Willow Corp S.�.R.L. v MTD Contractors Ltd
Factual and Procedural Background
By an adjudication decision dated 19 December 2018, Judge Pepperall ordered that Company A should pay Company B the sum of 1,174,854.92 plus VAT and interest of 36,294.84. No payment was made. Instead, on 28 December 2018, Company A issued a Part 8 claim seeking declarations regarding the proper construction of a supplementary agreement reached in June 2017 and contending that the adjudicator's decision was unenforceable. Company B defended the Part 8 proceedings and, on 7 January 2019, issued separate Part 7 proceedings seeking to enforce the adjudication.
Both matters were before the court. Company A sought judgment on its Part 8 claim, while Company B resisted the claim and sought summary judgment to enforce the adjudication.
The procedural history includes Company A's Part 8 claim issued on 28 December 2018, supported by a witness statement from its solicitor. Company B issued its Part 7 claim on 7 January 2019 with an immediate application for summary judgment, supported by witness statements from its solicitor. The parties agreed directions for the orderly listing of both claims, which allowed Company A to file responsive evidence by 6 February 2019 with no further rounds of evidence anticipated.
On 15 February 2019, Company B filed further late evidence and served additional documents after business hours the evening before the hearing. The court refused permission to rely on this late evidence, giving reasons in this judgment.
Legal Issues Presented
- Whether the June 2017 supplementary agreement was properly constructed such that Practical Completion was achieved by 28 July 2017.
- Whether the adjudicator's decision rejecting Company A's claim for liquidated damages is legally enforceable.
- Whether the adjudicator's decision is unenforceable due to alleged breaches of natural justice.
- Whether severance of the adjudicator's decision is permissible to enforce part of the decision despite errors.
Arguments of the Parties
Appellant's Arguments (Company A)
- The June agreement's purpose was to agree steps necessary to complete the hotel, including a 21-week extension and a modification of the Practical Completion obligation.
- Paragraph 5.0 of the attached schedule allowed Practical Completion to be certified even if excepted works remained outstanding, provided they were listed.
- Argued that the adjudicator’s construction permitted Company B to avoid further work yet insist on certification of Practical Completion, which was improper.
- Asserted that Practical Completion had not been achieved by 28 July 2017.
- Alleged breaches of natural justice, including insufficient time to review the case, improper admission of evidence at reply stage, and unfair findings based on surrejoinder evidence without opportunity to respond.
Respondent's Arguments (Company B)
- Argued that the June agreement imposed an obligation to achieve Practical Completion by 28 July 2017, except for specified works allowed to be completed later.
- Submitted that the adjudicator’s construction was not obviously or demonstrably wrong and should not be overturned.
- Contended that Company A had reasonable opportunity to respond to the case and evidence, including rejoinder and further response stages.
- Maintained that alleged breaches of natural justice were minor and did not justify refusing enforcement.
- Asserted that the loss of profits claim was reasonably assessed by the adjudicator based on assumptions about occupancy rates.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Macob Civil Engineering Ltd v. Morrison Construction Ltd [1999] BLR 93 | Established the "pay now, argue later" principle in adjudication enforcement. | Confirmed that adjudicator's decisions are binding unless clearly wrong or unfair. |
| Mead General Building Ltd v. Dartmoor Properties Ltd [2009] EWHC 200 (TCC) | Reiterated principles of adjudication enforcement and summary judgment. | Supported the court's approach to enforcement absent compelling reasons to refuse. |
| Carillion Construction Ltd v. Devonport Royal Dockyard Ltd [2006] BLR 15 | Enforcement of adjudicator's decision unless unfair or outside jurisdiction. | Emphasized the need for quick interim solutions and limited court interference. |
| Caledonian Modular Ltd v. Mar City Developments Ltd [2015] EWHC 1855 (TCC) | Exception to summary judgment where short, self-contained issues suitable for Part 8 claims. | Supported determination of construction issue via Part 8 proceedings. |
| Hutton Construction Ltd v. Wilson Properties (London) Ltd [2017] EWHC 517 (TCC) | Criteria for resisting summary judgment using Part 8 claims. | Applied criteria to assess whether construction issues should delay enforcement. |
| Denton v. TH White Ltd [2014] EWCA Civ 906 | Guidance on relief from sanctions for late evidence. | Denied permission to rely on late evidence due to seriousness of default and lack of explanation. |
| Arnold v. Britton [2015] UKSC 36 | Principles of contractual interpretation focusing on natural and ordinary meaning. | Applied to interpret the June agreement in its commercial and factual context. |
| Mears Ltd v. Costplan Services (South East) Ltd [2019] EWCA Civ 502 | Clarification of the law on Practical Completion. | Guided the court's understanding of Practical Completion and patent defects. |
| Pilon Ltd v. Breyer Group plc [2010] EWHC 837 (TCC) | Limits on challenges to adjudicator's decisions on natural justice grounds. | Supported enforcement absent plain and obvious breaches. |
| CG Group Ltd v. Breyer Group plc [2013] EWHC 2722 (TCC) | Consideration of natural justice challenges under time constraints. | Emphasized court's deference to adjudicators' constrained circumstances. |
| Beumer Group UK Ltd v. Vinci Construction UK Ltd [2016] EWHC 2283 (TCC) | Summary of natural justice principles in adjudication enforcement. | Reinforced need for plain cases to refuse enforcement on natural justice grounds. |
| Balfour Beatty Construction Ltd v. The Mayor & Burgesses of the London Borough of Lambeth [2002] EWHC 597 (TCC) | Adjudicator’s duty to provide reasonable opportunity to comment despite time pressure. | Considered but court found no breach of natural justice in this case. |
| Cantillon Ltd v. Urvasco Ltd [2008] EWHC 282 (TCC) | Principles on severance of adjudicator's decision. | Guided court's approach to severing unenforceable parts of decision. |
| Greencoat Construction Ltd v. Working Environments Ltd [2012] EWHC 1039 (TCC) | Severance of adjudicator's decision where jurisdictional error limited to part of dispute. | Supported enforcement of valid parts despite errors in others. |
| Lidl UK GmbH v. RG Carter Colchester Ltd [2012] EWHC 3138 (TCC) | Further development of severance principles in single dispute adjudications. | Confirmed severance possible if flawed part clearly separable from remainder. |
Court's Reasoning and Analysis
The court began by addressing the procedural issue of late evidence filed by Company B. Applying the Civil Procedure Rules and the principles from Denton v. TH White Ltd, the court refused permission to admit late evidence due to the seriousness of the default, lack of explanation, and prejudice to Company A. Similarly, late evidence in the summary judgment application was disallowed to prevent ambush and ensure fairness.
Turning to the substantive issues, the court analysed the June 2017 agreement and its schedule, applying established principles of contractual interpretation from Arnold v. Britton. The court found that the natural and ordinary meaning of the agreement required Company B to achieve Practical Completion by 28 July 2017 except for specified works allowed to be completed later.
The court rejected the adjudicator's construction that Practical Completion was achieved merely by agreeing a list of outstanding works, as this would undermine the purposes of the agreement, including the obligation to complete the hotel and the financial settlement.
The court reviewed authoritative case law on Practical Completion, including Mears Ltd v. Costplan Services, confirming that Practical Completion is fact-specific and that outstanding works may be excused only if expressly allowed. It held that the June agreement did not deem Practical Completion achieved by mere agreement on outstanding works without actual completion of required works.
Regarding natural justice challenges, the court applied the stringent standard from Carillion Construction Ltd and subsequent cases, requiring plain and obvious unfairness to refuse enforcement. The court found no significant breach of natural justice, noting that Company A had adequate opportunity to respond and that the adjudicator's procedural decisions were within the rough and tumble of the adjudication process.
Finally, the court considered severance of the adjudicator's decision due to the error in contractual construction. Applying the principles from Cantillon Ltd and subsequent authorities, the court held that the error was limited to the rejection of the liquidated damages claim and did not infect the remainder of the decision. Therefore, severance was appropriate to enforce the balance of the adjudicator's decision.
Holding and Implications
The court ENFORCED the adjudicator's decision in part, specifically ordering Company A to pay Company B the sum awarded, excluding the liquidated damages claim which was dismissed due to error in contractual construction.
The natural justice challenges raised by Company A were rejected as insufficient to refuse enforcement. The court's decision allows for severance of adjudication decisions where errors are confined to discrete parts, supporting the statutory aim of swift interim dispute resolution.
No new precedent was established beyond the application of existing principles to the facts of this case. The decision clarifies the court's approach to late evidence, contractual interpretation of practical completion clauses, natural justice challenges in adjudication, and severance of adjudicator decisions.