Carroll v Scottish Borders Council

Scottish Court of Session
Jul 12, 2013
Smart Summary (Beta)

Factual and Procedural Background

The Appellant resides in The City and objected to a planning permission granted by Scottish Borders Council (the Respondent) for the erection of two wind turbines, each 110 metres high, on land southwest of Neuk Farm, The City. The interested party, Company A, owns the site and applied for the planning permission. Initially, applications for the turbines were refused in 2010 and again in October 2012 on the basis that the proposal was contrary to the development plan. A review was conducted by a Local Review Body consisting of five councillors, who overturned the planning officer’s recommendation by a majority vote and granted permission on 21 March 2013, subject to conditions.

The Appellant appealed the Council’s decision to the Court of Session under section 239 of the Town and Country Planning (Scotland) Act 1997, arguing that the decision was ultra vires and that statutory requirements had not been complied with. The Appellant also sought a protective expenses order under Rule of Court 58A to limit her potential liability for expenses arising from the appeal.

Legal Issues Presented

  1. Whether the decision of the Local Review Body to grant planning permission was within the powers conferred by the Town and Country Planning (Scotland) Act 1997 and complied with the relevant statutory requirements.
  2. Whether the Appellant was entitled to a protective expenses order under Rule of Court 58A to limit her liability for expenses in the environmental appeal proceedings.

Arguments of the Parties

Appellant's Arguments

  • The planning permission granted was not within the powers accorded to the Respondent under the 1997 Act and relevant statutory requirements were not complied with.
  • The turbines would be highly visible from her home approximately one kilometre away, adversely affecting her residential amenity and property value.
  • The Local Review Body’s decision was inconsistent with earlier refusals and was made without a site visit or hearing from the Appellant or other objectors.
  • The proceedings were prohibitively expensive without a protective expenses order, justifying the limitation of liability under Rule 58A.

Respondent and Interested Party's Arguments

  • The Respondent granted planning permission lawfully and in accordance with planning policies and procedures.
  • The Appellant’s financial resources and the estimated expenses of litigation were considered, but no opposition was raised to the protective expenses order or interim suspension of the planning decision.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
R (Corner House Research) v Secretary of State for Trade and Industry [2005] 1 WLR 2600 Common law principles on protective expenses orders prior to Rule 58A. Referenced as background to the development of protective expenses orders, noting that Rule 58A replaced the need for common law orders.
R (Edwards) v Environment Agency, Case C-260/11 Interpretation of EU Directive 2011/92/EU regarding access to justice and costs in environmental litigation. Guided the court’s purposive and contextual interpretation of Rule 58A, emphasizing the need for litigation not to be prohibitively expensive and the importance of public participation in environmental matters.
R (Garner) v Elmbridge BC [2011] 3 All ER 418 Application of EU Directive principles to protective costs orders in England and Wales. Provided assistance on detailed issues related to protective expenses orders, influencing the court’s approach to financial assessments and procedural fairness under Rule 58A.
McArthur v Lord Advocate 2006 SLT 170 General principle that expenses are within the discretion of the court. Supported the court’s discretion in considering the importance of the proceedings when determining expenses under Rule 58A.
Marleasing SA v La Comercial Internacional de Alimentación SA, Case C-106/89; [1990] I ECR 4135 Principle requiring domestic law to conform with EU Directives. Supported the court’s duty to interpret Rule 58A in conformity with Directive 2011/92/EU.

Court's Reasoning and Analysis

The court analysed the protective expenses order application under Rule of Court 58A, which implements EU Directive 2011/92/EU to ensure environmental litigation is not prohibitively expensive, thereby facilitating public participation in environmental decision-making.

The court noted that Rule 58A must be interpreted purposively and contextually, in light of the Directive and relevant case law from the European Court of Justice, particularly the Edwards case. The Directive requires that proceedings be fair, equitable, timely, and not prohibitively expensive, with costs assessed in an objective manner but also considering the applicant’s actual financial resources.

Four key considerations guided the court’s determination:

  • Scope of Proceedings: The proposed proceedings fell within the Directive’s scope, as conceded by the parties, since the challenge concerned planning permission for wind turbines with environmental impact.
  • Sufficient Interest: The Appellant’s proximity to the turbines and the likely impact on residential amenity established a genuine interest in the proceedings.
  • Real Prospect of Success: The court applied a low threshold, requiring only an arguable case rather than a probable success. The Appellant’s grounds, including departure from planning policies and the Local Review Body’s departure from planning advice, satisfied this test.
  • Prohibitive Expense: The court conducted a partly subjective and partly objective assessment of the Appellant’s financial resources and the estimated litigation expenses. It concluded that without a protective expenses order, the Appellant could not reasonably proceed.

The court also emphasized confidentiality in disclosing financial information and the importance of keeping proceedings for protective expenses orders short and simple to minimize additional costs.

Regarding the terms of the protective expenses order, the court held that the Appellant’s liability for expenses to both the Respondent and Interested Party should be capped cumulatively at £5,000, and the Respondent’s and Interested Party’s liability to the Appellant capped at £30,000, consistent with Rule 58A defaults. The court treated the Respondent and Interested Party together for these purposes.

The court further decided that the expenses of the protective expenses order hearing itself should be borne by the Respondent and Interested Party and not count towards the £30,000 cap on their liability.

Finally, the court granted an interim suspension of the planning decision pending determination of the appeal and provided for an adjusted timetable for lodging documents.

Holding and Implications

The court GRANTED the Appellant’s motion for a protective expenses order under Rule of Court 58A, limiting the Appellant’s liability in expenses to the Respondent and Interested Party to a cumulative maximum of £5,000, and limiting the Respondent’s and Interested Party’s liability in expenses to the Appellant to £30,000.

The court also GRANTED an interim suspension of the planning permission decision pending the substantive appeal hearing.

This decision facilitates access to justice in environmental matters by reducing financial barriers to challenge planning decisions with environmental impact, in accordance with EU Directive 2011/92/EU and the Aarhus Convention. The ruling clarifies the application of Rule 58A in Scotland, emphasizing the balance between encouraging public participation and controlling litigation expenses. No new precedent beyond the interpretation and application of Rule 58A and relevant EU law was established; the decision primarily affects the parties by enabling the Appellant to proceed without prohibitive financial risk.