McLaughlin & Harvey Ltd v LJJ Ltd

England and Wales High Court (Technology & Construction Court)
May 2, 2024
Smart Summary (Beta)

Factual and Procedural Background

The Plaintiff, a large construction and civil engineering company, was engaged by Company A under a JCT 2016 Design and Build contract for the fit-out and refurbishment of a building known as Christchurch Court, Paternoster Square, London. The Plaintiff subcontracted the mechanical and electrical installations work to the Defendant, a specialist mechanical and electrical contractor, under an amended JCT 2016 Design and Build Sub-Contract with a sum of approximately £17 million.

There have been five adjudications between the parties concerning the Sub-Contract, all but one before the current Adjudicator. None of the previous adjudicator decisions have been substantively challenged and are binding. The present proceedings concern the fifth adjudication.

On 12 September 2023, the Plaintiff issued an Adjudication Notice seeking Key Date Damages from the Defendant amounting to £1,160,000 or such other sum as the Adjudicator might determine, payable forthwith.

The Adjudicator issued a Decision on 31 October 2023 directing the Defendant to pay £808,000 in Key Date Damages within seven days. Subsequently, the Defendant submitted extensive comments beyond clerical or typographical corrections, prompting the Adjudicator to issue a Revised Decision on 4 November 2023, amending the original Decision to include qualifications concerning whether the sum had already been allowed.

The Plaintiff sought summary judgment to enforce the original Decision, while the Defendant resisted enforcement on four grounds, including that the Revised Decision superseded the original and that the Adjudicator erred in issuing the Revised Decision.

Legal Issues Presented

  1. Whether the Revised Decision issued by the Adjudicator on 4 November 2023 superseded the original Decision of 31 October 2023, thereby preventing enforcement of the original Decision.
  2. Whether the Adjudicator's purported error in issuing the Revised Decision was an error within jurisdiction such that the court should not interfere.
  3. Whether the Plaintiff can approbate and reprobate the original Decision by seeking enforcement of it while also proposing corrections.
  4. Whether the Plaintiff is entitled to enforce the Revised Decision.

Arguments of the Parties

Defendant's Arguments

  • The Revised Decision supersedes the original Decision, thus the original cannot be enforced.
  • If the Adjudicator erred in issuing the Revised Decision, it was an error within his jurisdiction, and the court should not intervene.
  • The Plaintiff cannot both accept and reject the original Decision ("approbate and reprobate").
  • The Plaintiff cannot enforce the Revised Decision.

Plaintiff's Arguments

  • The Plaintiff contends that the Revised Decision was beyond the Adjudicator's power under the Scheme for Construction Contracts 1998, paragraph 22A(1), which limits corrections to clerical or typographical errors.
  • The Plaintiff argues that the further submissions made by the Defendant went beyond clerical corrections and that the Adjudicator's amendments constituted a substantive qualification or clarification, which he did not have jurisdiction to make.
  • The Plaintiff submits that it is entitled to enforce the original Decision notwithstanding minor corrections it made in response to the Adjudicator's invitation.
  • The Plaintiff argues that the Revised Decision does not address the key factual dispute concerning whether Key Date Damages had already been allowed, reinforcing that the Revised Decision was a clarification rather than a correction.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Axis M&E UK Limited v Multiplex Construction Europe Limited [2019] EWHC 169 (TCC) Clarification of the scope of the slip rule under paragraph 22A(1) of the Scheme for Construction Contracts 1998; correction limited to clerical or typographical errors arising by accident or omission, not substantive or second thoughts. The court relied on this authority to determine that the Adjudicator's amendments were substantive and thus outside the power to correct clerical errors.
Lesotho Highlands Development Authority v Impregilo SpA [2006] 1 AC 221 Distinction between an error within jurisdiction (erroneous exercise of power) and excess of jurisdiction (acting outside powers); erroneous exercise does not amount to excess. The court applied this principle to conclude that even if the Adjudicator erred, it was important to decide if the power exercised was within jurisdiction; found that the Revised Decision was outside jurisdiction as it was not a clerical correction.
O'Donnell Developments Limited v Build Ability Limited [2009] EWHC 3388 (TCC) Discussion on court interference with adjudicator's exercise of slip rule jurisdiction; erroneous exercise of slip rule does not take adjudicator outside jurisdiction. The court considered this case but distinguished it on facts, concluding the present Adjudicator acted outside his jurisdiction by making substantive amendments.
Macob Civil Engineering Limited v Morrison Construction Limited (1999) BLR 93 Doctrine of election: a party cannot "blow hot and cold" by accepting and rejecting an adjudicator's decision. The court found the Plaintiff was not prevented from enforcing the original Decision despite proposing minor corrections, thus no breach of the doctrine.
Bloor Construction (UK) Ltd v Bowmer & Kirkland (London) Ltd [2000] BLR 314 Scope of adjudicator's power to correct mistakes under an implied slip rule. The Adjudicator cited this case to justify corrections, but the court found the power under the Scheme to be narrower, limiting corrections to clerical or typographical errors only.

Court's Reasoning and Analysis

The court began by examining whether the Revised Decision superseded the original Decision and whether it was a valid correction under paragraph 22A(1) of the Scheme for Construction Contracts 1998. The court emphasized that the power to correct is narrowly confined to clerical or typographical errors arising by accident or omission.

Relying on authoritative definitions and precedent, the court found that a "clerical error" involves a mistake in transcription or expression by a clerk or penman, not a substantive change in reasoning or intention. The court concluded that the Adjudicator’s amendments were substantive, involving qualification and clarification of the Decision based on further submissions, rather than correction of clerical errors.

The court then considered whether the Adjudicator’s purported error in issuing the Revised Decision was an error within jurisdiction, referencing the House of Lords decision in Lesotho Highlands Development Authority v Impregilo SpA. That case established that an erroneous exercise of power does not amount to excess of power and thus does not remove jurisdiction. However, the court distinguished the present case, concluding that the Adjudicator exercised a power he did not have, effectively giving effect to second thoughts rather than correcting a slip. This placed the Revised Decision outside jurisdiction.

The court also analyzed the Defendant’s reliance on O'Donnell Developments Limited v Build Ability Limited, which suggested courts should not interfere with an adjudicator’s exercise of slip rule jurisdiction if the slip is agreed or accepted. The court found this authority was obiter and fact-sensitive, and on the facts here, the Adjudicator’s actions were not within the slip rule jurisdiction.

On the doctrine of approbation and reprobation, the court held that the Plaintiff’s minor corrections in response to the Adjudicator’s invitation did not prevent enforcement of the original Decision.

Finally, the court concluded that the Revised Decision did not supersede the original Decision and that enforcement of the original Decision was appropriate.

Holding and Implications

The court held that the Plaintiff is entitled to summary judgment to enforce the Adjudicator’s Decision dated 31 October 2023 for the sum of £808,000.

Holding: The Revised Decision issued on 4 November 2023 did not validly supersede the original Decision as it was beyond the Adjudicator’s jurisdiction to make substantive amendments under the slip rule. Therefore, the original Decision remains enforceable.

Implications: The Defendant must pay the sum determined by the original Decision within the stipulated timeframe. The court emphasized that enforcement of adjudicator decisions is the norm except in very exceptional cases. The question of whether the Defendant has already allowed the sum under the Sub-Contract or other mechanisms is a matter for separate contractual or arbitral processes and does not constitute a ground to resist enforcement here. No new precedent was established; the decision applies existing principles to the facts at hand.