BARNARD COL. v. TISHMAN CONSTR. CORP., N.Y

Appellate Division of the Supreme Court of New York, First Department.
May 13, 1999

Plaintiff's claim for breach of its construction management contract with defendant accrued in September 1988 upon completion of the project, a dormitory, and was properly dismissed as barred by the six-year Statute of Limitations (see, Cabrini Med. Ctr. v. Desina, 64 N.Y.2d 1059). Giving plaintiff's allegations every favorable inference, we agree with the IAS Court that the work that defendant began to perform in 1992 to fix water leaks in the dormitory's bathrooms cannot serve to extend the accrual date of plaintiff's cause of action (see, supra). We also agree with the IAS Court that plaintiff fails to allege the essential terms of a new contract for such remedial work.

Concur — Ellerin, P. J., Tom, Lerner, Buckley and Friedman, JJ.