BARHALE LTD AGAINST SP TRANSMISSION PLC
Factual and Procedural Background
In February 2018, Company A and Company B entered into a contract for civil works at an electricity sub-station in The City. The contract incorporated the NEC3 Engineering and Construction Contract, Main Option B, Third edition, April 2013, and specified the use of the Civil Engineering Standard Method of Measurement, 3rd edition ("CESMM3") for measurement. Company A carried out bulk excavation and filling works to construct foundations on made ground, exceeding the net volume of foundations themselves. A dispute arose concerning payment for the bulk excavation and filling work, with Company A seeking payment based on actual bulk volumes and Company B contending payment should be limited to net excavation volumes directly related to foundations, as per CESMM3 rules.
Company A referred the dispute to adjudication in June 2020. The adjudicator was tasked primarily with determining whether the Works Information required the bulk excavation and filling work undertaken by Company A. The adjudicator decided in favor of Company A, awarding additional payment for the bulk works. Company B challenged enforcement of the adjudicator's decision on grounds that the adjudicator failed to exhaust his jurisdiction by not addressing the contractual measurement arguments based on CESMM3 rules M6 and M16.
Legal Issues Presented
- Whether the adjudicator failed to exhaust his jurisdiction by not addressing the defender's argument concerning the application of CESMM3 measurement rules M6 and M16.
- Whether the adjudicator failed to provide adequate reasons for his decision.
- Whether the adjudicator's decision should be enforced despite any alleged failures.
Arguments of the Parties
Defender's Arguments
- The adjudicator failed to consider the defender's contractual argument regarding the correct method of measurement and payment under CESMM3 rules M6 and M16, which was a significant point of dispute.
- The adjudicator restricted his jurisdiction to the question of whether the Works Information required bulk excavation, thereby ignoring the separate contractual measurement issue.
- The adjudicator's failure to address these points was either a failure to exhaust jurisdiction or a failure to provide adequate reasons, rendering the decision unenforceable.
- English case law suggests deliberate failure to address an issue can render an adjudicator’s decision unenforceable; the defender argued this failure was deliberate.
Pursuer's Arguments
- The adjudicator addressed the defender's CESMM3 argument implicitly by linking the scope of instruction to entitlement to payment.
- The adjudicator’s decision was understandable and consistent with the nature of adjudication, which does not require exhaustive reasoning on every point.
- The presumption of regularity supports the conclusion that the adjudicator considered and rejected the defender’s arguments.
- Any failure to address the CESMM3 argument was inadvertent and does not render the decision unenforceable.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Macob Civil Engineering Ltd v Morrison Construction Ltd [1999] BLR 93 | Enforcement of adjudicator’s decisions as provisional and interim dispute resolution mechanism under the 1996 Act. | Confirmed that adjudicator’s decisions should be enforced unless unfair or outside jurisdiction. |
| Carillion Construction Ltd v Devonport Dockyard Ltd [2006] BLR 15 | Courts should respect adjudicator’s decisions and only rarely refuse enforcement. | Supported the principle that errors of law or fact by adjudicator do not prevent enforcement. |
| Bouygues UK Ltd v Dahl-Jensen UK Ltd [2000] BLR 522 | Adjudicator’s errors, including patent arithmetical errors, do not render decisions unenforceable. | Distinguished between errors in decision and failure to address jurisdictional issues. |
| Amec Group Ltd v Thames Water Utilities Ltd [2010] EWHC 419 (TCC) | Clarified distinction between not answering the right question and answering it wrongly. | Applied to confirm that adjudicator’s decision is enforceable if the right question was addressed. |
| Construction Centre Group Ltd v Highland Council 2002 SLT 174 | Adjudicator must deal with issues raised in defence if properly pleaded. | Emphasized adjudicator’s duty to address defence arguments within scope of referral. |
| Pilon Ltd v Breyer Group plc [2010] BLR 452 | Deliberate failure to address an issue may render decision unenforceable; inadvertent failure generally does not. | Discussed requirements for adjudicator’s engagement with all issues referred. |
| RGB P&C Limited v Victory House General Partner Limited [2019] EWHC 1188 (TCC) | Inadvertent failure to consider an issue rarely leads to unenforceability. | Supported the principle that failure to address an issue is usually an error within jurisdiction. |
| KNN Coburn LLP v GD Holdings Ltd 2013 EWHC 2879 (TCC) | Test for unenforceability based on inadvertent failure to consider an issue. | Held failure must mean adjudicator did not effectively address major issues to render decision unenforceable. |
| Ballast plc v The Burrell Company (Construction Management) Ltd 2001 SCLR 837 | Failure to exhaust jurisdiction may render adjudicator’s decision unenforceable. | Referenced in analysis of jurisdictional failure. |
| Dickie & Moore Limited v Trustees of the Lauren McLeish Discretionary Trust [2020] CSIH 38 | Severability of adjudicator’s decision where part is unenforceable. | Referenced in relation to potential severability of parts of the adjudicator’s decision. |
Court's Reasoning and Analysis
The court identified four issues before the adjudicator: (i) whether the Works Information required bulk excavation and filling; (ii) how the work was to be measured under CESMM3; (iii) the quantities to be valued and paid; and (iv) the defender’s counterclaim. The adjudicator addressed all issues except the critical second issue concerning CESMM3 measurement rules M6 and M16.
The court found that the adjudicator failed to engage with the defender’s contractual measurement argument despite it being a fundamental point raised repeatedly in submissions and correspondence. The adjudicator appeared to limit his jurisdiction to deciding whether bulk excavation was instructed, effectively ignoring the separate but crucial question of how the works should be measured and paid for under the contract.
The court rejected the pursuer’s argument that the adjudicator implicitly considered and rejected the CESMM3 argument, noting the adjudicator’s own correspondence confirmed his focus was solely on the instruction issue. The presumption of regularity was not applicable given the clear absence of engagement with the measurement argument.
The court further held that it was unnecessary to determine whether the failure was deliberate or inadvertent, but if required, the failure could be characterized as deliberate given the adjudicator’s repeated focus and responses in correspondence. Consequently, the adjudicator failed to exhaust his jurisdiction, rendering the decision unenforceable.
The court also declined to consider the defender’s alternative argument concerning inadequacy of reasons, as failure to exhaust jurisdiction was dispositive.
Holding and Implications
The court SET ASIDE the adjudicator's decision ope exceptionis, sustaining the defender's plea and granting decree of absolvitor. Questions of expenses were reserved.
The direct effect of this decision is that the adjudicator’s award for additional payment to Company A for bulk excavation and filling work is not enforceable. No new precedent was established beyond application of existing principles concerning adjudicator jurisdiction and enforcement. The case underscores the necessity for adjudicators to address all critical issues raised within the scope of the dispute referred to them to ensure enforceability of their decisions.