Factual and Procedural Background

The applicants challenged the grant of a five-year foreshore licence issued by the Minister for Housing, Local Government and Heritage to Company B to undertake geotechnical, geophysical, ecological, wind, wave, and current monitoring investigations for the proposed Dublin Array offshore wind farm off the coast of counties Dublin and Wicklow. The licence was executed on 13th January 2023.

The application for the licence was made on 1st October 2021 under section 3 of the Foreshore Act 1933 and was accompanied by a Natura Impact Statement and an Appropriate Assessment screening report. Two public consultations were conducted, with submissions from the public and prescribed bodies. An independent environmental consultant prepared an Appropriate Assessment screening report in May 2022, and the Minister published an Appropriate Assessment Screening Determination on 20th June 2022.

The Minister carried out a second public consultation regarding the Appropriate Assessment Screening from 30th June to 29th July 2022. Following further reports and assessments, the Marine Licence Vetting Committee concluded in November 2022 that the proposed works would not adversely affect the environment or European sites. The Minister approved the Appropriate Assessment Determination on 23rd November 2022.

The Appropriate Assessment did not consider cumulative and in-combination effects of projects for which consent had been applied but not granted, only those with granted consent. The licence was published in the official gazette on 27th January 2023.

The applicants initiated judicial review proceedings on 26th April 2023. The court granted and maintained an interim stay on the licence. Procedural developments included striking out the Minister of State as a respondent, partial dismissal of the case save for two points, an order of mandamus regarding licence amendment, and a decision to refer legal questions to the Court of Justice of the European Union (CJEU) for preliminary ruling.

The Maritime Area Regulatory Authority (MARA) was joined as a notice party and later added as a respondent following transfer of functions under the Maritime Area Planning Act 2021. Appeals have been filed by both the applicants and the State, with hearings scheduled in January 2024. The court formally stayed substantive finalisation of proceedings pending the CJEU judgment.

Legal Issues Presented

  1. Whether the phrase "in combination with other plans or projects" in Article 6(3) of Council Directive 92/43/EEC includes plans or projects for which applications for approval or consent have been submitted but not determined.
  2. If yes, whether appropriate assessment requires considering only those pending projects drawn to the attention of the competent authority, or all projects of which the authority is or ought to be aware.
  3. If yes, whether appropriate assessment requires considering pending projects submitted to different competent authorities, similarly limited by notice or awareness.
  4. If yes, whether appropriate assessment must include projects for which applications have not yet been made to any competent authority.
  5. If yes, whether assessment should be limited to projects drawn to the attention of the competent authority or include all projects of which it is or ought to be aware.
  6. Whether a national court may refuse to quash a development consent despite an incomplete appropriate assessment that failed to consider cumulative or in-combination effects by reference to pending projects, if there is no reasonable scientific doubt as to absence of adverse effects on European sites.
  7. If yes, whether the national court's assessment of absence of reasonable scientific doubt must be limited to matters pleaded and evidence before the decision-maker, or may include further evidence regardless of pleading or prior establishment.
  8. If yes, whether the assessment of absence of reasonable scientific doubt must be conducted solely on material before the competent authority at the time of the appropriate assessment, or may include facts and matters at the time of the decision to grant consent.

Arguments of the Parties

Applicants' Arguments

  • The words "in combination with other plans or projects" in Article 6(3) include projects with applications submitted but not yet determined, consistent with the precautionary principle and obligations to avoid deterioration and disturbance in European sites.
  • Appropriate assessment should consider all relevant pending projects of which the competent authority is or ought to be aware, not limited to those specifically drawn to its attention.
  • Assessment should include projects proposed but not yet applied for, to ensure lawful and comprehensive evaluation on remittal.
  • National courts should not quash development consents if no reasonable scientific doubt exists as to adverse effects, but the assessment of such doubt should consider all evidence and not be limited by prior pleadings or evidence.
  • The assessment of absence of reasonable scientific doubt should be based on facts and matters at the time of the decision to grant consent, not limited to material at the time of the appropriate assessment.

State's Arguments

  • Article 6(3) requires assessment only of projects that are existing or approved, excluding those merely proposed or with pending applications.
  • Competent authorities should consider only projects specifically drawn to their attention to avoid an unmanageable and open-ended assessment burden.
  • If the court finds otherwise, national courts may refuse to quash consents where absence of reasonable scientific doubt is established.
  • The court's assessment of absence of reasonable scientific doubt must be limited to matters pleaded by the applicant and evidence before the decision-maker.
  • The assessment of absence of reasonable scientific doubt should be based solely on material before the competent authority at the time of the appropriate assessment, not on subsequent facts.

Company B's Arguments

  • Did not provide specific proposed wording but generally aligned with the State's position opposing inclusion of pending projects not yet approved.
  • Argued that certain questions on projects not applied for are moot and hypothetical as they were not pleaded or supported by evidence.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Pasquale Foglia v Mariella Novello (C-244/80) [1981] Guidance on hypothetical questions in preliminary rulings Referenced to reject moot or hypothetical objections to questions referred to the CJEU.
Commission v Ireland (C-392/96) [1999] Interpretation of environmental directives and obligations Used as relevant EU precedent on environmental assessment obligations.
R. (Wells) v Secretary of State for Transport (C-201/02) [2004] Environmental impact assessment principles Referenced in context of appropriate assessment requirements.
Waddenzee v Staatssecretaris (C-127/02) [2004] Protection of Natura 2000 sites and assessment obligations Considered in relation to the integrity of European sites.
Commission v Ireland (C-418/04) [2007] Compliance with Habitats Directive provisions Referenced to support interpretation of Article 6(3) obligations.
Ecologistas en Acción-CODA (C-142/07) [2008] Environmental assessment and precautionary principle Applied to issues of cumulative effects and assessments.
Inter-Environnement Wallonie and Terre wallonne (C-41/11) [2012] Environmental procedural requirements Used to clarify procedural aspects of assessment.
Gemeinde Altrip (C-72/12) [2013] Interpretation of environmental impact assessment directives Considered in relation to cumulative effect assessments.
Slovak Bears II (C-243/15) [2016] Assessment of plans affecting protected sites Referenced regarding appropriate assessment scope.
Commission v Germany (C-142/16) [2017] Environmental protection obligations Applied to interpretation of EU environmental law.
Comune di Corridonia and Others (C-196/16 and C-197/16) [2017] Assessment of cumulative effects under Habitats Directive Used to support the court’s understanding of cumulative assessment requirements.
Comune di Castelbellino v Regione Marche (C-117/17) [2018] Environmental assessment procedural requirements Referenced for procedural context in assessments.
Coöperatie Mobilisation for the Environment and Others (C-293/17 and C-294/17) [2018] Environmental protection and compliance Considered in relation to the thoroughness of assessments.
Commission v Ireland (C-261/18) [2019] Interpretation of Habitats Directive provisions Used to clarify obligations under Article 6(3).
Land Nordrhein-Westfalen (C-535/18) [2020] Environmental impact and assessment standards Referenced regarding procedural and substantive standards.
Dansk Akvakultur v Miljø- og Fødevareklagenævnet (C-278/21) [2022] Unlawfully authorised projects and remediation Considered as academic commentary and relevant precedent on unlawful projects.
Hellfire Massy Residents Association v An Bord Pleanála (C-166/22) [2023] Environmental assessment and judicial review Referenced for procedural and substantive guidance on assessments.

Court's Reasoning and Analysis

The court examined the interpretation of Article 6(3) of Directive 92/43/EEC concerning whether pending projects with undetermined applications must be included in appropriate assessments. It noted the applicants' argument that excluding such projects contradicts the precautionary principle and undermines protection objectives, while the State and Company B argued for limiting assessment to existing or approved projects to avoid unmanageable administrative burdens.

The court found that the European Commission's guidance supports inclusion of projects that have been submitted for consent but not yet determined, as this interpretation aligns with the Directive's conservation goals. The court further considered the scope of projects to be assessed cumulatively or in combination, concluding that competent authorities must take reasonable steps to identify relevant projects but are not required to conduct exhaustive inquiries. The court emphasized the importance of reasonableness and practicality in fulfilling these obligations.

Regarding remedies, the court reasoned that if an appropriate assessment is defective but the court is satisfied there is no reasonable scientific doubt about the absence of adverse effects, quashing the consent would be formalistic and unnecessary. The court also held that judicial review should be conducted de novo with regard to scientific evidence, without being restricted by prior pleadings or evidence limitations.

The court addressed procedural issues with the transfer of functions to the MARA and corrected errors in the statutory commencement status, ensuring the correct legal entity is responsible for compliance and remedial actions.

Holding and Implications

The court ordered that the legal questions concerning the interpretation of Article 6(3) of Directive 92/43/EEC be referred to the Court of Justice of the European Union for a preliminary ruling under Article 267 TFEU, requesting an expedited procedure.

The court also directed procedural steps including the preparation and submission of papers for the CJEU, maintenance of the stay on substantive proceedings pending the CJEU judgment, and reserved costs related to the reference.

The direct effect of this decision is to pause final determination of the judicial review proceedings until the CJEU provides authoritative interpretation. The ruling does not itself set new precedent but frames the scope of appropriate assessments, the obligations of competent authorities, and the approach to judicial review and remedies in cases involving cumulative and in-combination effects of pending projects under EU environmental law.