SLB & Ors v PAK & Ors

England and Wales High Court (Commercial Court)
Mar 2, 2026
Smart Summary (Beta)

Factual and Procedural Background

These are appeals under section 69 of the Arbitration Act 1996 against ten separate arbitral awards all dated 27 February 2025 with common reasons issued by three maritime arbitrators (the Tribunal). The disputes arose from ten novated shipbuilding contracts ("the SBCs") under which each separate special-purpose vehicle Claimant (collectively the Buyers) agreed to buy, and the Defendants (the Yard / the Seller) agreed to build and sell, ten container vessels (the Vessels).

The Tribunal unanimously held that the Yard's contractual obligation to provide letters of guarantee (the "Refund Guarantees") within 120 days (or such later date as the Buyer may designate) was an innominate term and not a condition. The Tribunal concluded that the Yard's admitted failure to obtain the Refund Guarantees within 120 days entitled the Buyers to exercise contractual cancellation rights but did not entitle them to loss of bargain damages.

Permission to appeal was granted by Judge [Last Name] on 9 June 2025 on the following question of law: whether the Yard's obligation in Article X(A)(f) to provide a Refund Guarantee within 120 days of novation is a condition.

Parties: The First to Eighth Claimants were subsidiaries of Company A (incorporated outside the UK). The Ninth and Tenth Claimants were separate corporations incorporated outside the UK. The three Defendants were common to each arbitration; the Second and Third Defendants operated large shipyards and, together with the First Defendant trading house, were subsidiaries of Company B.

The SBCs were novated versions of 2015 contracts. Novation dates were 5 November 2021 (Stream A) and 30 December 2021 (Stream B). Material terms were materially identical across the ten SBCs. The contracts provided for staged pre-delivery instalments (three pre-delivery instalments contingent on receipt of the Refund Guarantee, and a final instalment on delivery), liquidated-damage adjustments for delay, specific delivery dates, and Article X which provided rights of rescission and an obligation on the Yard to refund instalments upon rescission, secured by the Refund Guarantee (template annexed as Exhibit A).

It was common ground before the Tribunal that the Yard failed to provide the Refund Guarantees within 120 days; the Buyers rescinded the SBCs at days 138 and 140 respectively. In the arbitrations the Buyers sought loss of bargain damages; the Tribunal decided liability issues first and concluded Article X(A)(f) was an innominate term.

Legal Issues Presented

  1. Whether the Yard's obligation in Article X(A)(f) to provide a Refund Guarantee within 120 days of novation is a condition.
  2. Whether the Yard's failure to provide Refund Guarantees within 120 days amounted to a repudiatory breach or renunciation of the SBCs (as framed and decided by the Tribunal).

Arguments of the Parties

Appellants' (Buyers') Arguments

  • The Refund Guarantee obligation should be construed as a condition because of the express "no later than 120 days" long-stop wording and the commercial significance of the guarantee.
  • Interdependence: the obligation to provide the Refund Guarantee was said to be interdependent with the Buyers' obligation to pay instalments and with the Yard's obligation to build the Vessels, making time of the essence (relying on mercantile authority such as Bunge v Tradax and other guarantees/letter-of-credit authorities).
  • If classified as an innominate term, the Buyers submitted the delay was nevertheless repudiatory in the circumstances and that the Tribunal misapplied or mis-stated the relevant legal principles on time stipulations in mercantile contracts.
  • Market risk argument: in a rising market a yard might delay to pursue higher-priced contracts, prejudicing Buyers who would then be unable to recover loss of bargain damages unless the term were a condition.

Respondents' (Yard's) Arguments

  • The obligation in Article X(A)(f) is an innominate term: the clause is not expressed to be a condition and the contractual scheme defers Buyers' payment obligations until receipt of the Refund Guarantee, so there is no immediate interdependence that makes time of the essence for construction.
  • The SBCs contain a comprehensive regime dealing with delay, liquidated damages, and specific termination rights (Article X) including an express refund mechanism and mutual discharge on refund (Article X.3), demonstrating that parties chose contractual remedies rather than automatic termination with loss-of-bargain damages.
  • Tribunal factual findings (Yard solvent at contracting, ordinary commercial expectations, and the absence of evidence that the Refund Guarantee was an earnest of performance) support treating the term as innominate; Buyers cannot challenge those findings on appeal.
  • If the Yard wrongfully refused to build the Vessel, that would constitute renunciation and permit rescission and damages; but delay in providing the Refund Guarantee does not automatically prevent performance of the SBCs.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Dolphin Tanker SRL v Westport Petroleum Inc. (The Savina Caylyn) [2011] 1 Lloyd's Rep 550 Appeal on a question of law limited to facts found by arbitrators; courts must accept arbitrators' factual findings. Reiterated principle that this appeal is confined to the facts found by the Tribunal and the court must not re-open factual findings.
Geogas SA v. Trammo Gas Ltd, The 'Baleares' [1993] 1 Lloyd's Rep 215 Arbitrators are masters of the facts; limits on court re-evaluating factual findings on appeal. Used to support the principle that the court must accept Tribunal's factual matrix.
ICS v. West Bromwich BS [1998] 1 WLR 896 Commercial background admissible but limited to findings in the award. Confirmed that commercial background must derive from the Tribunal's factual findings.
Bunge v Tradax [1981] 1 WLR 711 When time stipulations in mercantile contracts may be treated as conditions; interdependence and need for certainty. Central authority for distinction between conditions and innominate terms; analysed and applied to the SBCs' context and interdependence issues.
United Scientific Holdings Ltd v Burnley BC [1978] AC 904 Time stipulations not automatically of the essence; balance detriment to parties. Explained legal approach to whether time is of the essence; used to frame analysis.
The Spar Capella [2015] EWHC 718 (Comm) Payment-time stipulation and presence of contractual withdrawal clause indicate term classification; contractual termination clause influence. Emphasised that contractual termination rights weigh in favour of treating a term as innominate where parties provided a contractual option to terminate.
The Arctic [2019] 2 Lloyd's Rep 603 General guidance on classification of contractual terms; interdependence and textual/contextual factors. Applied the Spar Capella guidance to non-time clause; supported the proposition that terms are innominate unless clearly a condition.
Harold Wood Brick Co v Ferris [1935] 2 KB 198 Long-stop dates and "not later than" phrasing can be condition in context. Distinguished on facts: contextual approach required; "no later than" alone insufficient to create a condition.
Teekay Tankers v STX Offshore [2018] 1 All ER 279 Obiter remarks concerning consequences where a yard cannot finance construction without guarantees; relevance of factual context. Distinguished: the court treated many of those remarks as obiter and the present factual findings differed (yard solvent at contracting).
The Hansa Murcia [2013] 1 All E.R. (Comm) 1277 Failure to maintain/extend refund guarantee is not automatically repudiatory; repudiation depends on whether buyer's security is imperilled. Supportive of the Tribunal's conclusion that delay in a refund guarantee is not necessarily repudiatory absent practical risk to Buyers' funds.
Classic Maritime v Lion Diversified Holdings [2010] 1 Lloyd's Rep 59 Provision of guarantee treated as condition where guarantee is fundamental due to counterparty financial position and contract value. Distinguished: factual interdependence and financial weakness present there were absent in the SBCs.
Cehave NV v Bremer Handelsgesellschaft mbH (The Hansa Nord) [1976] QB 44 Principles on classifying contractual terms and need to consider surrounding circumstances. Referred to in discussion of long-standing principles guiding condition vs innominate classification.
Other authorities cited (e.g. Bentsen v. Taylor, Sons Co. [1893] 2 QB 274; STC v Golodetz [1989] 2 Lloyd's Rep 277; March Engineering v Emblem [1990]) Older authority and supporting case law on classification of contractual terms and related principles. Used to develop and corroborate the multi-factor construction approach applied to Article X(A)(f).

Court's Reasoning and Analysis

The court analysed whether Article X(A)(f) was, on true construction, a condition or an innominate term, applying established authorities (notably Bunge v Tradax, United Scientific, The Spar Capella and The Arctic). The analysis proceeded as follows:

  1. Legal starting point: unless wording or context shows that a stipulation is intended as a condition, the term is innominate. The court endorsed the Tribunal's starting point that the default is not to treat time stipulations as conditions absent clear indication.
  2. Textual analysis: Article X(A)(f) is not expressed to be a condition. The phrase "no later than 120 days" denotes a time limit but, by itself, is not decisive. The clause expressly permits the Buyer to designate a later date "from time to time", a factor pointing away from a fixed long-stop condition.
  3. Interdependence and commercial matrix: the court examined whether the Refund Guarantee was interdependent with the Yard's ability to construct the Vessels (as in Bunge). It found key distinctions: the SBCs deferred the Buyer's payment obligations until receipt of the Refund Guarantee (the instalments do not become due if the guarantee is not provided), so a failure to provide the Refund Guarantee did not place the Buyer in immediate default of payment nor automatically derail the Yard's construction obligations. The Tribunal's factual findings (not open to re-litigation on appeal) included that the Yard was solvent at contracting and construction could begin notwithstanding absence of the Refund Guarantee.
  4. Contractual scheme and termination clause: the SBCs contain a comprehensive regime for delay and default (liquidated damages for delivery delay; rights to rescind after specified delays; Article X termination rights linked to refund and Article X.3 mutual discharge). The existence of an express contractual termination option and the express provision that refund triggers mutual discharge indicate that the parties agreed contractual remedies rather than automatic common-law termination with loss-of-bargain damages. That scheme weighed in favour of treating Article X(A)(f) as innominate.
  5. Risk of technicality and range of breaches: the court emphasised that breaches of the Refund Guarantee timing could range from trivial (a short delay causing no loss) to serious. That characteristic is a hallmark of an innominate term.
  6. Distinguishing authorities relied on by Buyers: cases where guarantees or letters of credit were found to be conditions were distinguished on their facts (financial weakness of counterparties, tight interdependence and the essential nature of the guarantee to enable the seller's performance). Teekay's obiter remarks were treated as inapposite given differing factual findings in the present case.
  7. Conclusion of law applied to facts: on the Tribunal's factual findings and the contract's text and structure, Article X(A)(f) was an innominate term; the Yard's failure entitled Buyers to exercise contractual cancellation under Article X but did not automatically confer loss-of-bargain damages.

Holding and Implications

Holding: DISMISSED — the appeals are dismissed. The court held that Article X(A)(f) is an innominate term, not a condition, and there was no error of law in the Tribunal's conclusion.

Implications:

  • Direct effect on the parties: the Buyers were entitled to exercise their contractual option to rescind under Article X when Refund Guarantees were not provided within the contractual period, but they were not automatically entitled to loss-of-bargain (secondary/common-law) damages solely on that basis.
  • Contractual design respected: the decision upholds the parties' negotiated contractual scheme (deferred instalment obligations, liquidated damages, and a specific termination/refund mechanism) as determining the remedies for delay/non-provision of Refund Guarantees.
  • No new general precedent altering the established construction principles was created: the court applied existing authorities (Bunge, United Scientific, The Spar Capella, The Arctic, and related cases) and reiterated that classification of time stipulations depends on textual and contextual construction and the parties' allocated contractual remedies.