18 CFR 2.19 : Conservation Of Power And Water Resources (§ 1.101 To Parts 1318-1399) — (§ 1.101 To Parts 391-399) — Federal Energy Regulatory Commission, Department Of Energy (§ 1.101 To Parts 391-399) — General Rules (§ 1.101 To § 3C.3) — General Policy And Interpretations (§ 2.1 To Appendix C To Part 2) — Statements Of General Policy And Interpretations Under The Federal Power Act (§ 2.2 To § 2.26) — State and Federal comprehensive plans.

4 Aug 2016

(a) In determining whether the proposed hydroelectric project is best adapted to a comprehensive plan under section (10)(a)(1) of the Federal Power Act for improving or developing a waterway, the Commission will consider the extent to which the project is consistent with a comprehensive plan (where one exists) for improving, developing, or conserving a waterway or waterways affected by the project that is prepared by:

(1) An agency established pursuant to Federal law that has the authority to prepare such a plan, or

(2) A state agency, of the state in which the facility is or will be located, authorized to conduct such planning pursuant to state law.

(b) The Commission will treat as a state or Federal comprehensive plan a plan that:

(1) Is a comprehensive study of one or more of the beneficial uses of a waterway or waterways;

(2) Includes a description of the standards applied, the data relied upon, and the methodology used in preparing the plan; and

(3) Is filed with the Secretary of the Commission.