Thompson & Anor v An Bord Pleanala (Approved)
Factual and Procedural Background
The case concerns an application under Sections 50 and 50A of the Planning and Development Act 2000 (as amended), brought by the Applicants, academic scientists, challenging a decision of the Respondent, the planning authority, An Bord Pleanála. The Notice Party had lodged a planning application on 14 March 2022 with Fingal County Council for subdivision of a site and construction of a single story infill dwelling at a location on Howth Road, Sutton, Dublin 13. The Council requested additional information and subsequently granted permission with conditions on 28 September 2022. The Applicants appealed this decision to the Board on 26 October 2022. The Board’s decision to grant permission was made on 26 June 2023 and formalised in a Board Order dated 28 June 2023.
The Applicants brought judicial review proceedings challenging the Board’s decision, but their application was one day late according to the conventional interpretation of the statutory time limits. They argued that time should run from notification of the decision rather than the date of the decision itself, or alternatively sought an extension of time. The Respondent and Notice Party opposed these contentions.
Procedurally, the application for leave to apply for judicial review was initiated on 23 August 2023 before Roberts J. The matter underwent several procedural steps including adjournments due to non-compliance with notification rules and filing requirements. Leave was eventually granted on 6 November 2023. Directions for the filing of affidavits and submissions were given, and a motion regarding the time issue was brought by the Applicants on 16 January 2024. The hearing took place on 20 February 2024 with judgment reserved.
Legal Issues Presented
- Whether the judicial review proceedings were brought within the statutory eight-week time limit prescribed by Section 50(6) of the Planning and Development Act 2000 (as amended), given that the Applicants filed one day late.
- Whether time for bringing the proceedings should run from the date of the Board’s decision or from the date of notification to the Applicants.
- Whether the Court should exercise its discretion to extend the time limit under Section 50(8) of the Planning and Development Act 2000 (as amended) based on good and sufficient reason and circumstances outside the Applicants’ control.
- Whether the statutory scheme governing time limits is compatible with EU law, particularly in circumstances where the Board was in breach of its notification obligations.
Arguments of the Parties
Applicants' Arguments
- The Applicants contended that the time limit for judicial review should start running from the date they were notified of the Board’s decision, not the date of the decision itself, because the Board failed to notify them promptly.
- They argued that the Board was in breach of its statutory duty to notify and publish the decision within three days, and this breach should affect the commencement of the time limit.
- Alternatively, they sought an extension of time under Section 50(8), submitting good and sufficient reasons including late notification and personal difficulties such as illness in the family.
- They also raised a fall-back EU law argument that the domestic statutory time limits, as applied strictly from the date of the decision, may be incompatible with EU principles of legal certainty, equivalence, and effectiveness.
Respondent and Notice Party's Arguments
- They maintained that the statutory time limit runs from the date of the decision itself as expressly provided by Section 50(6) of the Planning and Development Act 2000 (as amended), supported by a substantial body of caselaw.
- The late notification by the Board did not affect the commencement of the time limit.
- They argued the Applicants failed to establish good and sufficient reason or circumstances outside their control to justify an extension of time under Section 50(8).
- They submitted that the Applicants’ EU law arguments amounted to re-writing the legislation and were misconceived.
- The Board acknowledged it had been in default of its obligation to publish the decision within three days but contended this did not affect the statutory time limit for challenge.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Heather Hill Management Company CLG & Anor v. An Bord Pleanála & Anor [2019] IEHC 186 | Time limits for judicial review apply to final decisions, not sub-decisions such as Appropriate Assessment. | Supported the proposition that time runs from the date of the final decision, not notification. |
| Urrinbridge Ltd. v. An Bord Pleanála [2011] IEHC 400 | Interpreted Section 50(7) regarding when time runs for judicial review, emphasizing notice of decision as relevant. | Clarified that the full statutory text must be considered; time runs from decision date for normal planning decisions. |
| Irish Skydiving Club Ltd. v. An Bord Pleanála [2016] IEHC 448 | Confirmed that time runs from the date of the decision, not notification. | Reinforced the settled interpretation of statutory time limits. |
| Kelly v. Leitrim County Council and An Bord Pleanála [2005] IEHC 11 | Supported the statutory interpretation of time limits for judicial review. | Used to affirm the principle that time runs from the date of decision. |
| Reidy v. An Bord Pleanála [2020] IEHC 423 | Reinforced the application of statutory time limits. | Applied to confirm the commencement of time from the decision date. |
| O'Riordan v. An Bord Pleanála [2021] IEHC 1 | Confirmed the approach to timing of judicial review applications. | Supported the established statutory interpretation. |
| Heaney v. An Bord Pleanála [2022] IECA 123 | Confirmed that time runs from the date of the decision for judicial review applications. | Held not to be per incuriam and binding on the court. |
| Krikke v. Barranafaddock Sustainable Electricity Ltd. [2022] IESC 41 | Confirmed compatibility of statutory time limits with EU law principles of equivalence and effectiveness. | Supported the conclusion that the statutory scheme is consistent with EU law. |
| Uniplex (UK) Ltd, C-406/08, ECLI:EU:C:2010:45 | Discussed legal certainty in relation to time limits under EU law. | Referenced as relevant to the EU law arguments about notification and timing. |
Court's Reasoning and Analysis
The Court analysed the statutory framework governing the timing of judicial review applications under the Planning and Development Act 2000 (as amended), particularly Sections 50(6), 50(7), and 50(8). It emphasised that the time limit for bringing a judicial review challenge to a planning decision runs from the date of the decision itself, not the date of notification, consistent with settled caselaw and statutory text. The Court carefully compared the full statutory language with prior quotations relied upon by the Applicants, noting that selective omission of critical parts led to misunderstanding.
The Court found that the Board was in breach of its statutory obligation to publish the decision and relevant materials within three days, but this did not alter the commencement of the time limit. The Applicants failed to bring proceedings within the eight-week period running from the decision date, being one day late.
Regarding the extension of time, the Court held that the Applicants did not satisfy the statutory test under Section 50(8), which requires both good and sufficient reason and that the failure to bring proceedings in time was caused by circumstances outside their control. The Applicants’ mistaken belief as to when time started to run and their strategy of corresponding with the Board rather than promptly consulting legal advisers were not circumstances beyond their control causing the delay.
The Court addressed the Applicants’ EU law arguments as a fall-back, acknowledging the possibility that strict application of the time limit might raise EU law issues if notification is delayed. However, the Court noted that the Supreme Court has upheld the compatibility of the statutory scheme with EU law principles. The Court observed that the Applicants had not yet involved the State in these EU law challenges and directed that notice be given to the State to allow proper consideration of these issues.
Ultimately, the Court reaffirmed the settled legal position that time runs from the date of the decision, not notification, and that the extension of time was not justified on the facts.
Holding and Implications
The Court’s final decision was to DISMISS the Applicants’ motion to declare that their proceedings were within time and to refuse an extension of time under Section 50(8) of the Planning and Development Act 2000 (as amended).
The direct effect of this decision is that the judicial review application was brought out of time and is therefore liable to be dismissed on that ground unless the Applicants succeed in obtaining an extension of time in future proceedings. The Court did not set any new precedent but confirmed the established legal position regarding the commencement of statutory time limits for challenging planning decisions. The Court also ordered procedural steps to allow the Applicants to notify the State regarding their EU law arguments, ensuring those issues can be properly addressed in due course.