Skanska Construction UK Ltd v. The ERDC Group Ltd & Anor

Scottish Court of Session
Nov 28, 2002
Smart Summary (Beta)

Factual and Procedural Background

The dispute arises from a construction sub-contract between Company A and Company B concerning landscaping works governed by the SBCC Domestic Sub-Contract Conditions (1997 edition, August 1998 revision). The sub-contract included provisions for interim and final payments, adjustment of the sub-contract sum, direct loss and expense claims, and adjudication procedures.

Company B initiated two adjudications against Company A relating to claims for direct loss and expense. The first adjudication took place in December 2001 and January 2002 concerning an interim payment application. The adjudicator ruled that Company A was not liable to pay the claimed sums due to insufficient information and evidence.

In September 2002, Company B commenced a second adjudication relating to the final account dated March 2002, seeking payment of sums again largely related to direct loss and expense. Company A contended that this second dispute was "the same or substantially the same" as the first adjudication and requested the second adjudicator to resign pursuant to the sub-contract clause requiring resignation where the dispute is substantially the same as one previously adjudicated.

The second adjudicator refused to resign, finding jurisdiction to proceed on the basis that the first dispute concerned an interim payment, whereas the second concerned adjustment of the final sub-contract sum under different contractual provisions.

Company A sought judicial review and interim relief to suspend the second adjudication pending determination of the jurisdictional issue. The court heard submissions and refused to grant interim interdict or suspension, issuing written reasons subsequently.

Legal Issues Presented

  1. Whether the second adjudication dispute is "the same or substantially the same" as the first adjudication dispute, thereby requiring the second adjudicator to resign under Clause 8.3.2 of the sub-contract.
  2. Whether the claim for direct loss and expense in the second adjudication is time-barred by contractual provisions requiring submission of supporting documents within six months of practical completion.
  3. Whether interim interdict and suspension of the second adjudication should be granted pending judicial review of the adjudicator's jurisdiction.

Arguments of the Parties

Appellant's Arguments (Company A)

  • The second adjudication dispute is substantially the same as the first, involving essentially the same claim for direct loss and expense despite being framed as a final payment rather than an interim payment.
  • The sums claimed in both adjudications are similar in nature and amount, including categories such as prolongation of preliminaries, additional supervision, and head office overhead recovery at the same rate.
  • The first adjudicator's decision on direct loss and expense must be final due to contractual time-limits requiring supporting documents to be submitted within six months of practical completion, which had expired before the second adjudication.
  • Company A argued that any new documents or claims made after the six-month period should be disregarded or objected to, preventing re-assessment in the second adjudication.
  • They contended that a prima facie case was made for interim interdict and suspension to avoid unnecessary expense and delay the adjudication until jurisdiction was resolved.
  • They challenged the precedents relied upon by the second adjudicator, submitting that cases such as Holt Insulation Ltd v Colt International Ltd and Sherwood & Casson Ltd v Mackenzie were distinguishable or wrongly decided.

Appellee's Arguments (Company B)

  • The cost of preparing a Response to the Referral was minimal and any repetition in claims made the task easier for Company A.
  • The adjudication process is governed by a strict statutory timetable under section 108 of the Housing Grants, Construction and Regeneration Act 1996, requiring decisions within 28 days and recognizing the provisional nature of adjudicator rulings.
  • To oust the adjudicator requires a very strong prima facie case, which Company A had not established.
  • The first adjudication concerned an interim payment, while the second concerned final payment adjustments under different contractual clauses, representing distinct stages and disputes.
  • The second adjudication involved a different valuation exercise with potentially more information available, justifying the adjudicator's jurisdiction.
  • Authorities such as Holt and Sherwood supported the position that interim and final valuations are different disputes, including claims for direct loss and expense.
  • Company A had waived any time-bar arguments by participating in providing further information and attending meetings after the six-month period.
  • Company A could participate in the second adjudication and later challenge enforcement on jurisdictional grounds, making interim suspension unnecessary.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Holt Insulation Ltd v Colt International Ltd Distinction between disputes at different stages of payment (interim vs final) and adjudicator jurisdiction. The court noted the second adjudicator relied on this case to justify jurisdiction, finding the first dispute concerned interim payment while the second concerned final sum adjustment.
Sherwood & Casson Ltd v Mackenzie, 2000 T.C.C. 418 Recognition of the difference between interim and final valuations, including claims for direct loss and expense. The court found this authority supportive of the position that the two adjudications involved fundamentally different disputes.
Watson Building Services Ltd v Harrison, 2001 S.L.T. 846 Options available to a party challenging adjudicator jurisdiction, including participation followed by challenge to enforcement. The court referenced this case to emphasize that Company A could participate in the adjudication and later contest jurisdiction, undermining the need for interim relief.

Court's Reasoning and Analysis

The court analyzed the nature of the disputes in the two adjudications, concluding that they were not "the same or substantially the same" for the purposes of Clause 8.3.2. The first adjudication concerned an interim payment, while the second concerned a final payment adjustment under different contractual provisions. The stage of the contract, the applicable clauses, and the information available differed substantially.

Regarding the time-bar argument, the court found no clear and unambiguous contractual language imposing a strict prohibition on submitting claims or supporting documentation after six months from practical completion. Clause 4.38.3 suggested that direct loss and expense could be ascertained and added to the sub-contract sum over time.

The court further held that Company A had waived any right to rely on a time-bar by their conduct in providing information and attending meetings after the six-month period.

Consequently, the court found that Company A failed to establish a prima facie case for interim interdict or suspension of the second adjudication. It was unnecessary to consider the balance of convenience.

Holding and Implications

The court REFUSED to grant interim interdict or interim suspension of the second adjudication.

The direct effect of this decision is that the second adjudication was allowed to proceed without interruption. No new precedent was established; the ruling reinforced the distinction between interim and final payment disputes under construction contracts and the limited circumstances in which adjudicator jurisdiction can be challenged by interim relief.