ATALIAN SERVEST AMK LTD AGAINST B W (ELECTRICAL CONTRACTORS LTD)

Scottish Court of Session
Feb 16, 2023
Smart Summary (Beta)

Factual and Procedural Background

In 2020, Company A was engaged as a subcontractor performing construction work at a prominent cricket ground in The City. Company A subcontracted Company B to carry out electrical works related to the project. The works did not proceed as planned, and both parties now assert financial claims against each other. These claims are to be finally determined in a substantive action initiated by Company B in May 2022. The present proceedings are satellite litigations aimed primarily at deciding interim payment obligations pending the resolution of the substantive action. Both actions were heard together on preliminary pleas.

The subcontract contained a clause (Clause 33 of Schedule 3) detailing procedures for final account submission, valuation, and payment, including timelines for notification of completion, submission of final accounts, issuance of a final account statement by Company A, and dispute resolution mechanisms including adjudication and court proceedings.

Company A notified Company B of practical completion in February 2022, and Company B submitted its final account in April 2022. Company A issued a final account statement in May 2022, which indicated a net sum payable by Company B to Company A. Company B disputed this statement and initiated adjudication and court proceedings within the contractual timelines.

The first adjudicator resigned due to the volume of material, and a second adjudicator was appointed. The second adjudicator issued a decision in November 2022, determining a net sum payable by Company A to Company B, rejecting the validity of Company A’s final account statement, and awarding interest and adjudicator’s fees.

Company B sought to enforce the adjudicator’s decision through the court, while Company A challenged the decision’s validity and sought declarators affirming the validity and binding nature of its final account statement and payment of the amount it claimed was due from Company B.

Legal Issues Presented

  1. Whether the adjudicator's decision should be enforced or set aside ope exceptionis on grounds of jurisdictional error, breach of natural justice, or failure to exhaust jurisdiction.
  2. Whether Company A’s Final Account Statement was validly issued in accordance with the subcontract and binding on Company B and the adjudicator.
  3. The competency of Company A’s action challenging the adjudicator’s decision and seeking payment under the Final Account Statement.

Arguments of the Parties

Defender's (Company A's) Arguments

  • The court must respect adjudicator decisions unless it is clear the adjudicator decided a question not referred to him or acted unfairly.
  • The adjudicator must decide within the scope of the referral and give parties opportunity to respond to new factual or legal bases.
  • The adjudicator improperly created a new contract ("beck and call contract") and decided on a basis not put to the parties, breaching natural justice.
  • The adjudicator failed to consider and exhaust various lines of defence advanced by Company A.

Pursuer's (Company B's) Arguments

  • The adjudicator’s decision addressed the dispute referred to him: the amount due under the subcontract.
  • The adjudicator was entitled to take initiative in ascertaining facts and law, including raising the validity of the Final Account Statement.
  • Both parties had ample opportunity to comment on the adjudicator’s valuation approach and procedural matters, negating any breach of natural justice.
  • The adjudicator considered and rejected Company A’s defences; failure to exhaust jurisdiction was not established.
  • Company A’s Final Account Statement was validly issued and binding on Company B and the adjudicator for the purposes of the adjudication.
  • Company A’s challenge to the adjudicator’s decision was not ripe for final determination and thus incompetent.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Carillion Construction Limited v Devonport Royal Dockyard Limited [2006] BLR 15 Limits on court intervention in adjudication decisions; respect for jurisdiction and natural justice. Supported the principle that adjudicator decisions are binding unless jurisdictional or fairness issues arise.
Gillies Ramsay Diamond v PJW Enterprises Limited 2004 SC 430 Assumption that adjudicators consider all relevant submissions unless decision suggests otherwise; sufficiency of reasons. Used to evaluate whether adjudicator considered arguments and provided intelligible reasons.
Construction Centre Group Limited v Highland Council 2002 SLT 1274 Standards for adjudication decision enforcement. Reinforced the strict approach to natural justice and jurisdictional limits in adjudication.
Connaught Partnerships Limited (in administration) v Perth & Kinross Council 2014 SLT 608 Limits on court's interference with adjudicator decisions. Affirmed that courts should not lightly overturn adjudicator decisions.
Barhale Limited v SP Transmission plc 2021 SLT 52 Adjudicator's jurisdiction and natural justice principles. Supported the principles applied to adjudicator's conduct and decision-making.
Amec Group Limited v Thames Water Utilities Limited [2010] EWHC 419 (TCC) Adjudicator’s procedural powers and fairness. Referenced in support of adjudicator’s procedural discretion.
Pilon Limited v Breyer Group plc [2010] BLR 452 Adjudication procedure and jurisdiction. Used to illustrate limits on adjudicator jurisdiction.
NKT Cables A/S v SP Power Systems Limited 2017 SLT 494 Natural justice and jurisdiction in adjudication. Applied to assess adjudicator’s compliance with procedural fairness.
Costain Limited v Strathclyde Builders Limited 2004 SLT 102 Enforcement of adjudicator decisions. Supported the general principles of adjudicator decision enforcement.
Carillion Utility Services Limited v SP Power Systems Limited 2012 SLT 119 Adjudication jurisdiction and procedural fairness. Referenced in assessing adjudicator’s jurisdictional scope.
Highland and Island Airports Limited v Shetland Islands Council [2012] CSOH 12 Adjudicator’s jurisdiction and natural justice. Used to support procedural fairness standards.
Ardmore Construction Limited v Taylor Woodrow Construction Limited [2006] CSOH 3 Adjudicator jurisdiction and natural justice. Referenced on adjudicator’s procedural limits.
Barrs v British Wool Marketing Board 1957 SC 72 General principles of natural justice. Applied to adjudicator’s duty of fairness.
McAlpine PPS Pipeline Systems JV v Transco plc [2004] EWHC 2030 (TCC) Limits on adjudicator jurisdiction and natural justice. Supported principles limiting adjudicator’s power.
Cantillon Limited v Urvasco Limited [2008] BLR 250 Adjudicator jurisdiction and procedural fairness. Referenced in adjudication procedural context.
Van Oord UK Limited v Dragados UK Limited [2022] CSOH 30 Adjudicator jurisdiction and natural justice. Applied to adjudicator’s procedural conduct.
Tierney v G F Bisset (Inverbervie) Limited 2022 SLT (Sh Ct) 113 Specification requirements for payment notices under the 1996 Act. Used to assess adequacy of Final Account Statement’s detail.
Grove Developments Limited v S&T (UK) Limited [2018] Bus LR 954 Test for adequacy of payment notices as an agenda for dispute. Supported finding that Final Account Statement provided adequate agenda.
D McLaughlin & Sons Limited v East Ayrshire Council [2022] CSIH 42, 2022 SLT 1245 Binding status of final account certificates and effect of timeous challenges. Applied to interpret binding effect of Final Account Statement and adjudications.
Trustees of the Marc Gilbard 2009 Settlement Trust v OD Developments and Projects [2015] EWHC 70 (TCC), [2015] BLR 213 Interpretation of finality clauses in construction contracts. Considered in relation to contract clause on binding final account statements.
Bennett v FMK Construction Limited [2005] EWHC 1268 Effect of adjudicator resignation on subsequent adjudications. Distinguished as not supporting continuation of adjudication after resignation.
Brighton University v Dovehouse Interiors Limited [2014] EWHC 940 Effect of adjudicator resignation and subsequent adjudication proceedings. Distinguished similarly to Bennett.
Hutton Construction Limited v Wilson Properties (London) Ltd [2017] Bus LR 908 Conditions for challenging adjudicator decisions during enforcement. Referenced regarding competency of challenge to adjudicator decision.
Rainy Sky SA v Kookmin Bank [2011] 1 WLR 2900 Principles of commercial contract construction. Applied to interpret subcontract provisions on Final Account Statement content.
Dickie & Moore v Trustees of the Lauren McLeish Discretionary Trust 2021 SC 1 Interpretation of the Scheme for Construction Contracts (Scotland) 1998 to achieve its purpose. Guided the court’s approach to adjudication procedures and enforcement.
Bresco Electrical Services Ltd v Michael J Lonsdale (Electrical) Ltd [2020] UKSC 25 Adjudication as a mainstream dispute resolution mechanism producing de facto final resolution. Considered in relation to policy on raising court proceedings prematurely.
Aspect Contracts (Asbestos) Ltd v Higgins Construction Plc [2015] UKSC 38, [2015] 1 WLR 2961 Improbability of statutory scheme requiring premature court proceedings. Referenced in policy considerations on dispute resolution timing.
Marc Gilbard and McLaughlin & Sons (discussed above) Contractual conclusivity and finality of final account certificates. Analyzed in detail for their applicability to the subcontract clause at issue.

Court's Reasoning and Analysis

The court began by reaffirming the statutory scheme for adjudication under the Housing Grants, Construction and Regeneration Act 1996 and the Scheme for Construction Contracts (Scotland) 1998, which provides for binding interim decisions by adjudicators subject to limited grounds for court intervention.

Regarding the challenge to the adjudicator’s decision, the court held that the adjudicator had decided the question referred to him: the sum due from Company A to Company B under the subcontract. Although the adjudicator referred to the possibility of a "beck and call" contract, the court found no persuasive evidence that he treated this as a new contract or that this reasoning was a "frolic" outside his jurisdiction. The adjudicator’s approach to valuation, while possibly imperfect, was a genuine attempt to address the dispute.

The court found that the adjudicator was entitled to raise the validity of Company A’s Final Account Statement and gave the parties ample opportunity to comment, thus observing the principles of natural justice. The adjudicator’s decision showed he considered and rejected Company A’s arguments, indicating no failure to exhaust jurisdiction.

Turning to the validity of the Final Account Statement, the court construed clause 33.3 of the subcontract strictly, holding that it only required Company A to state the amount it considered due within 28 days of receipt of Company B’s final account. The court rejected the submission that the statement needed to specify the basis of calculation for contractual validity, distinguishing the contractual requirement from statutory requirements under the 1996 Act and the Scheme, which impose minimum content requirements for payment notices. The Final Account Statement met the contractual requirement and, even if subject to statutory content requirements, provided an adequate agenda for dispute.

On the binding nature of the Final Account Statement under clause 33.4, the court rejected Company A’s argument that the clause should be interpreted to limit challenges to the timeous adjudication or court proceedings alone. The court distinguished the subcontract from standard form contracts considered in precedent cases, noting the subcontract’s bespoke nature and the absence of language evidencing an intention to maximize conclusivity. The natural construction was that the Statement is binding on Company B unless challenged by timeous adjudication or litigation, and Company B had timeously commenced such proceedings, preventing the Statement from becoming final and binding.

The court also found that the adjudications by the two adjudicators were separate and that the second adjudication was not a continuation of the first. Consequently, the Final Account Statement remained binding for the purposes of the second adjudication.

Regarding the competency of Company A’s action, the court held that the challenge to the adjudicator’s decision was not ripe for final determination and that the claim for payment under the Final Account Statement was incompetent because it conflicted with the binding adjudicator decision. However, the declarators on validity and binding nature of the Statement were competent and considered.

Holding and Implications

In the action brought by Company B (CA101/22), the court granted decree in favour of Company B, enforcing the adjudicator’s decision and dismissing Company A’s pleas.

In the action brought by Company A (CA98/22), the court declared that the Final Account Statement was validly issued under the subcontract but dismissed Company A’s claims that it was binding on Company B and the adjudicator for the purposes of the adjudication. The court dismissed Company A’s claim for payment of the sum stated in the Final Account Statement as incompetent.

The decision enforces the adjudicator’s interim determination as the measure of the parties’ payment obligations pending final resolution in the substantive action. No new precedent altering the established principles of adjudication enforcement or contractual interpretation was established. The ruling clarifies the application of bespoke contractual clauses on final account statements in the context of statutory adjudication schemes, emphasizing strict contractual construction and the importance of procedural fairness in adjudication.