Glasswall, LLC v. Monadnock Constr., Inc.

District Court of Appeal of Florida, Third District.
Jan 27, 2016
Smart Summary (Beta)

Factual and Procedural Background

Glasswall, LLC, a manufacturer of impact-resistant windows and door systems, entered into AIA-modified contracts with Monadnock Construction, Inc., the general contractor for two high-rise apartment buildings in Queens, New York. The contracts, dated January 3, 2013, obligated Glasswall to manufacture window assemblies for the project in exchange for $13 million. A dispute arose regarding Glasswall's timely delivery, prompting Monadnock to initiate arbitration proceedings with the American Arbitration Association (AAA) in New York. In response, Glasswall and associated parties filed suits in Miami–Dade County Circuit Court challenging the arbitration's propriety and asserting claims against Monadnock and others. The trial court denied Glasswall's motion for a temporary injunction to stay the New York arbitration and granted Monadnock's motion to stay the related circuit court cases pending the arbitration's outcome. Glasswall appealed both orders, which were consolidated for review by the District Court of Appeal of Florida, Third District.

Legal Issues Presented

  1. Whether the parties' construction contracts demonstrate a "clear and unmistakable" intent to submit the issue of arbitrability to an arbitrator rather than a court.
  2. Whether the trial court properly denied Glasswall's motion for a temporary injunction to stay the New York arbitration.
  3. Whether the trial court properly granted Monadnock's motion to stay the related circuit court proceedings pending arbitration.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Rintin Corp., S.A. v. Domar, Ltd., 766 So.2d 407 (Fla. 3d DCA 2000) Establishes that incorporation of arbitration rules referencing the Florida International Arbitration Act (FIAA) constitutes "clear and unmistakable" evidence that parties intend for arbitrators to decide arbitrability. The court found Rintin sufficiently analogous, concluding the parties' incorporation of AAA Construction Industry Rules similarly evidenced intent to arbitrate arbitrability issues.
Oracle Am., Inc. v. Myriad Group A.G., 724 F.3d 1069 (9th Cir. 2013) Holding that incorporation of AAA arbitration rules constitutes clear and unmistakable evidence of agreement to arbitrate arbitrability. The court noted federal courts, including this precedent, support the conclusion that incorporation of AAA rules indicates intent to arbitrate arbitrability.
Petrofac, Inc. v. DynMcDermott Petroleum Operations Co., 687 F.3d 671 (5th Cir. 2012) Affirms that express adoption of AAA rules evidences parties' agreement to arbitrate arbitrability. Referenced as part of the majority federal court view endorsing arbitration of arbitrability where AAA rules are incorporated.
Terminix Int'l Co., LP v. Palmer Ranch Ltd. P'ship, 432 F.3d 1327 (11th Cir. 2005) Incorporation of AAA rules clearly and unmistakably shows parties agreed arbitrator decides validity of arbitration clause. Used to support the court's conclusion that the parties intended an arbitrator to decide arbitrability.
Higley S., Inc. v. Park Shore Dev. Co., 494 So.2d 227 (Fla. 2d DCA 1986) Defines AIA contracts as commonly used in the construction industry. Referenced to explain the nature of the contracts involved in the case.
Ajamian v. CantorCO2e, L.P., 203 Cal.App.4th 771, 137 Cal.Rptr.3d 773 (2012) Refused to enforce an arbitration provision in an un-negotiated employment agreement due to unconscionability and unequal bargaining power. Distinguished and disregarded by the court as non-analogous given the commercial, negotiated nature of the contracts in this case.

Court's Reasoning and Analysis

The court analyzed the parties' construction contracts, which incorporated the American Arbitration Association's Construction Industry Arbitration Rules, including a provision granting the arbitrator authority to rule on their own jurisdiction and the arbitrability of claims. The court emphasized the principle that arbitration clauses are treated as independent agreements and that decisions invalidating the main contract do not necessarily invalidate the arbitration clause. Citing Rintin Corp., S.A. v. Domar, Ltd., the court found the incorporation of AAA rules to be "clear and unmistakable" evidence that the parties intended for arbitrators, not courts, to decide arbitrability. The court further noted that the majority of federal courts have reached similar conclusions when AAA rules are incorporated. It rejected Glasswall's reliance on the Ajamian case, distinguishing it as involving a non-negotiated employment contract with unequal bargaining power, which is factually distinct from this commercial construction contract dispute. Based on this analysis, the court affirmed the trial court's denial of the temporary injunction and its stay of the related circuit court proceedings pending arbitration.

Holding and Implications

Holding: The appellate court affirmed the trial court's denial of Glasswall's motion for a temporary injunction to stay arbitration and the granting of Monadnock's motion to stay the related circuit court cases pending the New York arbitration.

Implications: The decision confirms that incorporation of the AAA Construction Industry Arbitration Rules into a contract constitutes clear and unmistakable evidence that the parties intended for arbitrators to decide issues of arbitrability. The ruling enforces the arbitration clause as written and supports the principle that courts must respect parties' agreements to arbitrate, including the delegation of arbitrability questions to arbitrators. No new precedent was established beyond affirming the application of existing principles to the parties' contracts. The direct effect is that the arbitration in New York proceeds without interference from the Florida courts, and the related litigation is stayed pending the arbitration's conclusion.

Show all summary ...

WELLS, Judge.

Crabtree & Auslander, John G. Crabtree, Charles Auslander, George R. Baise, Jr., and Brian C. Tackenberg, for appellant.

Duane Morris LLP, Alvin D. Lodish and Richard D. Shane, for appellees.

Opinion

WELLS, Judge.

In this consolidated appeal, Glasswall, LLC appeals from a non-final order denying its motion for a temporary injunction to stay a New York arbitration and from a non-final order granting the appellees' motion to stay the underlying cases in this matter pending conclusion of the New York arbitration. We have jurisdiction. See Fla. R.App. P. 9.130(a)(3)(B), (a)(3)(C)(iv). Finding that the construction contracts at issue sufficiently demonstrate the parties' intent that an arbitrator decide issues of arbitrability, we affirm.

The parties to 3D15–1124 are Glasswall, LLC and Monadnock Construction, Inc. The parties to 3D15–1652 are Glasswall, Monadnock, HPS 50th Avenue Associates, LLC, HPS Borden Avenue Associates, LLC, The Related Companies, and Bruce Beal.

Glasswall is the manufacturer of impact-resistant windows and door systems used in high-rise commercial and residential buildings. Manadnock Construction, Inc. is the general contractor for two high-rise apartment buildings being constructed on the waterfront in Queens, New York. On January 3, 2013, Monadnock and Glasswall entered into AIA-modified contracts pursuant to which Glasswall agreed to manufacture window assemblies for the New York project in return for $13 million. When a dispute arose over Glasswall's ability to timely deliver its product, Monadnock instituted an arbitration proceeding with the American Arbitration Association (“AAA”) in New York, seeking various remedies and damages for Glasswall's purported breaches of the parties' contracts. For their part, Glasswall, its owner Ugo Colombo, and Colombo's wife, Sara Jayne Kennedy, each filed suits in Miami–Dade County Circuit Court challenging the propriety of the arbitration proceeding initiated by Monadnock in New York and asserting claims against Monadnock and the other appellees, several of which are the subject of this appeal (lower court case numbers 15–6405, 14–2090, and 14–5447).

“AIA” stands for The American Institute of Architects. AIA contracts are “commonly used in the construction industry.” Higley S., Inc. v. Park Shore Dev. Co., 494 So.2d 227, 228 (Fla. 2d DCA 1986).

Glasswall voluntarily dismissed lower court case number 15–6017.

The parties then filed competing motions, with Glasswall seeking a temporary injunction to stay the New York arbitration and Monadnock seeking to stay the instant circuit court cases pending the outcome of the New York arbitration—the crux of the motions centering on whether the parties had agreed to submit the issue of arbitrability to an arbitrator. Upon finding that the parties' contracts evidenced a “clear and unmistakable” intent that an arbitrator decide issues of arbitrability because the agreements explicitly incorporated the Construction Industry Arbitration Rules of the AAA, the trial court entered separate orders denying Glasswall's motion for a temporary injunction and granting Monadnock's motion for a stay of the cases brought here pending arbitration. Glasswall appealed both orders which this has court consolidated for all purposes. For the following reasons we affirm.

The subject construction contracts contain identical provisions wherein Glasswall and Monadnock agreed that claims arising out of their agreements would be subject to mediation followed by binding arbitration, both administered by the AAA in accordance with its construction industry rules and procedures in effect on the date of the agreements:

ARTICLE 6 MEDIATION AND BINDING DISPUTE RESOLUTION

§ 6.1 MEDIATION

§ 6.1.1 Any claim arising out of or related to this Subcontract, except claims as otherwise provided in Section 4.1.5 and except those waived in this Subcontract, shall be subject to mediation as a condition precedent to binding dispute resolution.

§ 6.1.2 The parties shall endeavor to resolve their claims by mediation which, unless the parties mutually agree otherwise, shall be administered by the American Arbitration Association in accordance with its Construction Industry Mediation Procedures in effect on the date of the Agreement. A request for mediation shall be made in writing, delivered to the other party to this Subcontract and filed with the person or entity administering the mediation. The request may be made concurrently with the filing of binding dispute resolution proceedings but, in such event, mediation shall proceed in advance of binding dispute resolution proceedings, which shall be stayed pending mediation for a period of 60 days from the date of filing, unless stayed for a longer period by agreement of the parties or court order. If an arbitration is stayed pursuant to this Section, the parties may nonetheless proceed to the selection of the arbitrators(s) and agree upon a schedule for later proceedings.

....

§ 6.2 BINDING DISPUTE RESOLUTION

For any claim subject to, but not resolved by mediation pursuant to Section 6.1, the method of binding dispute resolution shall be as follows:

(Check the appropriate box. If the Contractor and ... Manufacturer do not select a method of binding dispute resolution below, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, claims will be resolved by litigation in a court of competent jurisdiction.)

[ X ] Arbitration pursuant to Section 6.3 of this Agreement

[ ] Litigation in a court of competent jurisdiction

[ ] Other (specify)

§ 6.3 ARBITRATION

§ 6.3.1 If the Contractor and ... Manufacturer have selected arbitration as the method of binding dispute resolution in Section 6.2, any claim subject to, but not resolved by, mediation shall be subject to arbitration which, unless the parties mutually agree otherwise, shall be administered by the American Arbitration Association in accordance with its Construction Industry Arbitration Rules in effect on the date of the Agreement....

The relevant Construction Industry Arbitration Rule of the AAA in effect at the time of the parties' agreements, which was incorporated by reference into the subject construction contracts, provides that the arbitrator has the power to rule on his or her own jurisdiction, including the arbitrability of a claim:

R–9 Jurisdiction

(a) The arbitrator shall have the power to rule on his or her own jurisdiction, including any objections with respect to the existence, scope or validity of the arbitration agreement.

(b) The arbitrator shall have the power to determine the existence or validity of a contract of which an arbitration clause forms a part. Such an

arbitration clause shall be treated as an agreement independent of the other terms of the contract. A decision by the arbitrator that the contract is and void shall not for that reason alone render invalid the arbitration clause.

(c) A party must object to the jurisdiction of the arbitrator or to the arbitrability of a claim or counterclaim no later than the filing of the answering statement to the claim or counterclaim that gives rise to the objection. The arbitrator may rule on such objections as a preliminary matter or as part of the final award.

While arbitrability is generally an issue for a trial court to decide, “courts are required to enforce privately negotiated agreements to arbitrate.” Rintin Corp., S.A. v. Domar, Ltd., 766 So.2d 407, 408–09 (Fla. 3d DCA 2000). In Rintin, this court addressed a contract which like the one presently before us, did not include specific language indicating that the issue of arbitrability of a dispute would be submitted to an arbitral panel but did incorporate a reference to Florida's International Arbitration Act. There, we decided that such reference constituted “clear and unmistakable” evidence that the parties intended that arbitrability be determined by the arbitral panel:

... Rintin and Domar executed a shareholders' agreement containing an arbitration clause that read, in pertinent part, as follows:

Any controversy arising from the interpretation, performance or termination of this agreement or its noncompliance that cannot be settled by the parties ... will be submitted to arbitration ... according to the provisions of Florida International Arbitration Act (FIAA) and the rules of the American Arbitration Association (AAA).

....

In the instant, case, although the parties did not include specific language indicating that the issue of arbitrability of a dispute will be submitted to an arbitral panel, they did include a specific reference to the FIAA which contains such a provision. The inclusion of this reference is “clear and unmistakable” evidence of the parties' intent to be governed by the FIAA and its provision requiring the submission of the issue of arbitrability of a dispute to the arbitral panel.

Id. at 408, 409.

We find Rintin to be sufficiently analogous to this case to conclude that by incorporating the Construction Industry Rules of the AAA which make the issue of arbitrability subject to arbitration, there is “clear and unmistakable” evidence of Glasswall's and Monadnock's intent to submit the issue of arbitrability to an arbitrator.

In so holding, we note that the parties are in agreement that the majority of federal courts considering similar circumstances where the AAA's arbitration rules have been incorporated by reference into a contract likewise have found that the parties sufficiently evidenced their intent to have arbitrators, not a court, hear and decide issues of arbitrability. See, e.g., Oracle Am., Inc. v. Myriad Group A.G., 724 F.3d 1069, 1074 (9th Cir.2013) (“Virtually every circuit to have considered the issue has determined that incorporation of the American Arbitration Association's (AAA) arbitration rules constitutes clear and unmistakable evidence that the parties agreed to arbitrate arbitrability.”); Petrofac, Inc. v. DynMcDermott Petroleum Operations Co., 687 F.3d 671, 675 (5th Cir.2012) (“We agree with most of our sister circuits that the express adoption of [AAA]

rules presents clear and unmistakable evidence that the parties agreed to arbitrate arbitrability.”); Terminix Int'l Co., LP v. Palmer Ranch Ltd. P'ship, 432 F.3d 1327, 1332 (11th Cir.2005) (“By incorporating the AAA rules ... into their agreement, the parties clearly and unmistakably agreed that the arbitrator should decide whether the arbitration clause is valid.”). To this end, we decline Glasswall's invitation to side with those few courts which have found otherwise.

In particular, we disregard the California state appellate decision in Ajamian v. CantorCO2e, L.P., 203 Cal.App.4th 771, 137 Cal.Rptr.3d 773 (2012), upon which Glasswall heavily relies, as that case arose in the wholly non-analogous context of an un-negotiated employment agreement between an employer and its employee. There, the court refused to enforce an arbitration provision incorporated into the employment agreement finding it was “unconscionable” to do so because of the “unequal bargaining power” of the parties. Id. at 793, 795–96, 137 Cal.Rptr.3d 773. No argument has been made here that Glasswall was not on equal footing with Monadnock when it negotiated and executed the construction agreements at issue here.
--------

Accordingly, we find the trial court properly denied Glasswall's motion for a temporary injunction and properly entered a stay of the multiple lower court proceedings pending the New York arbitration.

Affirmed.

--------