46 CFR 108.221 : Shipping (§ 1.01-05 To Subchapter D) — (§ 90.01-1 To § 139.165) — Coast Guard, Department Of Homeland Security (Continued) (§ 90.01-1 To § 139.165) — Mobile Offshore Drilling Units (§ 107.01 To Appendix A To Part 109) — Design And Equipment (§ 108.101 To § 108.901) — Construction And Arrangement (§ 108.113 To § 108.241) — Rails (§ 108.217 To § 108.223) — Storm rails.

4 Aug 2016

Each unit must have a storm rail in the following locations:

(a) On each deckhouse side that is normally accessible.

(b) On each side of each passageway that is wider than 1.83 meters (6 feet).

(c) On at least one side of each passageway that is less than 1.83 meters (6 feet) wide.

46 CFR 108.221