18 CFR 153.23 : Conservation Of Power And Water Resources (§ 1.101 To Parts 1318-1399) — (§ 1.101 To Parts 391-399) — Federal Energy Regulatory Commission, Department Of Energy (§ 1.101 To Parts 391-399) — Regulations Under Natural Gas Act (§ 152.1 To § 158.12) — Applications For Authorization To Construct, Operate, Or Modify Facilities Used For The Export Or Import Of Natural Gas (§ 153.1 To § 153.23) — Paper Media And Other Requirements (§ 153.20 To § 153.23) — Reporting requirements.

4 Aug 2016

Each person authorized under this part 153 that is not otherwise required to file information concerning the start of construction or modification of import/export facilities, the completion of construction or modification, and the commencement of service must file such information with the Commission within 10 days after such event. Each person, other than entities without pipeline capacity, must also report by March 1 of each year the estimated peak day capacity and actual peak day usage of its import/export facilities.