APPEAL BY (1) EE LTD and (2) HUTCHISON 3G UK LTD AGAINST JOHN STEWART DUNCAN
Factual and Procedural Background
In 2003, the Owner entered into an agreement with Company A, later assigned to Company A and Company B (the Operators), granting rights to operate telecommunications apparatus at a site in The City. The agreed lease term expired in 2012 but continued yearly by tacit relocation under Scots law. In 2018, the Operators sought a new lease reflecting provisions of the new Electronic Communications Code, including updated assignation rights, facility sharing, upgrading rights, and a "no network scheme" valuation basis, which the Owner resisted, preferring continuation under the old code. The Operators served notices proposing termination of the old agreement and replacement with the new draft lease. The Owners opposed, leading to an application to the Lands Tribunal for Scotland, which refused the Operators’ application for lack of a relevant case. The Operators appealed against this decision.
Legal Issues Presented
- What is the proper approach to paragraph 33(14) of the Electronic Communications Code regarding changes to subsisting agreements?
- Whether the Operators must demonstrate specific necessity or a high threshold of "business and technical needs" to obtain an order replacing the old agreement with one compliant with the new code?
- Whether the notice served under paragraph 33(3) specifying the date for termination complies with the code’s requirements?
- Whether a lease continued by tacit relocation remains an agreement in writing subject to the code and tribunal jurisdiction?
Arguments of the Parties
Operators' Arguments
- The new code is designed to facilitate rollout and investment in new electronic communications infrastructure and should be interpreted broadly in line with its purpose and relevant EU directives.
- The tribunal erred in imposing a high bar requiring specific necessity to justify changes; "business and technical needs" should be understood as reasonable requirements for modernisation and updating.
- The Operators are entitled to minimum rights under the new code, including sharing, upgrading, and no scheme valuation, even for subsisting agreements.
- The tribunal wrongly treated the application as a strict adversarial pleading matter rather than a discretionary application under the code.
- The tribunal erred in limiting its discretion to either accept or reject the Operators’ proposed order without considering modifications.
Owner's Arguments
- The tribunal correctly applied the law and required specific justification beyond mere business convenience or profit to replace an existing contract running by tacit relocation.
- Part 3 of the new code does not apply to subsisting agreements, and the tribunal’s discretion under paragraph 34 requires particular regard to the Operators' business and technical needs, which were not sufficiently demonstrated.
- The notice under paragraph 33(3) was invalid because it did not specify a termination date that was an anniversary of the original lease term (the ish).
- After expiry of the agreed term and continuation by tacit relocation, the agreement ceased to be in writing as required by the code, removing tribunal jurisdiction.
- The code should be interpreted to minimize interference with property rights.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Cornerstone Telecommunications Infrastructure Ltd v University of London [2020] 1 WLR 2124 | Broad interpretation of the new code consistent with its purpose and EU Directives. | Supported Operators' submission on the intended facilitation of new technology rollout. |
| CTIL v University of Arts London [2020] UKUT 248 (LC) | Landowners' public duty to participate in facilitating electronic communications infrastructure. | Referenced to support Operators’ arguments on public interest and minimum rights. |
| On Tower UK Ltd v JH & FW Green Ltd [2020] UKUT 348 (LC) | Rejection of restrictive approach to sharing rights under the code. | Used to criticize the restrictive approach of the Scottish tribunal. |
| Allen v Thorn Electrical Industries Ltd [1968] 1 QB 487 | Caution against liberal statutory interpretation interfering with freely-negotiated contracts. | Supported Owner’s submission on statutory interpretation respecting contracts. |
| CTIL v Compton Beauchamp Estates Ltd [2019] UKUT 107 (LC) | Similar caution on statutory interference with contracts. | Reinforced Owner’s argument on judicial restraint. |
| CTIL v Ashloch Ltd [2021] EWCA Civ 90 | Interpretation of paragraph 33(3) regarding timing of changes to code agreements. | Supported Court’s purposive interpretation of notice requirements. |
| Arqiva Services Ltd v AP Wireless II (UK) Ltd [2020] UKUT 195 (LC) | Whether tacit relocation creates a new tenancy or prolongs original written agreement for code application. | Supported tribunal’s view that tacit relocation extends the original written agreement under Scots law. |
Court's Reasoning and Analysis
The court analysed the transitional provisions of the Electronic Communications Code, focusing on paragraph 33(14) and paragraph 34 of the code as applied to subsisting agreements continued by tacit relocation. It agreed with the tribunal that once the original lease term expired, the agreement became a "subsisting agreement" under the old code, subject to the new code’s part 5 with modifications.
The court disagreed with the tribunal’s imposition of a "high bar" requiring the Operators to demonstrate that the existing agreement was unduly onerous or thwarted specific projects to justify replacement. Instead, it held that "business and technical needs" should be understood broadly to include the statutory minimum rights conferred by the new code, such as sharing, upgrading, and no scheme valuation rights, which Parliament intended to become available to operators over time.
The court emphasized that the tribunal’s restrictive approach would prolong the old code’s application beyond its intended obsolescence, contrary to legislative purpose. The court rejected the tribunal’s description of the application as "judicial cancellation" of a contract, clarifying that the process replaces an expired agreement with one in line with the new code, consistent with the statutory scheme and transitional provisions.
Regarding the notice under paragraph 33(3), the court acknowledged difficulties in the wording but accepted a purposive interpretation allowing a specified date that need not be the exact anniversary of the original lease term, provided the six months’ notice requirement and timing relative to the termination rights are satisfied.
On the question of jurisdiction and whether tacit relocation results in an agreement in writing, the court agreed with the tribunal that tacit relocation prolongs the original written lease under Scots law, thereby preserving the tribunal’s jurisdiction under the code.
Finally, the court held that the tribunal should exercise its broad discretion under paragraph 34 to make appropriate orders, including modifications to proposed terms, rather than a strict accept/reject approach.
Holding and Implications
The court ALLOWED the Operators' appeal, REFUSED the Owner's cross appeal, QUASHED the tribunal's decision dismissing the application as irrelevant, and REMITTED the matter to the tribunal for further procedure consistent with the guidance in the opinion.
The decision clarifies that for subsisting agreements under the old code continued by tacit relocation, operators are entitled to seek replacement agreements reflecting the statutory minimum rights of the new code without needing to demonstrate a high threshold of specific necessity. The court endorses a purposive and broad interpretation of "business and technical needs" to facilitate modernization and the legislative aim of bringing old agreements into line with the new regime. No new precedent beyond the direct effect on the parties and the tribunal’s approach was established.