties were ordered to bear their own costs.
- The Court did not state or create any new legal precedent beyond applying existing authorities. It emphasized established principles: (a) a no-claim or final settlement must be clear and unambiguous to constitute accord and satisfaction; (b) commercial pressure to sign no-demand certificates is a relevant factor to be considered on the facts; and (c) the scope of interference under Section 34 is limited and does not permit reappraisal of factual findings of the arbitrator.
- No broader legal innovations or departures from precedent were articulated; the decision applies the cited authorities to the facts and upholds the arbitrator's procedural and factual conclusions.
Sanjay Kishan Kaul, J. (Oral)— The petitioner, a Government of India Undertaking, was desirous of supplying stone boulders to Bangladesh and elicited offers for the same. A tender was floated dated 6th/8th September, 1999 and the respondent submitted a tender which was opened on 24.9.1999 There were apparently some subsequent discussions between the parties for renegotiation of terms which resulted in a letter from the petitioner dated 6.10.1999 and a revised offer from the respondent dated 12.10.1999 This revised offer was accepted vide a letter of the petitioner dated 6.11.1999
2. A formal contract was also executed on 7.12.2000 The respondent made the supplies but, according to the petitioner, there were deficiency in both quantity and quality. The result of the same was that against the payment sought for by the respondent of Rs. 25,22,772.48 the petitioner paid only an amount of Rs. 16,82,037.48 and deducted an amount of Rs. 8,40,735/-. This gave rise to disputes between the parties. Clause 31.0 of the General Conditions of Contracts provided for settlement of disputes through the mode of arbitration and the arbitrator was to be appointed by the Managing Director of IRCON. Mr. Rajendra Nath, a retired Engineer of the Railways was appointed as the sole arbitrator.
3. The petitioner filed an application under Section 16 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the said Act) but the same was decided against the petitioner on 28.4.2005 and ultimately the award was passed on 21.7.2006 awarding the disputed amount along with interest to the respondent. The petitioner has now filed the present petition under Section 34 of the said Act challenging both the order under Section 16 of the said Act and the award dated 21.7.2006
4. A perusal of the grounds raised in the petition show that the challenge has really been laid only to the order passed on 28.4.2005 on the application of the petitioner under Section 16 of the said Act. There is no challenge to the merits of the award dated 21.7.2006 Learned counsel for the petitioner, thus, fairly states that the petitioner would fail or succeed depending on the fate of the challenge laid to the order passed on 28.4.2005
5. In order to appreciate the aforesaid controversy, some of the communications exchanged between the parties would have to be averted to. This is so since the substratum of the case of the petitioner is that there was really no dispute pending between the parties and there had been full accord and satisfaction of the claim of the respondent and the arbitration was only an afterthought.
6. Learned counsel for the respondent has drawn the attention of this Court to what is alleged by the petitioner to be minutes of what transpired on 6.3.2003, as recorded by Mr. Harjinder Singh, General Manager of the petitioner on 24.3.2003 The document is not signed by the representative of the respondent. It is stated in this document that the deduction of Rs. 8,40,735.00 is required to be made.
7. In respect of the rights and obligations of the parties governed by the contract, learned counsel for the respondent has referred to the revised offer dated 12.10.1999 of the respondent where under the category of other terms and conditions, the following provision was proposed:
“(ii) That the quality and quantity of the material should be inspected and conformed at the loading point in writing before the material is loaded into railway wagons. Our responsibility seizes in all respects after the material is loaded into wagons.”
8. Learned counsel has also referred to the confirmation of the said revised offer vide a letter dated 6.11.1999 by the petitioner where clause 1.4 reads as under:
“1.4 The quality and quantity of the material shall be inspected and confirmed at the loading point in writing before the material is loaded into railway wagons.”
9. A reading of the aforesaid clauses, thus, makes it clear that what was proposed and accepted was that the quality and quantity of the material should be inspected and conformed at the loading point in writing before the material is loaded into the railway wagons and the responsibility of the respondent would seize in all respects after the material was loaded into the wagons. The documentary evidence placed on record and considered by the arbitrator on merits substantiates that such a verification was carried out by the officers of the petitioner but despite that, the disputes arose on account of the fact that the deficiencies were alleged to have been found when the goods arrived at Bangladesh. Learned counsel for the respondent, in fact, emphasized that the supplies were made from more than one source and they were mixed up with the result that the deficiencies could never have been laid at the door of the respondent specially taking into consideration the terms of the contract and that is what weighed with the arbitrator.
10. Be that as it may, in my considered view, the real controversy is on account of the plea of full accord and satisfaction canvassed by the learned counsel for the petitioner.
11. The first communication, relevant in this behalf, is addressed by the petitioner on 30.4.2003, which is in the following terms:
“30.04.2003
M/s Krishna Trading Co.
P.O Sahibganj
Jharkhand
Fax No. 06436-222190
Sub: Supply of Boulders for JBRLP-II, Bangladesh
Ref: Our Order No. IRCON/CO/CIVIL-BD/Boulder/99000.PKG-I/70 dated 06.11.1999
In the meeting held with you on 06.03.2003 at IRCON's Corporate office, it was agreed that an amount of Rs 16,82,037.00 (Rupees Sixteen Lacs Eighty Two Thousand Thirty Seven only) is payable to you as full and final settlement against above referred order as per the following details:
Amount Payable:
1. Security Deposit -11,77,499.63 2. Performance Guarantee - 5,88,750.00 3. Deduction from 1st RA bill - 47,100.00 4. Deduction from 4th RA bill -53,738.87 5. Deduction from 6th RA bill -2,14,927.00 6. Deduction from 8th RA bill - 3,41,102.60 7. Deduction from 0.5% rebate - 99,654.38 Total amount payable - 25,22,772.00 (A) Deductions: 1785 Cum @ Rs. 471.00 Cum (On account of less measurement in Bangladesh and supply of some quoted materials) - 8,40,735.00(B) Net Payable amount (A) - (B) Rs. 16,82,037.00
You are requested to send your consent for the above in addition to a No-claim Certificate so that final payment is processed.
Thanking you
(Harjinder Singh)
General Manager/JB” (emphasis supplied)
12. A reading of the aforesaid fax message, thus, shows that it is the case of the petitioner that in the meeting held on 6.3.2003 an agreement was reached that the amount to be paid by the petitioner to the respondent of Rs. 16,82,037.00 would be in full and final satisfaction of the claim of the respondent and, thus, the respondent was requested to send its consent for the same “in addition to a No-claim Certificate so that final payment is processed.”
13. In response to the said letter, the respondent claims to have sent a fax dated 12.5.2003 in the following terms:
“12.05.03
Shri Harjinder Singh
General Manager/JB
Ircon International Ltd.
New Delhi
Fax No. 011-26885165/011-26873913
Sub: Supply of Boulders for JBRLP-II, Bangladesh under LOA No. IRCON/CO/CIVIL-BD/Boulder/99000.PKG-I/70 dated 06.11.1999
Ref: Your Telefax Massage date 30.04.2003
Dear Sir,
With reference to above, we are enclosing herewith “No claim certificate” under protest.
You are requested to please send the amount by Demand Draft at the earliest.
Yours faithfully,
For Krishna Trading Company
(M.P Chirania)
Proprietor”
14. Along with the fax message a no demand certificate was also sent dated 7th/12th May, 2003, which is as under:
“NO DEMAND CERTIFICATE
Received the sum of Rs. 16,82,037.00 (Rupees Sixteen Lacs Eighty Two Thousand and Thirty Seven only) in full and final settlement of all payments due for “Supply of stone boulders loaded in Railway Wagons at Maharajpur for JBRLP-II, Bangladesh” executed by us under the contract agreement No. IRCON/CO/CIVIL-BD/99009 between IRCON and us vide supply order No. IRCON/CO/CIVIL-BD/99009.PKG-I/79 dated 6.11.99 and all other previous orders including all amounts payable to us as per the agreement. We hereby unconditionally and without any reservations whatsoever certify that with this payment, we shall have no claim of whatsoever description on any account whatsoever from IRCON against the aforesaid job executed by us. We further declare unequivocally that with this payment, we have received all the amount payable to us and have no dispute of any description whatsoever regarding the amount due as calculated/paid to us and we shall be continued to be bound by the terms and conditions of the contract.
(M.P Chirania)
Prop.”
15. The said communication was followed up by a fax message dated 15.5.2003 by the respondent in the following terms:
“15.05.03
Shri Harjinder Singh
General Manager/JB
Ircon International Ltd.
New Delhi
Fax No. 011-26885165/011-26873913
Sub: Payment of final bill against supply of Boulders for JBRLP-II, Bangladesh under LOA No. IRCON/CO/CIVIL-BD/Boulder/99000.PKG-1/70 dated 06.11.1999
Ref: Our telephonic talk dt. 15-05-2003.
With reference to above we have to state as under:—
1. That we are ready to accept a sum of Rs. 16,82,037/- (Rs. Sixteen lacs eighty two thousand thirty seven only) against our outstanding amount of Rs. 25,22,722/-.
2. That we shall have no claim from IRCON in connection to the above captioned work in future.
Please send the payment through Demand Draft on State Bank of India payable at Sahibganj (Branch Code-0173) Branch at the earliest by speed post and not by courier service.”
16. It is the case of the petitioner that the fax message dated 12.5.2003 was never received by it and the No Demand Certificate, in fact, has been received under the cover of fax dated 15.5.2003 In response to the same, the petitioner sent a letter dated 9.6.2003 enclosing a draft for an amount of Rs. 16,78,671, which reads as under:—
“IRCON/CO/CIVIL-BD/Bounder/99009/117609.06.03
M/s Krishna Trading Co.
P.O Sahibganj
Jharkhand-816109
Sub: Supply of Boulders for JBRLP-II, Bangladesh
Ref:(i) Our supply order No. IRCON/CO/CIVIL-BD/Boulder/99000.PKG-I/79 dated 06.11.1999
(ii) Your Letter No. nil dated 15.5.2003
Dear Sir,
Consequent upon the submission of “No demand Certificate” along with your letter dated 15.5.2003, a demand draft No. 113625 dated 9.6.2003 for Rs. 16,78,671.00 (Rupees Sixteen Lacs Seventy Eight Thousand Six Hundred Seventy One only) drawn on State Bank of India, Sahibganj is enclosed along with as full and final payment of all your dues against our supply order referred above.
Kindly acknowledge the receipt.”
17. The respondent only on 27.10.2003 sought to raise the issue about the balance amount payable and sought reference of disputes to arbitration.
18. It is the case of the petitioner that the fax message dated 15.5.2003 in unequivocal terms records the full accord and satisfaction of the claim of the respondent and, thus, it was not open to the respondent to make any further claim. Learned counsel for the petitioner has also emphasized that the findings arrived at by the arbitrator who found that the fax message dated 12.5.2003 must be accepted as genuine are perverse and are liable to be set aside.
19. In order to appreciate the aforesaid contention, the reasoning of the arbitrator in this behalf has to be averted to. The fax message dated 12.5.2003 was produced before the arbitrator along with the fax transmission report. In order to confirm whether such a fax message had been received by the petitioner, the petitioner was asked to produce its register of fax receipts. The petitioner produced the said register and there was an entry of the fax received vide entry No. 4669 from Ranchi. However, the register recorded that the same was addressed by the AGM to Sahib, an Officer in the Corporate Office. Since the fax transmission report had been produced by the respondent, the arbitrator directed the petitioner to produce the original fax which is alleged to have been received as recorded in the said register. The petitioner failed to produce this stating that the fax message was no more available on account of the shifting of the premises. The arbitrator drew an adverse inference and came to the conclusion that the fax message dated 12.5.2003 was a genuine document.
20. I am unable to persuade myself to agree with the submission of learned counsel for the petitioner that this Court should once again re-appraise the material to come to a conclusion that this document is not genuine one. That is the jurisdiction of the arbitrator and it is not for this Court to sit as a Court of appeal despite the submission of learned counsel for the petitioner that the jurisdiction being exercised by this Court is more akin to an appellate jurisdiction since it is the order under Section 16 of the said Act which is sought to be challenged. A reference to the provisions of Section 16 of the said Act would show that only if a conclusion is reached that the arbitrator has no jurisdiction, would an appeal lie under Section 37 of the said Act while in case such an application is rejected, the remedy is only at the stage when objections are filed to the award under Section 34 of the said Act in view of sub-section (6) of Section 16 of the said Act. I am, thus, of the view that the matter has to be scrutinized within the parameters of Section 34 of the said Act.
21. Even for the sake of argument if it is presumed that a more deeper analysis is necessary, I see no reason to come to a different conclusion than that which was arrived at by the arbitrator. The fax message dated 12.5.2003 coupled with the fax transmission report itself would have been sufficient. The arbitrator took due care to ask the petitioner to produce the records of the fax message received in which there was a fax received from the same destination but it is the case of the petitioner that the said fax was an inter-departmental fax of the petitioner. The petitioner, however, failed to produce that fax. All this material would only lead to one conclusion that the fax sent by the respondent had to be relied upon.
22. The most important document, in my considered view, is the subsequent fax message dated 15.5.2003 This is so as the same succeeds the fax message dated 12.5.2003 and records that the respondent was ready to accept a sum of Rs. 16,82,037/- against the outstanding of the respondent of Rs. 25,22,732/- and that the respondent would have no claim from the petitioner in connection to the captioned work in future. It, thus, has to be analyzed whether this fax message would amount to full accord and satisfaction of the claim of the respondent.
23. Learned counsel for the respondent sought to explain the said document by pointing out that the letter dated 30.4.2003 of the petitioner called upon the respondent to send “consent for the above”, i.e, Rs. 16,82,037/- which was to be “in addition to a No-claim Certificate so that the final payment is processed”. It is, thus, pleaded that the letter dated 30.4.2003 made a dual demand; the first to send a consent to the said letter for the payment of the amount mentioned therein and second a No-claim Certificate. The fax dated 12.5.2003 clearly mentioned that it is in response to the letter dated 30.4.2003 and enclosing a No-claim Certificate. The fax message dated 15.5.2003 makes a reference to the telephonic conversation between the representative of the parties on 15.5.2003 It is, thus, submitted that despite the No-claim Certificate being sent, since the same was under the cover of the fax message dated 12.5.2003 which stipulated that No-claim Certificate was “under protest”, a demand was made upon the respondent to send the consent as demanded vide letter dated 30.4.2003 apart from the No-claim Certificate. It is in pursuance to the said demand that the fax dated 15.5.2003 is stated to have been sent.
24. The legal position in respect of as to how such a No-claim Certificate has to be appreciated has been discussed in Pandit Construction Company v. Delhi Development Authority and Anr., 2007 (3) ALR 205 (Delhi), a judgment of this Court. It was found that often endorsements are made on the final bill as “accepted in full and final”. The judgment of the Apex Court in Bharat Coking Coal Ltd. v. Annapurna Construction, 2003 (3) R.A.J 44 (SC) was averted to where the Supreme Court had observed that merely because a party had accepted the final bill, the same would not mean that it was not entitled to any claim. In order for the claim to be presumed to be fully settled, it should unequivocally be stated that no further claim would be raised and, thus, the Supreme Court held that in the absence of such a declaration, the contractor must be held to be estopped and precluded from raising any claims. It is in view thereof that this Court came to the conclusion in Pandit Construction Company v. Delhi Development Authority and Anr. (supra) that the settlement must be recorded in clear and unambiguous terms.
25. Learned counsel for the respondent has referred to the judgment of the Supreme Court in Chairman and M.D, NTPC Ltd v. Reshmi Constructions, Builders and Contractors; (2004) 2 SCC 663 where in paragraphs 27 and 28 it has been observed as under:
“27. Even when rights and obligations of the parties are worked out the contract does not come to an end inter alia for the purpose of determination of the disputes arising thereunder, and, thus, the arbitration agreement can be invoked. Although it may not be strictly in place but we cannot shut our eyes to the ground reality that in the cases where a contractor has made huge investment, he cannot afford not to take from the employer the amount under the bills, for various reasons which may include discharge of his liability towards the banks, financial institutions and other persons. In such a situation, the public sector undertakings would have an upper hand. They would not ordinarily release the money unless a ‘No Demand Certificate’ is signed. Each case, therefore, is required to be considered on its own facts.
28. Further, necessitas non habet lagem is an age-old maxim which means necessity knows no law. A person may sometimes have to succumb to the pressure of the other party to the bargain who is in a stronger position.”
26. Learned counsel for the respondent, thus, submits that the fax dated 15.5.2003 cannot be read in isolation and merely because the phraseology used therein is that no claim would be made in future, the same cannot be treated as an accord in full and final satisfaction.
27. Learned counsel for the petitioner, on the other hand, contends that a bare perusal of the fax dated 15.5.2003, taking into consideration the wordings of the same, would amount to full accord and satisfaction even if the fax dated 12.5.2003 is presumed to have been served on the petitioner.
28. If the aforesaid parameters are applied to the facts of the present case, it will be seen that the demand made vide the letter dated 30.4.2003 by the petitioner for release of payment to the respondent was two-fold. The petitioner wanted a No-claim Certificate which was to be in addition to consent for the amount stipulated in the said letter as the final amount. Thus, both, the No-claim Certificate and the fax dated 15.5.2003, were really in pursuance to the said letter. It was a condition precedent for the release of the amount and it is only thereafter that the amounts were released. It is trite to say that there is an element of unequal bargaining position when a contractor has carried out work and dues are pending for a considerable period of time. If a party awarding the contract insists on a letter in the form of a no due or no claim as a pre-condition for release of the payment, it cannot be said that the contractor is deprived of the opportunity to make an appropriate claim before the Arbitral Tribunal.
29. A Division Bench of the Bombay High Court in Ravindra Anant Deshmukh v. City and Industrial Development Corporation of Maharashtra Ltd., AIR 1997 Bombay 284 held that a no demand certificate obtained as a condition precedent for scrutiny of bill cannot constitute accord and satisfaction and a cause for refusing to refer dispute to arbitration.
30. In Jiwani Engineering Works (P) Ltd v. Union of India, AIR 1981 Calcutta 101, the learned single Judge has recognized the well known and notorious fact that unless a no claim certificate is issued by the contractor, the payment of final bill would not be made.
31. In the given facts discussed aforesaid, I am, thus, of the considered view that it cannot be said that the respondent had surrendered the right to make claim for the balance amount deducted out of the contract amount.
32. The objections filed by the petitioner have also sought to make a grievance that the arbitrator did not record any evidence by way of affidavits or oral testimony but sought various documents. I do not find any force in this plea for the reason that the arbitrator can lay down his own procedure especially when the communications exchanged between the parties is through letters/faxes. In this behalf, learned counsel for the respondent has also drawn the attention of this Court to two letters dated 13.4.2005 and 8.4.2005 addressed to the arbitrator by the petitioner and the respondent respectively. These letters are in the form of a certificate that the parties having been given full opportunity to present their case under Section 16 of the said Act and had nothing more to add to the same. It is only thereafter on consideration of the matter, the arbitrator found in favour of the respondent.
33. It also cannot be lost sight of that the arbitrator is a technical person and has considered the respective pleas of the parties in depth. The evidence has also been examined and a finding has been reached on the basis of the appraisal of the evidence. The scope of scrutiny by this Court within the expanded definition of Oil and Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd., AIR 2003 SC 2629 does not permit this Court to sit as a Court of appeal or seek to derive different conclusions than that arrived at by the arbitrator on the basis of the material on record. That is not the scope of scrutiny of objections under Section 34(2) of the said Act.
34. In view of the fact that there is no other plea raised, the petition is dismissed, leaving the parties to bear their own costs.