REHR v. WEST
Appellate Court of Illinois.
Jan 5, 1948
DAMAGES, § 147 — measure for breach of construction contract. In absence of proof of damages for breach of contract warranting workmanship in laying of cement floor, proper measure would be reasonable cost of repairing alleged defects in flooring, and allowing plaintiff as damages contract price was reversible error.
See Callaghan's Illinois Digest, same topic and section number.
Opinion by JUSTICE FEINBERG.
Not to be published in full. Opinion filed January 5, 1948; released for publication January 27, 1948.