RECLAIMING MOTION BY LC MANAGEMENT SERVICES (SCOTLAND) LTD AND OTHERS AGAINST HIGHLANDS AND ISLANDS ENTERPRISE
Factual and Procedural Background
From the 1970s, a fabrication yard provided services to the oil and gas industry, including offshore rig repairs. Over time, work volume declined, prompting plans to transform the site to stimulate the local economy. In October 2011, Company A, part of a global energy group, purchased part of the site intending to convert it into an energy park. Company A received substantial public funding, primarily from Defendant, totaling between €10.8 million and €14.4 million.
Plaintiff, part of a consortium that submitted a rival bid for the site, contended that the awards to Company A constituted unlawful state aid. Plaintiff argued that Defendant failed to notify the European Commission as required by law because the aid exceeded the notification threshold, which Plaintiff calculated as €11.25 million. Plaintiff also challenged the lawfulness of a £1.64 million tranche of aid under the specific scheme governing the award.
Plaintiff sought a declarator that Defendant breached European Competition law, damages of £25 million, and recovery of the awards. Defendant responded that the correct notification threshold was €15 million, thus no notification was required, and that the £1.64 million award complied with the relevant scheme. Defendant further submitted that Plaintiff’s damages claim lacked sufficient specification.
The court concluded that the notification threshold was indeed €15 million and that the £1.64 million award was lawful. The reclaiming motion was refused, adhering to the interlocutor of the commercial judge dated 25 September 2019, but for slightly different reasons. The court also indicated it would have dismissed the damages claim due to Plaintiff’s failure to specify causation and loss adequately. The Scottish Ministers, initially involved, settled with Plaintiff and did not participate before this court.
Legal Issues Presented
- What is the correct notification threshold for state aid under the General Block Exemption Regulation (GBER) applicable to the awards in question?
- Whether the £1.64 million aid tranche complied with the conditions of the Scottish Property Support Scheme (SPSS) and thus was lawful.
- Whether Defendant breached European Union state aid law by failing to notify the European Commission of the aid awarded.
- Whether Plaintiff's claim for damages is sufficiently specified to proceed.
Arguments of the Parties
Appellant's Arguments
- Plaintiff argued that the notification threshold was €11.25 million, based on an adjusted aid ceiling under the Regional Aid Guidelines, and that the aid exceeded this figure, triggering a notification obligation.
- Plaintiff contended that Defendant breached Articles 107 and 108 TFEU by failing to notify the Commission and by awarding aid without proper market failure justification.
- Plaintiff challenged the lawfulness of the £1.64 million aid tranche, asserting no market failure existed, supported by a rival bid and alternative valuations.
- Plaintiff sought damages of £25 million for alleged losses caused by the unlawful aid awards.
Respondent's Arguments
- Defendant maintained that the notification threshold was €15 million, calculated by applying the standard aid threshold of 20% to €100 million eligible costs and then taking 75% thereof, as per Article 6(2) GBER.
- Defendant argued that the £1.64 million award was lawful under the SPSS, having properly considered market failure with professional advice from reputable firms.
- Defendant rejected Plaintiff’s contention that the presence of a rival bid or alternative valuations negated the market failure finding, noting these facts did not render Defendant’s view unreasonable or irrational.
- Defendant submitted that Plaintiff’s damages claim was inadequately specified, lacking fair notice of causation and loss, and therefore unsuitable for proof.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Francovich v Italy [1993] 2 CMLR 66 | Criteria for state liability for damages arising from breaches of EU law. | Used to establish that damages claims require manifest and grave disregard by the member state and a direct causal link to loss. |
| Brasserie du Pêcheur SA v Germany [1996] QB 404; [1996] 1 CMLR 889 | State liability principles for breaches of EU law and damages claims. | Applied to assess the sufficiency of Plaintiff’s damages pleadings and the requirement for clear causation and loss specification. |
| Pearle BV v Hoofdberijfschap Ambachtan [2004] 3 CMLR 9 | Interpretation of state aid notification requirements and direct rights of action. | Supported the principle that interested parties may enforce notification and standstill obligations in national courts. |
| Administración del Estado v Xunta de Galicia [2006] 2 CMLR 6 | State aid notification and compatibility assessment. | Confirmed that notification requirements must be strictly observed to validate aid awards. |
| Case C-349/17 Eesti Pagar AS v Ettevõtluse Arendamise Sihtasutus ECLI:EU:C:2019:172 | Clarification of notification and standstill provisions, discretion of the Commission, and recovery of unlawful aid. | Clarified that exemptions must be strictly construed and that the Commission may order recovery of unlawful aid up to 10 years retroactively. |
Court's Reasoning and Analysis
The court focused on the interpretation of Article 6(2) of the General Block Exemption Regulation (GBER) to determine the correct notification threshold. The provision requires notification if aid exceeds 75% of the maximum aid an investment with eligible costs of €100 million could receive, applying the standard aid threshold for large enterprises.
The parties agreed the standard aid threshold was 20%, making the maximum aid €20 million. Applying 75% yields a notification threshold of €15 million. Plaintiff argued for a lower threshold (€11.25 million) based on an adjusted ceiling in the Regional Aid Guidelines (RAG), which applied differentiated aid percentages for expenditures above €50 million.
The court rejected Plaintiff’s argument, holding that the notification threshold calculation must rely on the standard aid threshold, not the adjusted ceiling, which pertains to maximum allowable aid but not notification thresholds. The court found Plaintiff’s reading distorted the text and resulted in double application of the 75% factor.
On the lawfulness of the £1.64 million award under the Scottish Property Support Scheme (SPSS), the court accepted Defendant’s reliance on professional advice and held that the finding of market failure was a matter for Defendant’s discretion. The presence of a rival bid or alternative valuations did not render this decision unreasonable or irrational.
The court also addressed Plaintiff’s damages claim, noting that EU law requires clear demonstration of manifest and grave disregard by the member state and a direct causal link between breach and loss. Plaintiff’s pleadings failed to provide adequate notice of causation and loss, rendering the damages claim unsustainable.
The court declined to refer the case to the Court of Justice of the European Union, finding the issues sufficiently clear.
Holding and Implications
The court REFUSED the reclaiming motion, upholding the commercial judge’s interlocutor dated 25 September 2019, on the basis that:
- The correct notification threshold under Article 6(2) GBER was €15 million, not €11.25 million.
- The £1.64 million award complied with the Scottish Property Support Scheme and was lawful.
- Plaintiff failed to specify adequately the causation and loss necessary to sustain the damages claim, which would have been dismissed if necessary.
The decision directly affects the parties by dismissing Plaintiff’s claims but does not establish new legal precedent beyond the application of existing EU state aid law principles and regulatory interpretation.