Bilton & Johnson (Building) Co Ltd v Three Rivers Property Investments Lt

England and Wales High Court (Technology & Construction Court)
Jan 14, 2022
Smart Summary (Beta)

Factual and Procedural Background

The Claimant applied for summary judgment to enforce an adjudicator's decision dated 2 September 2021, which awarded the Claimant an extension of time to 14 November 2019 for works contracted with the Defendant and ordered the Defendant to pay the Claimant £228,273.48 previously deducted as liquidated damages, plus interest and adjudicator's costs. The works involved refurbishment of an industrial estate owned by the Defendant.

The contract formation involved an initial agreement ("the Original Contract") on 15 August 2018, followed by a formal JCT Design and Build Contract 2016 ("the Signed Contract") signed by the Claimant on 9 January 2019, which superseded the Original Contract. The Original Contract contemplated completion dates and liquidated damages per section, while the Signed Contract specified a single completion date and a weekly liquidated damages rate applicable overall.

The Defendant withheld £234,641.56 as liquidated damages based on the Original Contract's per-section rate, which the adjudicator found incorrect. The adjudicator concluded the Defendant was entitled to liquidated damages of £6,368.08 based on the Signed Contract and extensions of time granted due to delays not attributable to the Claimant. The Defendant failed to pay the sums awarded except half the adjudicator's fees, prompting the Claimant to seek enforcement via summary judgment.

The Defendant resisted enforcement on two grounds: alleged breach of natural justice by the adjudicator in determining contractual terms not argued by parties, and failure to properly consider the Defendant's rectification defence concerning liquidated damages.

Legal Issues Presented

  1. Whether the adjudicator breached natural justice by deciding the applicable contractual terms on a basis not advanced by the parties and without giving them an opportunity to respond.
  2. Whether the adjudicator failed to properly consider the Defendant's rectification defence, thereby restricting his jurisdiction and breaching natural justice.

Arguments of the Parties

Defendant's Arguments

  • The adjudicator's findings on the applicable contractual terms were based on reasoning not presented by either party, denying the Defendant a chance to respond, thus breaching natural justice.
  • The adjudicator took a restrictive view of his jurisdiction by refusing to accept the rectification defence without canvassing this with the parties, constituting a breach of natural justice and failure to exhaust jurisdiction.

Claimant's Arguments

  • The adjudicator correctly identified the Signed Contract as governing the dispute, rejecting the Defendant's position, and this approach did not breach natural justice as the Defendant had full opportunity to argue its case.
  • The adjudicator addressed the rectification defence extensively and rejected it on substantive grounds, not for lack of jurisdiction or failure to consider it, thus no breach of natural justice occurred.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Global Switch Estates 1 Ltd v Sudlows Ltd [2020] EWHC 3314 (TCC) Courts adopt a robust approach to enforcement of adjudicator decisions. Supported the principle that adjudicator decisions are to be enforced unless clear jurisdictional or natural justice breaches exist.
Carillion v Devonport Royal Dockyard [2005] EWHC 778 (TCC) Adjudicator decisions must be enforced even if erroneous unless there is excess of jurisdiction or serious breach of natural justice. Guided the court's sceptical approach to technical defences and emphasized the importance of enforcing adjudicator decisions.
Balfour Beatty Construction Ltd v London Borough of Lambeth [2002] EWHC 597 (TCC) Natural justice requires parties be given a fair opportunity to respond to main points relevant to the dispute and decision. Used to assess whether the adjudicator breached natural justice by adopting an unagreed methodology without informing parties.
Primus Build Ltd v Pompey Centre Ltd [2009] EWHC 1487 (TCC) An adjudicator must notify parties if he intends to decide on a basis not advanced by them. Applied to determine if the adjudicator was obliged to canvass his reasoning on contractual terms with the parties.
Corebuild Ltd v Cleaver [2019] EWHC 2170 (TCC) Failure to consider a defence that had not been argued or evidence adduced may breach natural justice. Considered in relation to whether the adjudicator decided on a factual basis not argued by parties.
Pilon v Breyer Group Ltd [2010] BLR 452 An adjudicator must address the question referred; deliberate failure to consider a defence may render decision unenforceable. Informed the court’s approach to whether the adjudicator properly addressed the rectification defence.

Court's Reasoning and Analysis

The court examined whether the adjudicator breached natural justice by deciding the applicable contractual terms on a basis not explicitly advanced by the parties. The court found that although the adjudicator’s reasoning—that the Original Contract was superseded by the Signed Contract—was not expressly argued by either party, it was derived from the parties’ submissions and did not amount to a new case. The Defendant had ample opportunity to make submissions on the contractual terms and was not unfairly prejudiced.

Regarding the rectification defence, the adjudicator dedicated a substantial section of his decision to the issue and concluded that although it was arguable the contract could be rectified to reflect a higher liquidated damages rate, the Defendant was not entitled to withhold damages at that higher rate prior to rectification. The adjudicator also found the higher rate to be an unenforceable penalty and expressed that he lacked jurisdiction to order rectification absent parties' agreement or legal authority.

The court held that the adjudicator did not fail to address the rectification defence, nor did he act unfairly by failing to alert parties to his reasoning in advance. The Defendant had fair opportunity to present evidence and submissions. The court emphasized that errors of law or fact by an adjudicator do not invalidate enforcement unless there is a clear breach of jurisdiction or natural justice. The Defendant’s arguments did not disclose a real prospect of successfully defending the claim.

Holding and Implications

The court granted summary judgment in favor of the Claimant, enforcing the adjudicator's decision.

Holding: The Defendant’s grounds of defence were ill-founded and did not disclose any real prospect of success; summary judgment was granted for enforcement of the adjudicator’s decision.

Implications: The decision confirms the robust approach courts take to enforcement of adjudicator decisions under the Housing Grants, Construction and Regeneration Act 1996, emphasizing that technical or procedural errors by adjudicators rarely suffice to avoid enforcement absent clear jurisdictional or natural justice breaches. The Defendant must pay the sums awarded by the adjudicator. No new precedent was established beyond the application of existing principles.