Sudlows Ltd v Global Switch Estates 1 Ltd
Factual and Procedural Background
The Plaintiff, a contractor, brought a Part 7 claim against the Defendant, the employer, to enforce an adjudicator's decision awarding the Plaintiff a sum of money plus VAT. This was the sixth adjudication between the parties ("Adjudication 6"). The Plaintiff sought summary judgment for enforcement, which the Defendant resisted. The Defendant also initiated Part 8 proceedings seeking a declaration that the adjudicator in Adjudication 6 had breached natural justice by wrongly limiting his jurisdiction, specifically by holding himself bound by findings made by a previous adjudicator in Adjudication 5. The Defendant alternatively sought enforcement of the adjudicator’s alternative findings, which favored the Defendant and required the Plaintiff to pay the Defendant a sum plus VAT, interest, and fees.
The underlying contract was a JCT Design and Build 2011 form for fit-out works at the Defendant’s premises, including installation of chillers and electrical infrastructure. The dispute concerned delays related to Section 2 of the works, involving the creation of a private electricity substation and installation of high-voltage cables through ductwork under a road. The ductwork was completed late by the Defendant’s enabling contractor, causing delays to the Plaintiff’s cable installation. A cable was damaged during installation, allegedly due to defective ductwork and misleading information. Subsequently, the Plaintiff refused to terminate, connect, and energise replacement cables, leading to further delay and dispute.
In Adjudication 5, the Plaintiff sought an extension of time ("EOT") for delays up to 18 January 2021 ("Window 29"). The adjudicator in Adjudication 5 found in favour of the Plaintiff, concluding the Defendant was responsible for defective ductwork causing delay and that the Plaintiff was entitled to an EOT of 482 days in total across various windows including Window 29. The Defendant was not entitled to withhold liquidated damages for that period. The decision was detailed and included findings on culpability and entitlement to EOT.
Following Adjudication 5, the Defendant omitted energisation from the Plaintiff’s scope and certified practical completion on 7 June 2021. The Plaintiff sought a further EOT of 133 days from 19 January 2021 to 7 June 2021 and further payments, which the Defendant refused. This gave rise to Adjudication 6. The Plaintiff relied on the same Relevant Events and the findings of Adjudication 5 to support the further EOT claim. The Defendant accepted the prior EOT award but contended that the adjudicator in Adjudication 6 was not bound by the reasoning underpinning that decision and could consider new evidence, including reports and successful cable testing post-dating Adjudication 5.
The adjudicator in Adjudication 6 considered whether he was bound by the prior decision. He sought parties’ views on considering alternative positions. The Plaintiff accepted the adjudicator might consider an alternative position without conceding jurisdiction. The adjudicator ultimately awarded the Plaintiff the further EOT and related payments but also produced detailed alternative findings favoring the Defendant if he was wrong about being bound by Adjudication 5.
Legal Issues Presented
- Whether the adjudicator in Adjudication 6 was bound by the decision in Adjudication 5 such that he was required to grant the further 133 days EOT and associated prolongation costs ("Prior Decision Issue").
- If the adjudicator was not bound, whether the alternative findings he produced in favour of the Defendant could be enforced ("Alternative Finding Issue").
Arguments of the Parties
Plaintiff's Arguments
- The adjudicator in Adjudication 6 was bound by the findings of Adjudication 5 regarding Relevant Events and thus had to grant the further EOT.
- The Defendant was attempting to re-litigate issues already decided in Adjudication 5, which was impermissible.
- The new evidence relied upon by the Defendant was irrelevant, and the refusal to energise was reasonable given the novel and untested nature of the installation.
- Any alternative findings made by the adjudicator without jurisdiction should not be enforceable.
Defendant's Arguments
- The adjudicator in Adjudication 6 was not bound by the reasoning or findings on Relevant Events in Adjudication 5 and could consider new evidence relating to a different period.
- The new evidence, including testing reports and successful energisation, justified a different decision on the further EOT and prolongation costs.
- The dispute in Adjudication 6 was not the same or substantially the same as in Adjudication 5 because it concerned a different time period and new facts.
- The alternative findings made by the adjudicator should be enforceable if the primary decision was not.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Balfour Beatty v Shepherd Construction Ltd [2009] EWHC 2218 (TCC) | An adjudicator's decision on a dispute is binding and a later adjudicator cannot override or undermine it; a later adjudicator must resign if the dispute is the same or substantially the same. | The court cited this to underline that a later adjudicator cannot decide the same dispute again and must respect prior decisions, framing the jurisdictional issue in the case. |
| Brown v Complete Building Solutions Ltd [2016] EWHC Civ 1 | Summarises principles on when parties are bound by adjudicator decisions and when disputes are the same or substantially the same; the question is one of fact and degree. | The court relied on this to analyze whether the disputes in Adjudications 5 and 6 were the same or substantially the same, concluding they were not. |
| Quietfield Ltd v Vascroft Construction Ltd [2006] EWCA Civ 1737 | Adjudicator must resign if dispute is the same or substantially the same as a previous adjudication; the test is fact and degree. | Used as an example of how different evidence or different claims can mean disputes are not substantially the same, supporting the court’s conclusion here. |
| Global Switch Estates 1 Limited v Sudlows [2020] EWHC 3314 (TCC) | Clarified that a later adjudicator can be bound by an earlier EOT decision but may assess loss and expense claims independently. | Referenced to show that prior decisions on EOT bind later adjudicators on that point but do not preclude fresh evaluation of related claims. |
| Hyder Consulting v Carillion [2011] EWHC 1810 | Distinguishes between adjudicator's decision and reasoning; the decision and essential components thereof are binding, but reasoning alone is not. | The court used this to discuss what constitutes an essential component of an adjudicator’s decision and whether findings on EOT are binding. |
| Carillion Construction Ltd v Devonport Royal Dockyard Ltd [2005] EWCA Civ 1358 | Respect should be accorded to an adjudicator’s view on whether disputes are the same or substantially the same. | Supported the principle that the adjudicator’s perspective on dispute identity is important but not determinative, guiding the court’s independent assessment. |
Court's Reasoning and Analysis
The court examined the nature and scope of the disputes in Adjudications 5 and 6, focusing on whether they were the same or substantially the same. It considered the statutory scheme, relevant Scheme provisions, and authoritative case law, including the principles that an adjudicator’s decision is binding until finally determined by court or arbitration and that a later adjudicator must resign if the dispute is the same or substantially the same as a previous adjudication.
The court noted that Adjudication 5 concerned an EOT claim for delays up to 18 January 2021, while Adjudication 6 concerned a further EOT claim for a subsequent period with new evidence, including successful cable testing and expert reports not available at the time of Adjudication 5. The court found that the disputes were not the same or substantially the same due to the different time periods, new evidence, and the broader context of Adjudication 6, which included a final payment claim and wider valuation issues.
The court criticized the adjudicator in Adjudication 6 for taking a wrong view that he was bound by Adjudication 5’s findings on Relevant Events, noting that he failed to apply the proper test of whether the disputes were the same or substantially the same and gave insufficient weight to the new evidence. This misapprehension resulted in a breach of natural justice.
However, the court accepted that the adjudicator had jurisdiction to make alternative findings on the merits if he was not bound by Adjudication 5, and that those alternative findings were detailed and comprehensive. The court rejected arguments that the alternative findings were not enforceable due to their absence from the formal decision section or because they were obiter. It held that the alternative findings were intended to be binding if the primary findings fell away and that enforcement of those findings was appropriate.
Holding and Implications
The court held that the primary adjudication decision in favour of the Plaintiff (Sudlows) could not be enforced due to the adjudicator’s breach of natural justice in wrongly limiting his jurisdiction by being bound by the prior decision.
However, the alternative findings made by the adjudicator, which favored the Defendant (Global Switch Estates 1 Ltd) and awarded a sum payable to the Defendant, are enforceable.
The direct effect is that the Plaintiff’s claim to enforce the primary adjudication award is dismissed, but the Defendant’s claim to enforce the alternative award is upheld. No broader precedent is established beyond the application of established principles concerning adjudicator jurisdiction, natural justice, and enforcement of alternative findings in adjudications.