Doyle and Ors v An Coimisiun Pleanala and Ors [No. 3] (Approved)

High Court of Ireland
Mar 13, 2026
Smart Summary (Beta)

Factual and Procedural Background

The Plaintiffs (two environmental non-governmental organisations and three individuals) challenged planning permissions granted by the Commission on 5 April 2024 for (a) a data centre campus proposed on lands adjacent to the Tulla Road and (b) an associated 110kV GIS substation and cable works. Company A submitted the applications including an Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS). Clare County Council granted permission; third-party appeals were made to the Commission. The Commission conducted an inspector's report, Appropriate Assessment and EIA and ultimately granted permission subject to conditions. The Plaintiffs sought judicial review under the Planning & Development Act and the Climate Action and Low Carbon Development Act alleging failures under s.15 (domestic climate duty), various other statutory and EU law complaints (including EIA/AA and SEA/WFD points), and challenges concerning bats/derogation licensing. The Commission conceded a limited error in relation to a factual matter about a bat roost in the inspector's report; Company A (the notice party) nonetheless defended the permissions. The High Court conducted a modular hearing (Module I and Module II) addressing the conceded bat issue and the remaining pleaded climate and EIA grounds. Judgment was delivered dismissing the proceedings and including a recital clarifying that the conditions and incorporated documentation require the mitigation measures (including the Corporate Power Purchase Agreements (CPPAs) as described in the applicant’s appeal response) to be implemented.

Legal Issues Presented

  1. Whether the Commission complied with section 15 of the Climate Action and Low Carbon Development Act 2015 (as amended) — in particular whether the decision fell within the spectrum of outcomes that are, in so far as practicable, consistent with CAP 2023, the national climate objective and mitigation/adaptation objectives.
  2. Whether the Commission and inspector lawfully and adequately considered greenhouse gas impacts, carbon budgets/sectoral emissions ceilings and the role of the EU Emissions Trading System (ETS) in assessing consistency under s.15.
  3. Whether the Commission lawfully assessed the environmental effects on bat fauna (EIA and AA aspects) and whether a derogation licence was required before grant of consent.
  4. Whether mitigation measures (notably CPPAs and other measures described in the EIAR/appeal documents) were required, secured and sufficient to render the permission consistent with the statutory climate duties.

Arguments of the Parties

Plaintiffs' Arguments

  • The Commission applied the wrong legal test under s.15 (mere "regard to" rather than performing functions "in a manner consistent with" climate instruments), and failed to explain consistency with CAP 2023 and the national climate objective.
  • The Commission failed to quantify or reconcile project emissions with carbon budgets and sectoral emissions ceilings and therefore failed to show the decision fell within the lawful spectrum under Coolglass.
  • The Commission irrationally relied on prospective/contingent future renewable-gas/hydrogen or biomethane readiness and on PAS 2050-type reasoning to minimise significance of emissions.
  • The Commission failed to require mitigation/offsetting (in particular sufficiently specific or additional CPPAs) and did not secure "additionality" such that the development would undermine national mitigation targets.
  • The Commission and inspector inadequately addressed bat impacts; a derogation licence was required prior to grant of consent (EU law/EIA sequencing argument invoking Namur Est and related authorities).

Respondents' Arguments (The Commission and Company A)

  • Section 15 requires substance over form; the Commission and inspector engaged with CAP 2023, ETS coverage, emissions quantification, mitigation measures and adaptive design. The decision must be read fairly and in the round (Coyne principle).
  • Carbon budgets and SECs are macro instruments implemented nationally; s.15 does not convert them into project-level numerical gates. The EIAR/AWN appeal response quantified emissions and assessed significance; ETS/regulatory context is relevant.
  • References to hydrogen/biomethane and "potential" positive effects were conditional and prospective; the inspector did not treat future fuels as a deterministic justification for permission.
  • Mitigation commitments (including CPPAs and on-site measures) were before the Commission and are incorporated into the permission by Conditions 1 and 3 (the grant being made in accordance with submitted documentation); the consent therefore secures mitigation measures.
  • On the bats/derogation point, the factual position was that a single historical observation did not make continuing roost occupancy probable; a derogation was not shown to have been certainly required at the date of decision and Irish law does not operate a single-permit system like that addressed in Namur Est.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Coolglass v. An Coimisiún Pleanála [2026] IESC 5 Section 15 creates a legal standard: relevant bodies must perform functions "in so far as practicable" in a manner consistent with specified climate instruments; consistency is a spectrum of possible outcomes. The Court applied Coolglass as the governing test for s.15 and found the Plaintiffs had not demonstrated the Commission's decision fell outside the lawful spectrum of outcomes consistent with s.15.
Coyne v. An Bord Pleanála [2023] IEHC 412 Substance over form: compliance with s.15 is assessed in substance rather than by ritualistic recitation of wording. The Court relied on the substance- over-form principle to read the Commission's references to CAP 2023 and "had regard to" in context and to accept that the inspector and Commission engaged with s.15 substantively.
Doyle v. An Bord Pleanála (No. 1) [2025] IEHC 158 This is the Court's earlier module I ruling on the bat-roost factual error. The Court noted and relied on its No.1 judgment finding the inspector's factual error about a bat roost was harmless; that judgment influenced the Commission's position in Module II and the Court's approach.
Doyle v. An Bord Pleanála (No. 2) [2025] IEHC 205 Earlier interlocutory cost issue (applicants' costs submissions). Cited for procedural history; the Court referred to that judgment in the chronology.
Ballyboden Tidy Towns Group v. An Bord Pleanála & Ors. [2024] IESC 4 Developers can defend permissions even when decision-taker does not. The Court applied the procedural principle allowing Company A to defend the permission notwithstanding the Commission's limited concession.
Namur Est (Case C‑463/20) Sequencing of derogation/authorisation under Habitats/Birds law where a single permit system is used; EIA/derogation sequencing issues in EU law. The judgment was discussed; the Court concluded Namur Est did not displace the factual findings here and that Ireland's regime and the facts did not establish a requirement that derogation must have been obtained prior to consent in the circumstances of this case.
M.R. (Bangladesh) v. International Protection Appeals Tribunal [2020] IEHC 41 Decision-read-in-the-round principle; avoid reading decisions in most erroneous way. Cited to support approach of reading administrative decisions so as to uphold validity where reasonable reading is available.
Reilly v. An Coimisiún Pleanála [2025] IEHC 659 Enumerates an eight‑fold test for obtaining judicial review relief in planning contexts (jurisdiction, legal correctness, pleading, standing, materials before decision-maker, onus, materiality of error, discretion). The Court applied the eight‑fold tests as the analytical framework for considering whether relief was appropriate and concluded the Plaintiffs failed to satisfy them.
Foran v. An Coimisiún Pleanála & Glenveagh [2026] IEHC 23 Referenced in context of the eight‑fold test (cumulative requirements for judicial review relief). Listed among authorities supporting the Court's procedural/legal framework.
Sweeney v. Fahy [2014] IESC 50 Judicial review concerns legality rather than correctness (not an appeal on merits). Applied to stress the court's role is limited and that evaluative judgments are generally for decision‑takers.
State (Keegan) v. Stardust Compensation Tribunal [1986] I.R. 642 Separation of functions: court not to substitute its view for decision-taker on merits. Cited to reinforce limits of judicial review vs merits review.
Meadows v. Minister for Justice, Equality and Law Reform [2010] IESC 3 On the role and limits of judicial review and burden of proof principles. Used to support proposition that onus of proof rests with applicant in judicial review.
R (Cart) v. Upper Tribunal [2011] UKSC 28 Judicial review is not for re-weighing evaluative conclusions. Cited to support approach that courts should avoid substituting their own view for evaluative judgments.
Sherwin v. An Bord Pleanála [2024] IESC 13 Where decision-taker fails to engage with a statutory test the review standard may be intensified. Cited in relation to the standard of review for evaluative planning judgements.
Coyne v An Bord Pleanála [2023] IEHC 412 EIAR/EIA and ETS relevance; substance over form in s.15 compliance. Applied as authority that ETS and regulatory context can be relevant and that substance of engagement with s.15 matters more than formulaic wording.
Friends of Killymooney Lough v. An Coimisiún Pleanála No. 1 [2025] IEHC 407 Discusses use of independent expert entities in science-heavy climate litigation and evidential approaches. Referenced to note that applicants had not sought amicus/expert input which might have assisted with science-heavy points.
EngineNode — as cited within Coyne Substance compliance with s.15 rather than verbatim recitation. Referenced in argument summaries about the proper approach to s.15.
Tesco Stores Ltd v. Secretary of State for the Environment [1995] 1 WLR 759 Evaluative weight is for the decision-maker; courts defer on evaluative judgments. Cited to support deference to planning judgement on weight of considerations.
Baby O v. Minister for Justice [2002] IESC 44 On deference to administrative evaluative judgments. Cited for proposition that weight of evidence and evaluative judgement lies with decision-maker.
Heathrow Airport Ltd [2020] UKSC 52 Evaluative judgments and planning discretion. Referenced on deference to decision‑taker on evaluative matters.
R (Hoareau and Bancoult) v. Secretary of State for Foreign and Commonwealth Affairs [2019] EWHC 221 Judicial review is not politics by another means. Referenced to emphasise separation of powers and limits of judicial review.
O'Sullivan v. Health Service Executive [2023] IESC 11 Draft judgment circulation principles and constraints on re‑argument. Cited in relation to the court's draft-judgment procedure and restrictions on submissions.
O'Sullivan v. Sea Fisheries Protection Authority [2017] IESC 75 Procedural fairness and not importing trial‑like procedures into judicial review. Used in discussion of draft judgment confidentiality and procedure.
Attorney General v. Crosland (No. 2) [2021] UKSC 58 Confidentiality and purpose of draft judgments. Referenced in procedural considerations about draft judgments.
Baigent v. Random House Group Ltd [2006] EWHC 1131 Publication and confidentiality principles. Referenced in context of draft judgment confidentiality.
Public Institution for Social Security v. Banque Pictet & Cie SA and others [2022] EWCA Civ 368 Publication and confidentiality jurisprudence. Referenced in draft judgment discussion.
Itkin v. Wood [2023] JRC 101 Draft judgment confidentiality (Royal Court of Jersey). Referenced as authority on draft judgment practice.
St. Margaret's Recycling v. An Bord Pleanála [2024] IEHC 94 Decision reading-in-the-round; avoid micro-parsing of words. Applied to support the Court's approach of reading the Commission's decision fairly in context.
Mulloy v. An Bord Pleanála [2024] IEHC 86 Reading decisions in a valid manner where possible. Cited in support of reading decisions so as to uphold validity.
Save Cork City Community Association CLG v. An Bord Pleanála [2022] IESC 52 Disproportionate to quash for technical procedural errors; proportionality of relief. Referenced in discretionary considerations about relief.
Watchhouse Cross Shopping Centre v. An Coimisiún Pleanála [2025] IEHC 520 Proportionality and procedural fairness principles. Referenced in context of proportionality/discretion.
B.D.C. (Nigeria) v. International Protection Appeals Tribunal [2018] IEHC 460 Material before the decision‑maker lens (review through the material available at the time). Used in explaining the foundational concept of reviewing legality through material before decision-taker.
I.S.O.F. v. Minister for Justice, Equality and Law Reform [2010] IEHC 457 Belated points not generally admissible where not raised in process. Applied to stress importance of raising issues in administrative process; belated introduction in judicial review is limited.
Reid v. An Bord Pleanála (No. 1) [2021] IEHC 230 Exceptions permitting the court to receive new evidence in limited cases. Cited in relation to exceptions to receiving new evidence post-decision.
An Taisce v. An Bord Pleanála & Ors. [2022] IESC 8 On the applicant bearing the onus in EIA and AA challenges; the need for evidence to displace decision-taker's conclusion. Applied to underscore that applicants must displace decision-taker's conclusions by admissible evidence.
H.A. v. Minister for Justice [2022] IECA 166 When an error is shown on part of a decision-maker, the onus shifts to opposing parties to show harmlessness. Cited for onus-shifting principle when error is demonstrated.
Nagle View Turbine Aware Group v. An Bord Pleanála [2024] IEHC 603 Scientific/factual shortcomings in EIA/AA must be established by applicant (onus). Referenced to support proposition that scientific shortcomings must be proven by admissible evidence.
Eco Advocacy CLG v. An Bord Pleanála (No. 4) [2023] IEHC 713 Pleadings and acceptable clarity: provisions need not be enumerated verbatim if implicitly identifiable. Cited to explain pleading standards in complex EU law contexts.
Kennedy & Anor. v. An Bord Pleanála [2024] IEHC 570 Pleadings, onus and evidential standards in environmental assessment challenges. Referenced among authorities on pleading stringency and evidential burden.
Leech v. An Bord Pleanála [2024] IEHC 599 Acceptable clarity standard for pleadings. Referenced in pleading discussion.
Concerned Residents of Treascon and Clondoolusk v. An Bord Pleanála & Ors. [2024] IESC 28 Plea compliance with pleading rules; court may grant unpleaded relief only within pleaded contours. Cited in pleading and scope-of-relief discussion.
Sweetman v. An Bord Pleanála (Sweetman XV) [2020] IEHC 39 Non-transposition and complex EU law arguments require clarity in pleadings. Used to stress stringency of pleading in EU transposition claims.
Alen-Buckley v. An Bord Pleanála [2017] IEHC 311 Non-transposition claims not set out in pleadings are impermissible. Referenced as caution against raising new EU non-transposition arguments late.
Ballyboden Tidy Towns v. An Bord Pleanála [2021] IEHC 648 Applicants confined to pleaded grounds; high-level principles require a route-map in pleadings. Cited to require connection between factual problems and relief sought.
Foley v. Environmental Protection Agency [2022] IEHC 470 Requirement for a clear route-map linking facts to relief in environmental judicial reviews. Referenced concerning pleading clarity.
Hellfire Massy Residents Association v. An Bord Pleanála [2022] IESC 38 Critique of scattergun pleadings; courts reject overly broad pleaded cases. Applied to warn against scattergun pleading strategies.
Babington v. Minister for Justice Equality and Law Reform & Ors. [2012] IESC 65 Pleadings must be clear; repetition does not strengthen a point. Cited in pleading standards discussion.
A.P. v. Director of Public Prosecutions [2011] IESC 2 Applicants are confined to their pleadings. Referenced to reinforce pleading confinement principle.
Khashaba v. Medical Council [2016] IESC 10 Pleading obligations and consequences of deficient pleadings. Referenced for pleading principle.
Reid v. An Bord Pleanála (No. 7) [2024] IEHC 27 Pleadings and amendment jurisprudence. Referenced in context of pleading requirements.
People Over Wind & Anor. v. An Bord Pleanála & Ors. (No. 1) [2015] IEHC 271 Pleading stringency in judicial review challenging environmental matters. Referenced to emphasise strict pleading requirements.
R v. Crischuk 2010 BCSC 716 (and affirmed 2010 BCCA 391) Onus in environmental assessment contexts: applicant must show defects by evidence. Referenced for the proposition that EIA/AA shortcomings must be proved by applicant evidence.
Carrownagowan Concern Group v. An Bord Pleanála [2024] IEHC 300 Scientific/factual shortcomings in EIA must be established with admissible evidence. Applied to support evidential onus arguments.
O'Doherty and Waters v. Minister for Health [2022] IESC 32 Onus of proof remains with applicant even in constitutional challenges. Cited to reinforce presumption of validity and onus principles.
100 Meter Tall Group v. An Bord Pleanála [2025] IESCDET 85 AA/EIA evidential standards and the necessity to displace Board's reasons by evidence. Referenced in support of evidential requirements for displacing decision-taker's conclusions.
Connelly v. An Bord Pleanála [2018] IESC 31 Reasons obligation: main reasons on main issues must be provided; reasons may be found in adopted reports. Applied in considering sufficiency of reasons in inspector's report and Board order.
Killegland Estates Ltd v. Meath County Council [2023] IESC 39 Reasons need not be repeated where obvious; plan-consistency presumption. Used to support reading of reasons and presumption of plan-consistency under s.15.
Fahybeg Windfarm Opposition Group v. An Bord Pleanála [2025] IEHC 310 Construction of permissions incorporating plans/particulars into conditions. Applied to support conclusion that Conditions 1 and 3 incorporate mitigation commitments (including CPPA commitments) contained in submitted documentation.
Rural Residents Wind Aware v. An Coimisiún Pleanála (I) [2025] IEHC 600 Material-before-decision-maker lens and evidential principles in EIA review. Referenced in discussion about what must have been raised in the administrative process to engage duties under s.15.
RPS Consulting Engineers Ltd v. Kildare County Council [2015] IEHC 113 Reasons that existed at the relevant time can be evidenced after the event but reasons should not be created ex post facto. Referenced in discussion of reasons and evidence of reasons.
Redmond v An Bord Pleanála [2020] IEHC 151 Planning permission cannot authorise Article 12 harm. Referenced in addressing the Namur Est sequencing point and Irish context.
IE v Magistrat der Stadt Wien (Case C-477/19) Protection of formerly occupied resting places depends on "sufficiently high probability" of return. Cited in discussion on whether a former bat roost retains protected status; Court referenced the probability threshold and found factual probability lacking here.
Other authorities and EU instruments cited in the opinion This information was not available in the provided opinion as a concise rule/principle for each separate citation. This information was not available in the provided opinion.

Court's Reasoning and Analysis

The Court framed its review by reference to established judicial-review principles: (i) judicial review examines legality not merits; (ii) an eight‑fold cumulative test applies for granting relief in planning judicial review (jurisdiction, legal correctness, pleading specificity, standing, material before decision‑maker, onus of proof, whether any error is more than harmless, and discretion/proportionality); and (iii) decisions must be read fairly and in the round, avoiding undue micro‑parsing.

The Court analysed the s.15 challenge by applying Coolglass: s.15 imposes a legal standard requiring performance of functions "in so far as practicable" consistently with specified climate instruments, but consistency admits a spectrum of lawful outcomes and involves practicability and evaluative judgment. The Court found that (a) the Commission and inspector engaged substantively with CAP 2023, ETS coverage, emissions quantification, mitigation measures and adaptive design; (b) the EIAR and the AWN/appeal response quantified emissions and modelled mitigation scenarios; and (c) the Commission's adoption of the inspector's reasoning, read in context, demonstrated substantive engagement with s.15 rather than mere ritual recitation of words.

On the carbon budgets/SECs point the Court accepted that budgets are mathematical and national, but concluded the statutory architecture does not convert SECs/carbon budgets into project-level numerical gates that individual planning decisions must reconcile arithmetically. The Court emphasised that Applicants bore the onus to demonstrate that the decision fell outside the lawful spectrum and had not discharged that onus with admissible expert evidence displacing the Commission's assessment.

On mitigation, the Court held Conditions 1 and 3 (that the development be carried out in accordance with the submitted plans and that mitigation in the EIAR/NIS be implemented) operate to incorporate the mitigation measures and commitments in the documentation (including Company A's stated willingness to enter CPPAs) into the permission; accordingly the mitigation framework was legally secured by the consent as a matter of construction.

On the bats/derogation issue the Court accepted factual findings (in the earlier module) that the single Leisler's bat observation did not make continued roost occupancy sufficiently probable. The Court concluded that a derogation licence was not shown to have been certainly required at decision date; Namur Est did not operate to invalidate the decision on the facts here. The Court noted the Applicants’ failure to raise some of these points during the process and stressed the limited circumstances in which belated points or new evidence may be received.

Applying the eight‑fold test and exercising discretion (including proportionality considerations), the Court found the Applicants failed to demonstrate illegality or a material error causing prejudice and concluded against quashing the permissions.

Holding and Implications

DISPOSED OF

Holding: The proceedings are dismissed. The Court ordered (i) dismissal of the judicial review proceedings; (ii) a recital in the order clarifying that Conditions 1 and 3 read with the incorporated documentation require implementation of the mitigation measures submitted with the application, which include the CPPA commitments described in Company A's appeal response; and (iii) the order shall be perfected forthwith with no order as to costs unless parties make consequential applications.

Implications: The direct effect is that the Commission's decisions of 5 April 2024 granting the data centre and substation permissions remain operative. The Court reiterated that s.15 imposes an enforceable but flexible legal standard and that courts will assess compliance by reference to the spectrum-of-possible-outcomes test in Coolglass; however, on these facts the Court found no legal error requiring quashing. The judgment does not purport to establish a new general precedent beyond application of existing authorities (notably Coolglass) to these facts.