Bravejoin Company Ltd v Prosperity Moseley Street Ltd
Factual and Procedural Background
The Plaintiff is a company engaged in steelwork, cladding, and related fabrication. The Defendant is a single purpose vehicle involved in the development of a site in The City. Initially, the Plaintiff was subcontracted by Company A to perform works on the site. After Company A entered administration, the Plaintiff alleges it was engaged directly by the Defendant. In November 2020, the Plaintiff sent a series of invoices to the Defendant under circumstances involving email correspondence with an individual acting on behalf of the Defendant and related companies within a group referred to as the Prosperity Group.
The Defendant responded via emails acknowledging the invoices and indicating payment would be made by December 11, 2020, attaching a payment notice valuing part of the works. However, no payment was made. Subsequently, pay less notices were issued by the Defendant disputing certain invoices on the basis that the works claimed were unsubstantiated. The Defendant’s solicitors later disputed the contractual relationship and scope of services, asserting no direct contract existed between the Plaintiff and Defendant after Company A’s administration.
The Plaintiff referred the dispute to adjudication in July 2021. The adjudicator found that a dispute had crystallised due to non-payment of invoices and determined that the Defendant was obliged to pay a sum to the Plaintiff. The Plaintiff then brought proceedings to enforce the adjudicator’s decision. The Defendant challenged the enforcement on jurisdictional grounds and on the basis of the alleged failure of the Plaintiff’s design work.
Legal Issues Presented
- Whether a dispute had crystallised between the Plaintiff and Defendant prior to the commencement of adjudication, thereby conferring jurisdiction on the adjudicator.
- Whether the adjudicator’s decision that the Defendant was liable to pay the Plaintiff was enforceable.
- Whether the Defendant had a valid defence to enforcement, including challenges based on the alleged failure of the Plaintiff’s design work and contractual relationships.
Arguments of the Parties
Defendant's Arguments
- The Defendant argued there was no dispute with the Plaintiff as the Plaintiff had intimated claims against another company within the group, Prosperity Wealth.
- The Defendant contended there was no direct contract with it, and therefore no dispute had crystallised before adjudication.
- In oral submissions, the Defendant raised concerns about the Plaintiff’s design being defective and questioned why payment should be made for a failed design.
Plaintiff's Arguments
- The Plaintiff maintained that the invoices were rendered to the Defendant and that the Defendant acknowledged them through emails and payment notices.
- The Plaintiff asserted that the Defendant’s letter denying liability nonetheless evidenced the existence of a dispute.
- The Plaintiff argued that the Defendant’s challenge to the adjudicator’s jurisdiction was unfounded and that the adjudicator’s decision was enforceable.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Ringway Infrastructure Services Ltd v Vauxhall Motors Ltd [2007] EWHC 2421 (TCC) | Definition and crystallisation of a dispute; existence of a dispute can be inferred from conduct and surrounding circumstances without express rejection. | The court applied this authority to confirm that the non-payment and correspondence evidenced a crystallised dispute before adjudication. |
| CSK Electrical Contractors Ltd v Kingwood Electrical Services Ltd [2015] EWHC 667 (TCC) | Crystallisation of dispute may occur upon service of a claim followed by inactivity by the responding party for a short period. | Supported the conclusion that the dispute had crystallised due to non-payment after invoices were submitted. |
| AMEC Civil Engineering Ltd v Secretary of State for Transport [2004] EWHC 2339 (TCC) | General principles on when a dispute crystallises and how claims give rise to disputes. | Used to underpin the reasoning on the timing and nature of dispute crystallisation. |
| City Basements Ltd v Nordic Construction UK Ltd [2014] EWHC 4817 (TCC) | Objective assessment of whether a dispute exists, particularly in payment disputes; silence or non-payment can infer dispute. | Applied to determine that non-payment by the Defendant after the due date indicated a dispute. |
| Collins (Contractors) Ltd v Baltic Quay Management [1994] Ltd [2004] EWCA Civ 1757 | Meaning of 'dispute' in contractual and adjudication contexts; dispute may be inferred from conduct. | Referenced to support the ordinary meaning of dispute and its inference from facts. |
| VGC Construction Ltd v Jackson Civil Engineering Ltd [2008] EWHC 2082 (TCC) | Principles on withdrawal or abandonment of disputed claims and their effect on adjudication jurisdiction. | Considered in rejecting the Defendant’s contention that the Plaintiff had abandoned claims by querying the contracting party. |
Court's Reasoning and Analysis
The court analysed the facts and correspondence between the parties, focusing on whether a dispute had crystallised before adjudication. It found that the Plaintiff’s invoices, referencing the Defendant and including order numbers, were acknowledged by the Defendant’s representative through emails and payment notices. The Defendant’s issuance of pay less notices and a letter denying liability amounted to an indication of dispute rather than absence of one.
The court addressed the Defendant’s argument that the Plaintiff’s claim had been abandoned or that the dispute was with another group company. It concluded that raising the question of the appropriate contracting party was a common procedural issue and did not amount to withdrawal or abandonment of the claim, particularly as the Defendant did not act to its detriment on that basis.
Legal authorities were cited to clarify the concept of dispute crystallisation, emphasizing that a dispute can be objectively inferred from conduct such as non-payment and correspondence, rather than requiring explicit rejection of claims. The court found that the adjudicator had jurisdiction and that his decision was properly enforceable.
The Defendant’s substantive complaints about the quality of the Plaintiff’s design were deemed irrelevant to the enforcement of the adjudicator’s award, as such issues are not defences to enforcement.
Consequently, the court granted summary judgment for the Plaintiff for the sum awarded by the adjudicator, plus interest and costs.
Holding and Implications
The court’s final ruling was to grant summary judgment in favour of the Plaintiff for the amount of £39,038.66, plus interest and costs.
The court awarded interest pursuant to the Late Payment of Commercial Debts (Interest) Act 1998 at the rate applied by the adjudicator. The Plaintiff was also awarded its costs on the indemnity basis, reflecting the importance of adjudication enforcement and the court’s view that the Defendant’s defence was misconceived.
This decision directly enforces the adjudicator’s award, confirming that the Defendant is liable to pay the sum adjudicated. No broader legal precedent was established beyond the application of established principles relating to dispute crystallisation and enforcement of adjudication decisions.