Save The South Leinster Way & Anor v An Bord Pleanala & Ors (Approved)
Factual and Procedural Background
The case concerns a judicial review application under section 50 of the Planning and Development Act, 2000, as amended, relating to a decision to grant planning permission for a wind farm development at Castlebanny, County Kilkenny. The South Leinster Way, a walking route affected by the development, is part of the European E8 walking route. The applicants are an environmental protection organisation established in 2020 and its chairperson, both residing in the zone of influence of the proposed development.
The developer applied for planning permission directly to the planning board under the Strategic Infrastructure Development (SID) procedure. The board granted permission on 26th September 2022 for the construction of 21 wind turbines and ancillary works.
Under section 50(6) of the Planning and Development Act, an application for leave to apply for judicial review must be made within 8 weeks of the decision. The applicants filed their application on the 21st November 2022, one day after the expiry of the 8-week period, which ended on Sunday, 20th November 2022. Leave was granted on 23rd January 2023, and the applicants later sought to amend their statement of grounds to include a claim for an extension of time to make the application.
The court considered the applicants' motion to amend the grounds and their request for an extension of time to apply for judicial review beyond the statutory 8-week period.
Legal Issues Presented
- Whether the applicants were out of time in applying for leave to apply for judicial review, given that the 8-week period expired on a Sunday and the application was filed on the following Monday.
- Whether the court should extend the time period for making the application for leave to apply for judicial review under section 50(8) of the Planning and Development Act, 2000.
Arguments of the Parties
Applicants' Arguments
- The applicants argued that, by analogy with the expiry of limitation periods on days when court offices are closed, there should be a presumption that the time period extends to the next working day if the last day falls on a weekend or holiday.
- The applicants relied on Order 122, Rule 3 of the Rules of the Superior Courts, which provides a grace day if a time limit expires on a day when court offices are closed.
- They referred to information from the European Union E-Justice portal indicating that in other EU Member States, deadlines expiring on weekends or holidays are extended to the next working day.
- The applicants sought an extension of time to apply for judicial review in the event the court found the application was out of time.
Respondents' and Notice Party's Arguments
- The respondents and notice party contended that the statutory 8-week period must be strictly applied without implied extensions for weekends or holidays.
- They emphasized the commercial context and the importance of certainty in planning law, supported by extensive jurisprudence requiring strict compliance with time limits.
- They argued that the Rules of the Superior Courts do not apply to statutory time limits and that the Planning and Development Act expressly provides for disregarding certain periods, but not weekends or holidays in this context.
- The notice party highlighted the absence of any evidence that the applicants were prevented from applying within time or that the delay was outside their control.
- They submitted that human error, including legal error, is not a good and sufficient reason to extend time in this commercial context.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| K.S.K. Enterprises v. An Bord Pleanála [1994] 2 I.R. 128 | Strict approach to time limits in planning cases due to commercial context and need for certainty. | Supported the court's emphasis on strict compliance with statutory time limits. |
| Noonan Services Limited & Ors v. the Labour Court (Unreported, 2004) | Reinforces need for expedition and strict time limits in commercial contexts. | Used to illustrate the principle of strict time limits. |
| Irish Skydiving Club Ltd. v. An Bord Pleanála [2016] IEHC 448 | Importance of strict adherence to procedural time limits in planning matters. | Reinforced the court's position on time limit enforcement. |
| Kelly v. Leitrim County Council [2005] IEHC 11 | Strict compliance with statutory time limits in planning law. | Supported the court's reasoning on time limits. |
| Shell E & P Ireland Ltd v. McGrath [2013] IESC 1 | Clarified the application of strict time limits in commercial and planning contexts. | Used to reject the applicants' argument for implied extensions. |
| Drumquin Construction (Barefield) Ltd. v. Clare C.C. [2017] IEHC 818 | Emphasizes need for expedition in planning-related judicial reviews. | Supported the court's strict approach to time limits. |
| Arthropharm (Europe) Ltd v. The Health Products Regulatory Authority [2022] IECA 109 | Broad principle of expedition in commercial contexts. | Highlighted the prejudice to private law actors from delays. |
| O'Riordan v. An Bord Pleanála [2021] IEHC 1 | Strict time limits in planning judicial review not contrary to EU law. | Supported rejection of applicants' EU law argument. |
| Poole v. O'Sullivan [1993] 1 I.R. 484 | Limitation periods and extension principles in personal injury cases. | Distinguished as inapplicable to planning cases due to different policy considerations. |
| D.P.P. v. McCabe [2005] 2 IECCA 79 | Context-specific application of limitation rules. | Distinguished as unrelated to planning judicial review. |
| Max Developments Limited v. An Bord Pleanála [1994] 2 JIC 2502 | Leave on notice procedure and timing of judicial review applications. | Not directly applicable; later jurisprudence clarified timing rules. |
| McGuinness v. Armstrong Patents [1980] I.R. 289 | Concession-based decision on timing. | Not helpful to the applicants. |
| Heaney v. An Bord Pleanála [2022] IECA 123 | Strict time limits for judicial review are compatible with EU law. | Rejected applicants' EU law argument for extension. |
| Krikke v. Barranfaddock [2022] IESC 41 | Confirmed compatibility of strict time limits with EU law. | Supported court's refusal to extend time. |
| Reidy v. An Bord Pleanála [2020] IEHC 423 | Unawareness of correct limitation period is not good reason for extension. | Applied to reject applicants' excuse of human error. |
| Casey v. An Bord Pleanála [2004] 2 I.L.R.M. 296 | Short delays unsupported by good reason are fatal to extension applications. | Used to illustrate strict application of time limits. |
| Marshall v. Kildare County Council [2023] IEHC 73 | Short delay in judicial review application time is not excusable without good reason. | Reinforced strict adherence to time limits. |
Court's Reasoning and Analysis
The court first considered the applicants' argument that the statutory 8-week time limit for applying for judicial review should be extended by one day because the final day fell on a Sunday when court offices were closed. The court acknowledged that while there is an interpretative presumption in some contexts that deadlines expiring on non-working days extend to the next working day, this presumption does not apply here due to the commercial context and the specific statutory framework.
The court emphasized the importance of certainty and expedition in planning law, supported by extensive jurisprudence, which requires strict compliance with time limits. The Planning and Development Act expressly provides for disregarding certain days (e.g., Christmas period, COVID-19 emergency periods) but does not provide for extensions when the final day falls on a weekend or public holiday in the context of applicants issuing proceedings.
The court noted that the Act contains provisions allowing extensions for the planning board's decisions if the deadline falls on a holiday, but no equivalent provision exists for applicants. This indicated a legislative intention to exclude implied extensions beyond those expressly provided.
Regarding the applicants' request for an extension of time, the court applied the statutory test under section 50(8), which requires good and sufficient reason for the extension and that the circumstances causing the delay were outside the applicant's control. The court found that the applicants failed to satisfy either criterion. The delay was due to human error and a mistaken belief about the time limit, which is insufficient in this commercial context.
The court also rejected the applicants' reliance on EU law and the European Union E-Justice portal, finding no evidence that the applicants relied on or were misled by the information, and reaffirmed that strict time limits are compatible with EU law.
Finally, the court criticized the applicants for waiting until the last moment to act and for the lack of any evidential basis demonstrating that the delay was beyond their control.
Holding and Implications
The court made the following orders:
- The applicants were permitted to amend the statement of grounds to seek an extension of time, and the matter was treated as if that claim had been included without the formality of filing an amended pleading.
- The application for an extension of time was refused.
- The leave order was set aside and the leave application dismissed as out of time. The applicants were granted liberty to re-enter the proceedings within 28 days of any appellate court decision permitting an extension of time.
- The applicants' application to file a further substantive affidavit was dismissed.
- Unless otherwise agreed by the parties, the order was to be perfected forthwith on the basis of no order as to costs.
The direct effect of this decision is that the applicants' judicial review application was dismissed for being out of time, with no extension granted. The court reaffirmed the strict application of statutory time limits in planning judicial reviews and did not establish any new precedent altering the interpretation of the Planning and Development Act 2000 regarding time extensions for deadlines falling on weekends or holidays.