DICKIE & MOORE LTD AGAINST RONALD JAMES McLEISH AND OTHERS
Factual and Procedural Background
The Plaintiff and Defendant entered into a building contract in 2016 for the construction of a large house near The City. The contract incorporated standard adjudication provisions under the Scheme for Construction Contracts (Scotland) Regulations 1998 (as amended). The Plaintiff was the contractor and the Defendant the employer. Following completion of the house in 2017-2018, a final adjustment statement was issued by the Defendant, which included various deductions for work not done or not in accordance with the contract.
The Plaintiff challenged the final adjustment statement and certificate on multiple grounds, including deductions for remedial work not contractually required and defective work that had been remedied by the employer. The Plaintiff then served a notice of intention to refer disputes to adjudication, covering claims for extensions of time, loss and expense, adjustments to the final account, and withheld sums.
An adjudicator was appointed, who rejected the Defendants' jurisdictional challenge and issued a decision awarding the Plaintiff sums for payment, interest, extensions of time, loss and expense, and adjustments to the works final account. The Plaintiff then raised proceedings to enforce the adjudicator's award. The commercial judge considered four issues: adjudicator jurisdiction over the trust, exhaustion of jurisdiction, breach of natural justice, and whether the dispute had crystallized before referral.
The commercial judge found that part of the dispute (notably extension of time and loss and expense claims) had not crystallized before adjudication and thus the adjudicator lacked jurisdiction over those parts. However, he held that the enforceable parts of the decision could be severed from the unenforceable parts and enforced. The Defendants appealed this severance decision.
Legal Issues Presented
- Whether the adjudicator had jurisdiction to determine the claims advanced against the Defendant trust.
- Whether the adjudicator failed to exhaust his jurisdiction.
- Whether there was a material breach of natural justice in the adjudication process.
- Whether the dispute described in the notice of adjudication had crystallized before the notice was served.
- Whether the parts of the adjudicator's decision over which he lacked jurisdiction could be severed from those over which he had jurisdiction for enforcement purposes.
Arguments of the Parties
Defenders' Arguments
- The adjudicator lacked jurisdiction because the single dispute referred had not crystallized, rendering the entire adjudication null and void.
- The commercial judge erred by allowing severance of parts of the adjudicator's decision in a single dispute adjudication, contrary to established authority.
- The parties contracted to be bound only by the adjudicator's decision as issued, not as rewritten by the court.
- The commercial judge improperly adopted a policy-driven approach inconsistent with the contractual position and established law.
- The final works account could not be severed from the non-crystallized issues, including extension of time and liquidated damages claims.
Pursuer's Arguments
- The adjudicator had jurisdiction over the parts of the dispute that had crystallized and those parts of the decision should be enforced.
- The commercial judge correctly applied a practical and flexible approach to severance, consistent with the policy underlying the adjudication scheme.
- The Defenders' challenge to severance was misplaced and would undermine the fundamental purpose of prompt enforcement of adjudicator awards.
- The discrepancy in valuation figures did not establish non-crystallization for the works final account claims.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Cantillon Ltd v Urvasco Ltd [2008] BLR 250 | Severance of adjudicator decisions in single and multiple disputes; identification of disputes referred. | The court recognized the principles but rejected a rigid application, favoring a practical approach to severance. |
| Bovis Lend Lease Ltd v Trustees of the London Clinic [2009] EWHC 64 (TCC) | Severance of adjudicator decisions where multiple disputes are involved. | The court followed this approach to enforce parts of the decision unaffected by jurisdictional issues. |
| Cleveland Bridge UK Ltd v Whessoe-Volker Stevin Joint Venture [2010] BLR 415 | Rejection of severance in single dispute adjudications where part of the decision lacks jurisdiction. | The court disagreed with this approach, favoring severance consistent with the policy of the 1996 Act. |
| Homer Burgess Ltd v Chirex (Annan) Ltd 2000 SLT 277 | Enforcement of intra vires parts of an adjudicator decision despite jurisdictional defects in other parts. | Supported severance and enforcement of valid parts of the adjudicator’s decision. |
| Carillion Utility Services Ltd v SP Power Systems Ltd 2012 SLT 119 | Severance of adjudicator decisions where separate disputes are determined. | Confirmed severance is competent though not necessary on the facts; policy supports severance. |
| Willow Corp SARL v MTD Constructors Ltd [2019] EWHC 1591 (TCC) | Test for severance focusing on whether a core nucleus of the decision can be safely enforced. | Adopted by the court as a practical test for severance in partially invalid adjudicator awards. |
| Whyte and Mackay Ltd v Blyth & Blyth Consulting Engineers Ltd 2013 SLT 555 | Impact of breach of natural justice on severance of adjudicator awards. | Held that breach of natural justice likely taints entire decision, making severance impossible. |
| CSC Braehead Leisure Ltd v Laing O'Rourke Scotland Ltd 2009 SLT 454 | Substance over form in determining whether single or multiple disputes exist for severance. | Supported practical approach analyzing substance of dispute for severance decisions. |
| Working Environments Ltd v Greencoat Construction Ltd [2012] EWHC 1039 (TCC) | Enforcement of parts of adjudicator decisions despite jurisdictional excess in other parts. | Supported severance on practical grounds where reasoning in invalid part did not affect valid part. |
| Beck Interiors Ltd v UK Flooring Corporation Ltd [2012] EWHC 1808 (TCC) | Different types of jurisdictional challenges affect severance considerations. | Severance was possible on a practical basis in this case. |
| Lidl UK GmbH v RG Carter Colchester Ltd [2012] EWHC 3138 (TCC) | Severance of adjudicator decisions with overlapping issues. | Supported severance where reasoning in invalid part did not materially affect valid part. |
| Bell Building Projects Ltd v Arnold Clark Automobiles Ltd [2017] CSOH 55 | Severance not possible in certain adjudicator awards. | Referenced but distinguished in present case for its facts. |
| DC Community Partnerships Ltd v Renfrewshire Council [2017] CSOH 143 | Severance not possible in adjudicator awards involving single dispute. | Referenced but not followed as the present case was distinguishable. |
Court's Reasoning and Analysis
The court began by acknowledging the statutory and contractual framework governing adjudication, emphasizing the purpose of the Housing Grants, Construction and Regeneration Act 1996 and the Scheme for Construction Contracts to provide a swift, interim dispute resolution mechanism that protects cash flow in the construction industry.
The court accepted the commercial judge's approach of adopting a practical, flexible test for severance rather than a rigid rule based on whether a single or multiple disputes were referred. It recognized that adjudication awards may be partially valid and partially invalid, particularly where part of the dispute had not crystallized at the time of referral, thus falling outside the adjudicator's jurisdiction.
The court analyzed the case law extensively, noting divergent judicial opinions but ultimately endorsing the view that the valid parts of an adjudicator's decision should be enforced if they can be severed from the invalid parts without being tainted by the adjudicator's reasoning on those invalid parts.
Applying these principles to the facts, the court agreed with the commercial judge that the extension of time and associated loss and expense claims had not crystallized and so were outside the adjudicator's jurisdiction and unenforceable. However, the remainder of the adjudicator's decision, including the works final account and other claims, formed a "core nucleus" that was untainted and could safely be enforced.
The court rejected the Defenders' argument that the parties had contracted only to be bound by the adjudicator's original decision, holding that the court's power to sever and enforce valid parts is consistent with the contractual and statutory adjudication regime.
The court also found no sufficient evidence to support the Defenders' contention that discrepancies in valuation figures prevented crystallization of the works final account claims.
Holding and Implications
The court REFUSED the Defenders' reclaiming motion, thereby upholding the commercial judge's decision to enforce the severable parts of the adjudicator's award.
This decision confirms that where part of an adjudicator's award is outside jurisdiction due to non-crystallization of dispute, courts may sever and enforce the valid parts of the award. The ruling reinforces the policy underlying the adjudication scheme to enable prompt and effective enforcement of interim decisions, avoiding disproportionate invalidation of awards due to partial jurisdictional defects.
The ruling does not establish new precedent but affirms a practical and flexible approach to severance consistent with existing case law, emphasizing substance over form in adjudication enforcement.