Serco Ltd v Secretary of State for Defence

England and Wales High Court (Technology & Construction Court)
Feb 27, 2019
Smart Summary (Beta)

Factual and Procedural Background

This judgment concerns an application by the Defendant, the Secretary of State for Defence ("the MoD"), to strike out, or alternatively for summary judgment upon, certain passages in the Particulars of Claim filed by the Claimant, Company A, in a public procurement dispute. The procurement related to a contract for fire prevention, protection, and response services at the Defendant’s premises in the UK and abroad, including support for UK forces on exercises and operations. The contract, valued at approximately £1.1 billion over 12 years, was awarded to another bidder, Company B, following a four-year procurement process and a nine-month evaluation period. The Claimant was unsuccessful and challenged the award.

The Defendant sought to strike out parts of the claim that relied on the Public Contract Regulations 2015 ("PCR 2015"), arguing these regulations did not apply as the contract notice was published before the PCR 2015 came into force. The Claimant acknowledged this and indicated an intention to apply for amendment but had not yet done so. The Defendant also challenged the sufficiency of the pre-action notice provided by the Claimant under the Defence and Security Public Contract Regulations 2011 ("Defence Regulations"). The court heard submissions on the strike-out application and gave an ex tempore judgment.

Legal Issues Presented

  1. Whether the Claimant’s reliance on the Public Contract Regulations 2015 in the Particulars of Claim was valid given the timing of the procurement process and the applicable regulatory regime.
  2. Whether the pre-action correspondence from the Claimant complied with the notice requirements under Regulation 52(3) of the Defence Regulations, specifically regarding the sufficiency of notice of alleged breaches prior to issuing proceedings.

Arguments of the Parties

Defendant's Arguments

  • The PCR 2015 could not apply because the contract notice was published before these regulations came into force, and the transitional provisions exclude their application to this procurement.
  • The Claimant’s references to PCR 2015 in the Particulars of Claim should be struck out as having no prospect of success.
  • The pre-action correspondence must identify the alleged breaches with sufficient clarity and specificity as required by Regulation 52(3) of the Defence Regulations.
  • Any numbered references to breaches ("RoRs") not specifically identified in the pre-action letters should be struck out for insufficient notice.

Claimant's Arguments

  • The Claimant accepted that PCR 2015 did not apply and indicated a willingness to amend the claim accordingly.
  • The Claimant argued that the pre-action correspondence, including two detailed letters and a 37-page annex, provided sufficient notice of the alleged breaches under the Defence Regulations.
  • The Claimant contended that while not all RoRs were individually identified in the pre-action letters, the overall correspondence gave adequate notice of the claims to comply with the Regulations.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Iiyami UK v Samsung [2018] EWCA Civ 220 Clarification of the test for summary judgment (no real prospect of success) and strike-out (no reasonable grounds). The court applied the test equivalently for both strike-out and summary judgment in this procurement challenge.
Amaryllis Limited v HM Treasury [2009] EWHC 962 (TCC) Requirement for pre-action notice to identify the actual breach complained of with some specificity under procurement regulations. The court adopted the summary of authorities and principles from this case to assess sufficiency of notice under Regulation 52(3).
R v Portsmouth City Council Ex Parte Bonaco Builders Limited Interpretation of notice provisions requiring identification of the breach complained of to enable remedial action. Cited to support the principle that a breach must be identified with specificity in pre-action correspondence.
Keymed Limited v Forest Healthcare NHS Trust [1998] EuLR 71 Pre-action notice sufficient if it clearly states the alleged breach by reference to the relevant Regulations without requiring lengthy particulars. Used as an example where notice was found sufficient despite brevity, guiding the court’s assessment of the Claimant’s letters.
Luck T/a G Luck Arboricultural & Horticulture v LB Tower Hamlets [2003] EWCA Civ 52 Insufficient notice where the alleged breach was stated in very general terms without details or references to the Regulations. Supported the proposition that general references to breaches are inadequate to comply with notice requirements.

Court's Reasoning and Analysis

The court first addressed the applicability of the PCR 2015 to the procurement, concluding from undisputed dates and the transitional provisions that PCR 2015 did not apply because the contract notice was published before the regulations came into force. The Claimant conceded this point and the court struck out the parts of the claim relying on PCR 2015 as having no prospect of success.

Turning to the sufficiency of notice under the Defence Regulations, the court reviewed the relevant legal principles, drawing on a small body of authorities that require pre-action correspondence to identify the alleged breach with sufficient clarity to enable the contracting authority to address the complaint. The court emphasized that a general reference to breaches is inadequate, but detailed particulars are not necessary, citing Keymed as authority for sufficiency of a clear statement by reference to the Regulations.

The court examined the pre-action correspondence, including two detailed letters and a 37-page annex, which provided explanations of the evaluation process and identified specific concerns and numbered references ("RoRs"). Although not all RoRs were individually identified in the letters, the court found that the overall correspondence was sufficient to give the Defendant adequate notice of the alleged breaches. The court also noted that any perceived lack of specificity in the notice stemmed from the Defendant’s own failure to provide full information, which could not be used to bar the claim.

Consequently, the court rejected the Defendant's application to strike out the claim on the ground of insufficient notice, concluding that the Claimant had reasonable grounds for bringing the claim under the Defence Regulations.

Holding and Implications

The court's final decision was to STRIKE OUT the parts of the Claimant’s Particulars of Claim relying on the Public Contract Regulations 2015, as these regulations did not apply to the procurement in question.

However, the court REJECTED the Defendant’s application to strike out the claim for insufficient pre-action notice under the Defence and Security Public Contract Regulations 2011. The court held that the Claimant’s pre-action correspondence was sufficient to identify the alleged breaches and provided reasonable grounds for the claim to proceed.

The direct effect of this decision is that the claim under the Defence Regulations may continue, while any claim under PCR 2015 is dismissed. No new precedent was established; the court applied existing principles regarding regulatory applicability and pre-action notice requirements in public procurement challenges.