King v An Bord Pleanala (Approved)
Factual and Procedural Background
The applicant initiated judicial review proceedings challenging the decision of the respondent authority to confirm a compulsory purchase order (CPO) related to a proposed waste water treatment plant and associated infrastructure near a village in County Galway. The notice party is a statutory body responsible for water services, which proposed the development project.
The compulsory purchase order was made by the notice party on 5 December 2019 to acquire land necessary for the project. Objections to the CPO led to the respondent conducting an oral hearing and preparing reports and recommendations. The inspector recommended against confirming the CPO, citing the availability of more suitable alternative sites. However, the respondent ultimately decided on 3 March 2022 to confirm the CPO, finding that the selected site was suitable and that objections could not be sustained.
The applicant, a landowner affected by the CPO and an objector, commenced judicial review proceedings seeking to challenge the validity of the respondent's decision. Leave to apply for judicial review was granted ex parte, and opposition papers were filed. The applicant subsequently sought a pre-emptive costs order concerning the applicable costs regime for these judicial review proceedings.
Legal Issues Presented
- Whether the decision to confirm the compulsory purchase order constitutes part of a multi-stage "development consent" under the Environmental Impact Assessment Directive (Directive 2011/92/EU) and the Habitats Directive (Directive 92/43/EEC).
- Whether the judicial review proceedings attract the special costs rules prescribed under Section 50B of the Planning and Development Act 2000 and Part 2 of the Environment (Miscellaneous Provisions) Act 2011, which apply to certain environmental litigation.
- Whether the court has jurisdiction to grant a pre-emptive costs order in respect of proceedings where it is uncertain if the special costs rules apply.
- The interpretation of statutory provisions under the Planning and Development Act 2000 conferring powers to confirm compulsory purchase orders and whether these provisions "give effect to" the EIA Directive for the purpose of costs protection.
Arguments of the Parties
Applicant's Arguments
- The decision to confirm the compulsory purchase order is part of a multi-stage development consent subject to the EIA Directive.
- The decision involved consideration of environmental effects and alternative locations, thereby engaging the EIA Directive's requirements.
- Environmental impact assessment should have been carried out at the stage of confirming the CPO, not deferred until the planning application.
- The confirmation of the CPO effectively determines the location of the project, limiting public participation and narrowing options for environmental assessment.
- There are strong grounds to conclude that the statutory provisions under which the decision was made give effect to the EIA Directive, triggering the special costs regime.
- Refusing a pre-emptive costs order would unfairly expose the applicant to potentially prohibitive costs without certainty on costs protection.
Respondent's Arguments
- The decision to confirm the compulsory purchase order is a preliminary one and does not constitute development consent under the EIA Directive.
- The merits of site selection can be revisited in the subsequent planning permission process, including the possibility of refusal based on alternative sites.
- The statutory provisions do not expressly provide for environmental impact assessment or public participation at the CPO confirmation stage.
- The board lacks jurisdiction to carry out an environmental impact assessment in the context of confirming a compulsory purchase order.
- The legislative framework does not intend that an EIA be carried out at the CPO confirmation stage, and thus the special costs rules should not apply.
Notice Party's Arguments
- Initially suggested that a conforming interpretation of the statutory provisions to require EIA at the CPO stage might be contra legem but did not pursue this point.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Dunne v. Minister for the Environment Heritage and Local Government [2006] IESC 49 | Clarification that a decision does not constitute development consent merely because the project cannot proceed "but for" that decision; relevant criteria include whether the decision-maker can consider or modify environmental impacts. | Distinguished because the CPO confirmation involved consideration of environmental effects and alternatives, unlike the archaeological works decision in Dunne. |
| Heather Hill Management Company v. An Bord Pleanála [2022] IESC 43 | Definition of conditions under Section 50B of the Planning and Development Act 2000 for application of special costs rules in environmental litigation. | Used to establish the legal framework for determining whether special costs rules apply to the judicial review proceedings. |
| North East Pylon Pressure Campaign, Case C-470/16, EU:C:2017:781 (Advocate General Opinion) | Importance of clear and unambiguous rules regarding costs protection under Article 11 of the EIA Directive to avoid prohibitive costs for applicants. | Supported the existence of jurisdiction to grant pre-emptive costs orders to ensure compliance with EU law. |
| McCoy v. Shillelagh Quarries Ltd [2015] IECA 28 | Finality and binding nature of pre-emptive costs orders on the applicable costs regime. | Analogously applied to emphasize that the trial judge cannot revisit the costs regime determination made by the pre-emptive order. |
| O'Connor v. Offaly County Council [2020] IECA 72 | Discretionary considerations in granting costs protection when the issue is not ripe for determination. | Referenced to acknowledge that in some cases, discretion must inform pre-emptive costs orders. |
| Reid v. Industrial Development Agency [2015] IESC 82 | Recognition of constitutional protection of property rights affected by compulsory purchase orders. | Supported the solemnity and significance of the decision to confirm the compulsory purchase order. |
| Grealish v. An Bord Pleanála [2006] IEHC 310 | Expectation of consistency in decision-making by planning authorities between related decisions. | Used to argue that the CPO confirmation decision carries significant weight in subsequent planning applications. |
| Namur-Est Environnement, Case C-463/20, EU:C:2022:121 | Clarification on multi-stage development consents and the requirement for effective public participation at stages when all options are open. | Supported the argument that public participation and environmental assessment should occur prior to confirmation of the CPO. |
| Wells, Case C-201/02, EU:C:2004:12 | Environmental effects must be assessed at the principal decision stage unless effects only identifiable at implementing decision stage. | Referenced to frame the timing of environmental assessment in multi-stage consents. |
| Holohan, Case C-461/17, EU:C:2018:883 | Importance of alternatives in environmental impact assessment focused on influencing environmental effects. | Supported the significance of considering alternative locations in the assessment process. |
| Martin v. An Bord Pleanála [2007] IESC 23 | Multi-stage development consent can include decisions without express statutory functions for environmental impact assessment. | Supported the proposition that statutory provisions may be interpreted to give effect to the EIA Directive even absent express provisions. |
| Tobin v. Limerick City and County Council [2023] IEHC 626 | Compulsory acquisition under the Derelict Sites Act 1990 does not allow consideration of alternative locations. | Distinguished as the statutory regime differs from the Planning and Development Act 2000 regime at issue. |
| Village Residents Association Ltd v. An Bord Pleanála (No. 2) [2000] IEHC 34 | Recognition of High Court jurisdiction to grant pre-emptive costs orders. | Supported the court's jurisdiction to grant the pre-emptive costs order in the present case. |
| Enniskerry Alliance and Enniskerry Demesne Management Company v. An Bord Pleanála [2022] IEHC 6 | Confirmation that jurisdiction to grant pre-emptive costs orders persists notwithstanding statutory changes to costs jurisdiction. | Affirmed the court's jurisdiction to make the pre-emptive costs order. |
Court's Reasoning and Analysis
The court began by considering the nature of the decision to confirm the compulsory purchase order and whether it forms part of a multi-stage development consent under the EIA Directive. The court noted that the decision involved a substantive consideration of environmental effects, including alternative site locations, which aligns with the requirements of the EIA Directive for environmental assessment and public participation.
The court distinguished the present case from prior case law where decisions were held not to constitute development consent because the decision-maker lacked authority to reconsider or modify environmental aspects. Here, the respondent authority expressly evaluated alternatives and found no more suitable sites, effectively determining the project's location in advance of the planning permission stage.
This sequencing raises concerns about effective public participation and environmental assessment, as the confirmation of the CPO limits subsequent options and public input, contrary to the principles established by the Court of Justice of the European Union (CJEU) in recent case law.
The court further analyzed the statutory provisions under which the respondent acted, concluding that these provisions, when interpreted in light of EU law and the interpretative obligations imposed by the EIA Directive, are capable of giving effect to the Directive's requirements. Although the legislation does not expressly provide for environmental impact assessment at the CPO confirmation stage, the procedural powers of the respondent authority could be interpreted to accommodate such assessment.
Regarding the pre-emptive costs order, the court acknowledged the tension between the desirability of a definitive ruling on costs regimes and the complexity of the underlying legal issues, which would require a lengthy hearing. The court adopted a balancing approach, weighing the strength of the applicant's case that the special costs rules apply against the potential prejudice to the respondent if the order were made in error.
The court found that the applicant had established strong grounds that the special costs regime applies and that the greater risk of unfairness lies in refusing the pre-emptive costs order. The potential prejudice to the respondent was considered less significant and could be mitigated by the court's discretion in awarding costs in the substantive proceedings.
Accordingly, the court exercised its discretion to grant the pre-emptive costs order without definitively resolving the ultimate legal question, reserving that issue for the substantive judicial review hearing.
Holding and Implications
The court granted a pre-emptive costs order determining that the judicial review proceedings attract the special costs rules under Section 50B of the Planning and Development Act 2000. This order is final and conclusive regarding the applicable costs regime for these proceedings, barring appeal.
The direct effect is that costs will be allocated according to the special rules designed to ensure that the cost of environmental litigation is not prohibitively expensive for applicants. The order does not decide the substantive merits of the judicial review or whether the decision to confirm the compulsory purchase order is ultimately subject to the EIA Directive. Should the substantive hearing find that the special costs rules do not apply, the pre-emptive costs order will stand as binding for the present proceedings but may inform other cases.
No new precedent was set beyond confirming the court's jurisdiction to make such a pre-emptive costs order in complex cases and the appropriateness of balancing considerations when the legal question is difficult.