Wicklow County Council v Lee & anor

High Court of Ireland
Jan 15, 2019
Smart Summary (Beta)

Factual and Procedural Background

The case involves an appeal by the Respondents against an order of the Circuit Court, which enjoined them to cease unauthorised development on their property located in County Wicklow. The Applicant, Company A, had originally granted planning permission for a dwelling on the land in 2002 and 2003. However, in or about 2013, Company A discovered that the Respondents had constructed a large two-storey dormer structure ("the shed/workshop") and a large brick wall ("the screen wall") without planning permission.

The dispute centers on whether Company A was precluded from bringing enforcement proceedings due to the lapse of time under section 160(6) of the Planning and Development Act 2000, which imposes a seven-year limitation period for unauthorised developments without permission, and a twelve-year period for developments with permission (counting from the expiry of the permission).

Following inspections and warning letters issued by Company A, the Respondents applied for retention permission for the unauthorised structures in 2014, which was ultimately refused. Proceedings were initiated by Company A in May 2014 to enforce cessation of the unauthorised development. The Respondents raised the limitation defense in April 2015, claiming the developments commenced more than seven years prior to the proceedings.

The Circuit Court made an order in June 2015 requiring cessation of the unauthorised developments, which the Respondents appealed.

Legal Issues Presented

  1. Whether the Respondents are precluded from enforcement proceedings by lapse of time under section 160(6) of the Planning and Development Act 2000.
  2. When the unauthorised development can be said to have "commenced" for the purposes of applying the statutory limitation period.

Arguments of the Parties

Respondents' Arguments

  • The Respondents contend that the unauthorised developments commenced more than seven years before the initiation of proceedings, relying on evidence such as invoices and affidavits from contractors indicating foundation works in 2004 and 2005.
  • They argue that the limitation period under section 160(6) has expired, barring Company A from pursuing enforcement.

Applicant's Arguments

  • Company A relies on photographic and inspection evidence showing that the shed/workshop was not substantially completed until 2010 or 2011, which is within the seven-year limitation period.
  • Company A argues that sporadic and piecemeal works with long periods of inactivity do not constitute commencement of development under the statute.
  • The onus is on the Respondents to prove when the development commenced, which they have failed to do with sufficient clarity.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Wicklow County Council v. Fortune [2012] IEHC 406 The onus rests on the developer to prove when the unauthorised development commenced for limitation purposes. Used to establish that Respondents bear the burden of proof regarding commencement of development.
Dublin County Council South v. Balfe Ltd [1995] WJSC-HC 4391 When a use has been abandoned and then recommenced after a significant period, limitation runs from recommencement, not the earlier date. The court applied this logic to construction, rejecting that isolated early works constitute commencement if followed by long inactivity.
Kildare County Council v. Goode [1999] 2 IR 495 "Works" refers to a reasonably continuous, temporary, unitary process leading to completion, not sporadic or piecemeal activity. Supported the conclusion that the development must be continuous to constitute commencement under the statute.

Court's Reasoning and Analysis

The Court analyzed the statutory limitation periods under section 160(6) and the evidence concerning the timing of the unauthorised developments. It emphasized that the burden lies with the Respondents to prove when the development commenced. The Court found the Respondents' evidence insufficient to establish that the developments began more than seven years before proceedings.

The Court considered the sporadic nature of the works, noting preliminary foundation work in 2004 and 2005, but significant inactivity followed until the shed/workshop was substantially completed around 2010 or 2011. Applying precedent, the Court held that isolated early works with long gaps do not amount to commencement of development for limitation purposes.

Regarding the screen wall, the Court noted absence of evidence about when the unauthorised height was reached, and that foundation works alone do not establish commencement. The Court declined to consider the longer twelve-year limitation period as the Respondents failed to meet their burden.

Consequently, the Court affirmed the Circuit Court's order requiring cessation of the unauthorised developments.

Holding and Implications

The Court DISMISSED the Respondents' appeal and affirmed the Circuit Court's order enjoining cessation of the unauthorised dormer structure and screen wall.

This decision directly enforces planning control by upholding enforcement action within the statutory limitation period. No new precedent was established beyond confirming existing principles that the burden of proof lies with the developer to show commencement of development for limitation purposes, and that isolated preliminary works followed by significant inactivity do not constitute commencement under section 160.