30 CFR 585.417 : Mineral Resources (§ 1.1 To Parts 1291-1299) — (Parts 200-202 To Parts 591-599) — Bureau Of Ocean Energy Management, Department Of The Interior (Parts 500-519 To Parts 591-599) — Offshore (§ 550.101 To § 585.1019) — Renewable Energy And Alternate Uses Of Existing Facilities On The Outer Continental Shelf (§ 585.100 To § 585.1019) — Lease And Grant Administration (§ 585.400 To § 585.437) — Lease Or Grant Suspension (§ 585.415 To §§ 585.422-585.424) — When may BOEM order a suspension?

4 Aug 2016

(a) BOEM may order a suspension under the following circumstances:

(1) When necessary to comply with judicial decrees prohibiting some or all activities under your lease;

(2) When continued activities pose an imminent threat of serious or irreparable harm or damage to natural resources; life (including human and wildlife); property; the marine, coastal, or human environment; or sites, structures, or objects of historical or archaeological significance; or

(3) When the suspension is necessary for reasons of National security or defense.

(b) If BOEM orders a suspension under paragraph (a)(2) of this section, and if you wish to resume activities, we may require you to conduct a site-specific study that evaluates the cause of the harm, the potential damage, and the available mitigation measures. Other requirements and actions may occur:

(1) You may be required to pay for the study;

(2) You must furnish one paper copy and one electronic copy of the study and results to us;

(3) We will make the results available to other interested parties and to the public; and

(4) We will use the results of the study and any other information that become available:

(i) To decide if the suspension order can be lifted; and

(ii) To determine any actions that you must take to mitigate or avoid any damage to natural resources; life (including human and wildlife); property; the marine, coastal, or human environment; or sites, structures, or objects of historical or archaeological significance.