Michael J Lonsdale (Electrical) Ltd v Bresco Electrical Services Ltd

England and Wales High Court (Technology & Construction Court)
Jul 31, 2018
Smart Summary (Beta)

Factual and Procedural Background

This case involves a claim brought under CPR Part 8 by Plaintiff, a subcontractor, against Defendant, a company in voluntary liquidation since 12 March 2015. The dispute centers on whether Defendant, being in liquidation, can validly refer a dispute to adjudication concerning claims for sums said to be due under a construction sub-sub-contract dated 21 August 2014. The contract was governed by the Housing Grants Construction and Regeneration Act 1996 and related statutory schemes.

Defendant left the site in December 2014 amid allegations of wrongful termination by both parties. Plaintiff later claimed wrongful termination by Defendant and costs incurred for completion of works by a third party. Defendant counterclaimed alleging Plaintiff wrongfully terminated and owed money. In June 2018, Defendant issued a Notice of Intention to Refer a Dispute to Adjudication, which Plaintiff challenged on the basis that Defendant’s liquidation extinguished the claims relied upon.

Adjudicator was appointed and declined to resign despite Plaintiff’s invitation, issuing a non-binding decision affirming jurisdiction. Plaintiff then initiated these Part 8 proceedings seeking declarations and a permanent injunction to prevent Defendant from pursuing adjudication. The adjudication was stayed by consent pending determination of this claim.

Legal Issues Presented

  1. Whether a company in liquidation can validly refer a dispute to adjudication when that dispute includes any claim for further sums said to be due to the referring party from the responding party.
  2. The effect of the Insolvency (England and Wales) Rules 2016 (and by analogy the 1986 Rules) on the existence and enforceability of claims and cross-claims between parties where one is in liquidation.
  3. The jurisdiction of an adjudicator to determine disputes involving claims that are subject to insolvency set-off under the Insolvency Rules.
  4. Whether the statutory adjudication regime under the Housing Grants Construction and Regeneration Act 1996 overrides or is consistent with insolvency law principles regarding mutual dealings and set-off.

Arguments of the Parties

Appellant's Arguments (Defendant)

  • Liquidators regularly refer disputes to adjudication, either separately or as part of the account under the Insolvency Rules.
  • Adjudication is a contractual right available to parties even in liquidation, and practical or commercial considerations justify its use.
  • The claims and cross-claims do not cease to exist upon liquidation; therefore, adjudication remains available.
  • Refusing adjudication would undermine the statutory right to adjudicate disputes arising under construction contracts.

Appellee's Arguments (Plaintiff)

  • Upon liquidation, claims and cross-claims merge into a single claim for the net balance under the Insolvency Rules, extinguishing separate claims.
  • The adjudicator lacks jurisdiction to determine disputes that include claims for further sums due to the referring party post-liquidation.
  • Adjudication cannot override the mandatory insolvency set-off provisions which require an account to be taken of mutual dealings.
  • Practical behavior of liquidators or adjudicators does not affect the legal effect of insolvency law on claims.
  • The statutory adjudication regime does not provide adjudicators jurisdiction to determine disputes involving taking of insolvency accounts.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Stein v Blake [1996] AC 243 Bankruptcy set-off and insolvency set-off principles; claims and cross-claims merge and are extinguished upon insolvency/liquidation. Adopted to explain that claims and cross-claims between parties merge into a single balance due at liquidation, extinguishing separate claims enforceable by adjudication.
Bouygues (UK) Ltd v Dahl-Jensen (UK) Ltd [2000] EWCA Civ 507 Adjudicator’s decision enforcement and insolvency set-off; provisional nature of adjudication decisions in insolvency context. Confirmed that adjudication decisions will not be enforced if they conflict with insolvency set-off rules; summary judgment refused due to insolvency context.
Enterprise Managed Services Ltd v Tony McFadden Utilities Ltd [2009] EWHC 3222 (TCC) Jurisdiction of adjudicator in insolvency; whether adjudication can determine net balance claim under Insolvency Rules. Held adjudicator lacks jurisdiction to determine claims that have merged into a net balance under insolvency rules; adjudication cannot be piecemeal.
Twintec Ltd v Volker Fitzpatrick Ltd [2014] EWHC 10 (TCC) Court’s jurisdiction to grant injunctions restraining adjudications; enforcement of adjudicator’s jurisdiction. Supported that courts may restrain adjudications in rare clear-cut cases where adjudicator lacks jurisdiction, including insolvency-related disputes.
Philpott v Lycee Francais Charles de Gaulle School [2015] EWHC 1065 (Ch) Availability of adjudication during liquidation; whether arbitration clause and adjudication apply. Distinguished and rejected by the court for ignoring insolvency set-off principles; held adjudication is not an appropriate mechanism during liquidation for claims merged under Insolvency Rules.
Wilson and Sharp Investments Ltd v Harbour View Developments Ltd [2015] EWCA Civ 1030 Enforcement of interim payment obligations in insolvency; refusal of summary judgment where insolvency and counterclaims exist. Clarified that insolvency does not automatically bar summary judgment but courts consider merits and mutuality; not directly applicable to liquidation adjudication jurisdiction.
Melville Dundas Ltd (in receivership) v George Wimpey UK Ltd [2007] UKHL 18 Effect of insolvency on interim payments and 1996 Act provisions; interaction of insolvency and construction payment regime. Confirmed insolvency law principles override interim payment obligations; insolvency set-off rights remain intact despite 1996 Act.
Wight v Eckhardt Marine GmbH (Cayman Islands) [2003] UKPC 37 Nature of claims and debts on winding up; winding up does not extinguish debts but affects enforcement. Considered claims survive winding up but enforcement is collective under insolvency; claims cannot be separately enforced post-liquidation.
Joint Administrators of LB Holdings Intermediate 2 Ltd v Joint Administrators of Lehman Brothers International (Europe) [2017] UKSC 38 Whether contractual claims survive payment in insolvency; nature of insolvency proceedings and creditor rights. Held claims do not survive full payment in insolvency; confirmed uncertainty in insolvency law but not determinative for this case.
Willers v Joyce (No.2) [2016] UKSC 44 Approach to precedent by High Court judges; persuasive authority. Court followed relevant reasoning from Enterprise case as persuasive authority.

Court's Reasoning and Analysis

The court began by identifying the key issue: whether a company in liquidation can validly refer disputes involving claims for further sums due to adjudication. The court examined the Insolvency (England and Wales) Rules 2016, particularly Rule 14.25, which mandates that on liquidation mutual dealings between the company and creditors must be accounted and set off to arrive at a single net balance.

The court noted that the same principles applied under the earlier Insolvency Rules 1986. The effect of these rules, as explained in Stein v Blake and subsequent authorities, is that claims and cross-claims merge and are extinguished upon liquidation, leaving only a single claim for the net balance, which is the subject of the insolvency account process.

The court analyzed prior case law, including Bouygues v Dahl-Jensen and Enterprise Managed Services v Tony McFadden Utilities, which established that adjudication decisions cannot override insolvency set-off rules and that adjudicators lack jurisdiction to determine claims that have merged into a net balance claim under insolvency law.

The court rejected arguments that liquidators can pursue adjudication of individual claims or that the statutory adjudication regime overrides insolvency law. It emphasized that adjudication is a temporary and provisional mechanism incompatible with the finality and comprehensive nature of insolvency accounts.

The court also considered and declined to follow Philpott, which had taken a contrary view on the availability of adjudication during liquidation.

Further, the court addressed the argument that the 1996 Act grants a right to adjudicate "a dispute arising under the contract," but held that post-liquidation disputes relate to the insolvency account and not the contract itself, thus falling outside the adjudication regime.

The court carefully considered the interplay between insolvency law and construction adjudication, concluding that insolvency set-off principles prevail and that adjudicators lack jurisdiction to determine disputes involving claims for further sums by a company in liquidation.

Holding and Implications

The court held that a company in liquidation cannot refer a dispute to adjudication when that dispute includes (whether in whole or in part) determination of any claim for further sums said to be due to the referring party from the responding party.

The court granted declarations to this effect and a permanent injunction preventing Defendant from continuing the adjudication. The adjudicator was found to lack jurisdiction to determine the dispute referred.

The direct effect is that claims and cross-claims between parties where one is in liquidation are replaced by a single claim for the net balance under the Insolvency Rules, which cannot be adjudicated. No new precedent was set beyond confirming existing principles and applying them to the adjudication context. The decision underscores the primacy of insolvency law over adjudication in liquidation cases and limits the scope of adjudication to disputes not subsumed by insolvency set-off.