John Doyle Construction Ltd v. Laing Management (Scotland) LTD

Scottish Court of Session
Jun 11, 2004
Smart Summary (Beta)

Factual and Procedural Background

The Defendants were management contractors appointed to carry out construction of a corporate headquarters for Company A, their employer being Company B. The project was divided into multiple works packages, including WP2010 and WP2011. The Plaintiff was appointed as works contractors for WP2011, relating to certain superstructure works, under an amended Scottish Works Contract dated 14 September and 28 November 1995. The Plaintiff began work on WP2011 on 25 September 1995, with an agreed completion date 28 weeks later on 7 April 1996. Practical completion was achieved after 50 weeks on 7 September 1996.

The Plaintiff claimed entitlement to an extension of time of 22 weeks for WP2011, seeking a revised completion date of 7 September 1996, and claimed loss and expense incurred due to delay and disruption caused by the Defendants. The Plaintiff sought decree ordaining the Defendants to ascertain their loss and expense and to adjust the contract sum accordingly, concluding for payment of £4,807,144.16 as the balance due after adjustments. The dispute centered on the calculation of loss and expense allegedly caused by delay and disruption for which the Defendants were responsible.

At first instance, the action proceeded to debate in the Commercial Court focusing on two main issues: the relevancy and consistency of averments regarding delay caused by WP2010 on WP2011, and the relevancy of averments supporting the Plaintiff's claim for loss and expense, particularly the nature and maintenance of a global claim. The Lord Ordinary allowed the Plaintiff's averments to proceed to probation but held that delay in WP2010 beyond the granted extension was irrelevant for the Plaintiff’s claim. The Defendants challenged the relevancy of the Plaintiff’s claim for loss and expense on the basis that it was a global claim that could not be maintained if any material causal factor was not the Defendants’ responsibility.

Legal Issues Presented

  1. Whether the Plaintiff’s averments regarding delay caused by WP2010 on the commencement and completion of WP2011 were relevant and admissible.
  2. Whether the Plaintiff’s claim for loss and expense based on a global claim methodology was relevant and maintainable, particularly in light of the requirement that all material causative events must be attributable to the Defendants.
  3. The legal principles governing causation and apportionment in global claims for loss and expense under construction contracts.
  4. The adequacy of the Plaintiff’s pleadings in supporting a claim for loss and expense on a global or modified total cost basis.

Arguments of the Parties

Defenders' Arguments

  • The Plaintiff’s averments about delay caused by WP2010 on WP2011 were inconsistent, irrelevant, and should be excluded.
  • The Plaintiff’s claim for loss and expense was a global claim requiring that all causal factors be attributable to the Defenders; if any material cause was the Plaintiff’s responsibility or for which the Defenders had no liability, the claim should fail.
  • The schedules attached to the Plaintiff’s pleadings suggested delay was also caused by bad weather and the Plaintiff’s own responsibility for WP2010, undermining the claim.

Pursuers' Arguments

  • The Plaintiff contended that the claim was not a pure global claim but a modified total cost claim, confined largely to uneconomic labour costs and excluding some labour costs attributable to delay rather than disruption.
  • The Plaintiff averred that it was impossible to identify causal links between each cause of delay and the cost consequence, justifying a global claim approach.
  • The Plaintiff argued that the delay and disruption were caused by Defenders’ instructions, late issue of drawings and information, and delay in WP2010 only to the extent that the Defenders were responsible.
  • The Plaintiff accepted that they were not liable for delay or loss caused by WP2010 prior to a certain date and no longer relied on schedules attributing delay to WP2010 or bad weather.
  • The Plaintiff provided a detailed method of calculating uneconomic labour costs based on actual productivity comparisons rather than tender estimates, aiming to avoid double counting and to isolate disruption attributable to the Defenders.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
London Borough of Merton v Stanley Hugh Leach Ltd (1985) 32 BLR 51 Recognition that global claims for loss and expense may be advanced by contractors under construction contracts. Accepted as common ground that global claims are permissible in principle.
Wharf Properties Ltd v Eric Cumine Associates (1991) 52 BLR 8 Principles relating to claims for loss and expense in construction contracts. Referenced in support of global claim principles.
John Holland Construction & Engineering Pty Ltd v Kvaerner RJ Brown Pty Ltd (1996) 82 BLR 81 Detailed exposition of global and total cost claims and causation requirements. Used extensively to explain the nature of global claims and the necessity to eliminate causes of loss not attributable to the employer.
Boyajian v United States, 423 F 2d 1231 (1970) Criteria for acceptability of total cost claims and rejection of presumptions about contractor's costs. Adopted to emphasize need for realistic bids, reasonable costs, and that the claimant was not responsible for added expenses.
Leyland Shipping Company Ltd v Norwich Union Fire Insurance Society Ltd [1918] AC 350 Dominant cause test in causation of loss where multiple causes concur. Applied to establish that the dominant or proximate cause for loss determines liability, even if other concurrent causes exist.
Lichter v Mellon-Stuart Company, 305 F 2d 216 (1962) Approach to apportionment of loss in total cost claims when multiple causes contribute to loss. Supported the proposition that courts may undertake reasonable apportionment of loss between compensable and non-compensable causes.
Phillips Construction Co Inc v United States, 394 F 2d 834 (1968) Apportionment of loss between causes for which parties are responsible and causes for which neither is responsible. Endorsed the possibility of apportionment in claims involving concurrent causes.
Alexander v Cambridge Credit Corporation Ltd (1987) 9 NSWLR 310 Application of common sense to causation principles. Referenced to support the court’s approach to causation as a matter of common sense.

Court's Reasoning and Analysis

The Court agreed with the Lord Ordinary’s decision that the Plaintiff’s averments regarding delay caused by WP2010 beyond the granted extension were irrelevant to the claim for extension of time and loss and expense. However, the Court accepted that the Plaintiff’s primary case, based on delay caused by late instructions, late issue of drawings and information, and design changes attributable to the Defendants, was relevant and properly pled.

The Court analysed the nature of global claims, explaining that for such claims to succeed, all causative events contributing materially to the loss must be attributable to the Defendants (the employer). If any material cause is not the Defendants’ responsibility—such as bad weather or inefficiency on the Plaintiff’s part—the global claim fails unless apportionment is possible.

The Court elaborated on the legal principles of causation, emphasizing the need to prove (1) events for which the Defendants are legally responsible, (2) loss or expense suffered by the Plaintiff, and (3) a causal link between those events and the loss. The Court noted that while individual causal links between each event and loss are normally required, a global claim may be maintained if all causative events are attributable to the Defendants, eliminating the need to specify causal links for each event.

The Court further explained that where concurrent causes exist, the dominant cause test applies, whereby the dominant cause of loss determines liability. If the dominant cause is attributable to the Defendants, liability follows notwithstanding other concurrent causes. Otherwise, apportionment of loss between causes may be appropriate, especially where causes are concurrent and separable by time or effect.

The Court accepted the Plaintiff’s pleadings as adequately setting out the general causal propositions and delay events, noting that detailed proof of causation and apportionment issues must await a proof before answer. The Court also recognized the Plaintiff’s claim was a modified total cost claim rather than a pure global claim, confined largely to uneconomic labour costs and excluding some costs attributable to delay rather than disruption.

The Court held that the Plaintiff’s method of calculating uneconomic labour costs, based on comparing actual productivity during disrupted and normal work periods, was relevantly pled and not a pure global claim. The Court emphasized that the Plaintiff must prove at proof that the costs were reasonable and attributable to Defendants’ responsibility, and that the claim must exclude any costs caused by the Plaintiff or unrelated factors.

In summary, the Court found the pleadings sufficient to proceed to proof, where the complex causation and apportionment issues could be addressed with evidence. The Court rejected the Defendants’ contention that the pleadings were irrelevant or insufficient and confirmed that the claim might fail if evidence showed material causative factors not attributable to the Defendants, but that was a matter for proof.

Holding and Implications

The Court REFUSED the reclaiming motion, thereby upholding the Lord Ordinary’s decision to allow the Plaintiff’s pleadings to proceed to proof.

The direct effect of this decision is that the Plaintiff’s claim for loss and expense, based on a modified global claim methodology, is maintainable and will be examined in detail at proof before answer. The Court did not establish new precedent but reaffirmed and applied established legal principles regarding causation, global claims, and apportionment in construction contract disputes. The ruling clarifies that while global claims are permissible, they require that all material causative events be attributable to the defendant employer or otherwise subject to apportionment, and that pleadings must give fair notice of the general causal structure without excessive elaboration.