ENERGIEKONTUR UK LTD FOR JUDICIAL REVIEW
Factual and Procedural Background
The petitioner is a commercial wind farm developer seeking judicial review of the Ministry of Defence's (MOD) policy regarding the safeguarding of the Eskdalemuir Seismic Array ("the Array") and the noise budget allocation table applied by the MOD. The Array detects seismic vibrations related to nuclear tests and is protected under the Comprehensive Nuclear Test Ban Treaty, with the MOD responsible for safeguarding it from interference, including seismic vibrations caused by wind farms.
The MOD established two zones around the Array: an exclusion zone within 10 km, where wind farm developments are objected to, and a consultation zone within 50 km, where the MOD must be consulted. The MOD uses a noise budget allocation table to assess whether proposed wind farms would exceed the noise threshold of 0.335 nanometres ground displacement, based on reports commissioned by the Eskdalemuir Working Group (EWG), which includes wind farm operators and is convened by Scottish Ministers.
The MOD allocates noise budget on a "first come first served" basis but treats developments differently depending on their capacity: developments over 50MW are allocated noise budget at the Environmental Impact Assessment (EIA) scoping request stage, while those at or below 50MW are allocated noise budget upon submission of full planning applications to local authorities. The petitioner challenges this distinction as unreasonable, ultra vires, and unlawful.
The petitioner applied for planning permission for a wind farm under 50MW within the consultation zone. The MOD objected on the basis that the noise budget had been exhausted, primarily due to allocation to a larger development over 50MW at the scoping stage. The petitioner engaged with the MOD and the EWG to seek a policy revision but ultimately filed for judicial review, challenging the timing and fairness of the noise budget allocation policy.
The procedural issue before the court was whether to grant permission for the judicial review application, focusing on whether the petition was time-barred under the three-month limitation period and if an extension was equitable.
Legal Issues Presented
- Whether the MOD's policy of allocating noise budget differently for wind farm developments above and below 50MW capacity is unreasonable, ultra vires, and unlawful.
- Whether the petitioner’s judicial review application was time-barred under section 27A(1)(a) of the Court of Session Act 1988.
- Whether it was equitable to extend the three-month limitation period to allow the petition to proceed.
Arguments of the Parties
Appellant's Arguments
- The court should grant permission to proceed despite the time delay because the MOD’s policy is unlawful and should be challenged to uphold the rule of law and prevent ongoing public wrong.
- The petitioner had pursued alternative remedies, including engagement with the MOD and the EWG, and had sought to resolve the issue without litigation.
- The petitioner has a continuing interest in challenging the policy due to ongoing wind farm projects.
- It was unclear if any other party would raise the issue, so the petitioner’s challenge is necessary.
- No prejudice or hardship to the MOD would result from allowing the petition to proceed.
- Good administration and public interest require judicial determination of the policy’s lawfulness.
- The issue is important both for protecting the Array and supporting renewable energy policies.
- The petitioner’s case has a real prospect of success and the MOD has not provided a coherent explanation for the policy’s differential treatment.
- The petitioner only became aware of the policy details in spring 2018 and successive noise budget tables were not published.
Respondent's Arguments
- Permission to proceed should be refused because no sufficient circumstances justify allowing the application out of time.
- The petitioner delayed unreasonably, waiting about 21 months after becoming aware of the policy before initiating proceedings.
- The petitioner was never denied the opportunity to challenge the policy earlier, nor was there any indication the MOD would amend it.
- Good public administration requires legal certainty, which would be undermined if permission were granted.
- The policy has been in place since 2005 and has been relied upon by developers and authorities.
- There is no industry consensus on the correct approach to noise budget allocation.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| R (Burkett) v Hammersmith and Fulham LBC [2001] Env LR 684 (CA) | Judicial review as a remedy of last resort; balancing interests of good administration and correcting public wrongs. | The court applied this principle to justify extending the time limit, recognizing that the petitioner reasonably sought resolution through the working group before litigation. |
| R v Secretary of State for the Home Department, ex p Ruddock [1987] 1 WLR 1482 | Importance of resolving significant substantive issues through judicial review. | The court considered the importance of the issues related to the protection of the Array and renewable energy policies in deciding to grant permission. |
| R (Gavin) v Haringey LBC [2004] 1 PLR 61 | A claimant cannot be criticised for failing to take action before knowledge of the issue. | The court found the petitioner excusably ignorant of the policy before 2018, justifying extension of the time limit back to that date. |
Court's Reasoning and Analysis
The court exercised discretion under section 27A(1)(b) of the Court of Session Act 1988 to consider whether it was equitable to extend the three-month limitation period for judicial review. The analysis divided the timeline into three periods:
- From policy formulation (circa 2005) until the petitioner’s awareness (April/May 2018): The petitioner was excusably ignorant of the policy details and had no interest in the consultation zone before 2015. The court found it equitable to extend the time limit to the date of awareness.
- From spring 2018 until 26 April 2019: The petitioner sought to resolve the issue through the EWG and discussions with the MOD and Scottish Government, which was a reasonable approach. The court accepted this as justification for further extension.
- From 26 April 2019 until the petition was lodged on 31 December 2019: Little substantive progress occurred, and the petitioner could have commenced proceedings earlier. However, the court did not consider this alone decisive against extension.
The court rejected the strict "strike at the earliest reasonable moment" test for extending time, emphasizing a holistic assessment of all circumstances. It acknowledged the importance of the substantive issue regarding the fairness of the MOD’s noise budget allocation policy and recognized that refusal to grant permission might leave the issue unresolved despite its significance.
The court found no demonstrated prejudice to the MOD from granting permission. The petitioner’s challenge did not threaten the fundamental protection system for the Array or the principle of first come first served, but rather the timing of allocation priority. The court concluded that good administration did not require refusal at this stage and that the statutory threshold of a real prospect of success was met.
Holding and Implications
The court’s final decision was to extend the time limit for judicial review proceedings until 31 December 2019 and to grant permission for the petition to proceed.
This decision allows the petitioner’s challenge to the MOD’s noise budget allocation policy to be heard on its substantive merits. The ruling does not set new precedent on the substantive issues but confirms the court’s willingness to exercise discretion to extend time where equitable, particularly when significant public interest and potential unlawfulness are involved. The MOD’s policy remains subject to judicial scrutiny, but the protection regime for the Array and the principle of first come first served are not disturbed by this procedural ruling.