The Manchester Ship Canal Company Ltd v The Environment Agency

England and Wales High Court (Queen's Bench Division)
Jun 7, 2017
Smart Summary (Beta)

Factual and Procedural Background

The claimant, which owns and operates the Manchester Ship Canal, brought a claim seeking a declaration that the defendant, the Environment Agency (the statutory successor to the Mersey River Board), is liable to compensate the claimant under an agreement dated 15 November 1963 (the "Agreement"). The claim relates to two flooding incidents in June 2012 and December 2015, which allegedly caused increased flow rates from the River Irwell to the Manchester Ship Canal. The defendant applied to strike out the claim pursuant to CPR 3(2)(a) and/or for summary judgment under CPR 24.2, arguing that the claimant has no reasonable prospect of success. The application was supported by witness statements and expert reports, and the claimant filed responsive witness statements and expert reports. The court considered the application without a full trial.

Legal Issues Presented

  1. Whether the claimant has a real prospect of success in proving that an agreement was reached pursuant to clause 4 of the Agreement regarding the site for measuring water flow.
  2. Whether the court can construe the Agreement to allow retrospective agreement on the site or substitute its own decision in the absence of agreement or arbitration.
  3. Whether the requirement for agreement or arbitration as to the site is a non-essential term of the contract, allowing the court to intervene.
  4. Whether the site for measuring water flow could be determined retrospectively by arbitration.

Arguments of the Parties

Claimant's Arguments

  • The court may infer that an agreement was reached between the engineers of the parties as contemplated by clause 4, despite no formal record.
  • The Agreement can be construed to allow the site to be agreed retrospectively.
  • The requirement for agreement or arbitration is a non-essential part of the contract machinery, and the court can substitute its own decision, relying on Sudbrook Trading Estate Ltd v Eggleton [1983] 1 AC 444.
  • The site could be determined by arbitration retrospectively if the court does not intervene.
  • Clause 7 places the onus on the Board to construct gauges, and since no evidence shows new gauges were constructed, the inference is that the Board accepted existing gauge sites.
  • The purpose of the Agreement was to compensate the claimant for increased dredging costs caused by the Board’s works, and the court should give effect to this quid pro quo.
  • The court could interpret clause 4 as a right for the claimant to designate a site, which could be waived to allow use of existing data retrospectively.
  • The court could substitute its own machinery for determining the site, citing the Court of Appeal decision in Herbert v Doyle [2010] EWCA Civ 1095.

Defendant's Arguments

  • The claimant has not pleaded that an agreement was reached as to the site, and the claimant’s pleadings acknowledge the absence of such agreement.
  • There is no evidence supporting that an agreement was reached; had there been one, records would exist.
  • The sequence of events prescribed by the Agreement requires the site to be agreed or determined before gauges are constructed and measurements taken; the process cannot be retrospective.
  • The location and nature of the gauges are critical, and the flow information from the Adelphi Weir site is considered unreliable at high flows.
  • The decision in Sudbrook is distinguishable as it concerns valuation machinery and deadlock, which are not present here.
  • Clauses 4 to 8 are separate from clauses 1 to 3, and the Agreement remains operative even if compensation is not payable due to failure to agree a site.
  • The court cannot override the express terms of the Agreement based on general notions of fairness.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Sudbrook Trading Estate Ltd v Eggleton [1983] 1 AC 444 The court may substitute its own machinery for a contractual mechanism that is subsidiary and non-essential when that machinery breaks down due to one party's breach. The court distinguished this case from Sudbrook, finding that the requirement for agreement on the site is essential and cannot be overridden by the court. Unlike valuation cases, the court cannot identify the measurement site absent agreement.
Herbert v Doyle [2010] EWCA Civ 1095 The court may imply a term allowing it to select an option or mechanism in a contract where a party has failed to make a necessary choice, to give effect to the contract. The court accepted the principle but found the present case distinguishable because the parties are not in deadlock or default, and the court lacks sufficient evidence to designate a site.
Wood v Capita Insurance Services Ltd [2017] UKSC 24 Contract construction requires ascertaining the objective meaning of the language in context, giving weight to the wider contractual framework and commercial purpose. The court applied this principle to interpret clauses 4 and 7, concluding the agreement on the site had to be reached contemporaneously with the commencement of works, consistent with commercial common sense.

Court's Reasoning and Analysis

The court began by considering the defendant's strikeout and summary judgment application on the basis of the claimant's pleaded case, concluding that the claimant could not assert that an agreement as to the measurement site had been reached because it was not pleaded. The absence of any record or evidence of such an agreement, despite searches conducted, undermined any inference that an agreement existed.

The court rejected the claimant's inference that the Board was content to use existing gauge sites instead of constructing new ones as required by clause 7, noting that clause 7 explicitly requires new gauges to be constructed contemporaneously with the commencement of works. Expert opinion suggesting a "pragmatic" approach was regarded as speculative and insufficient to establish an agreement.

Applying principles of contractual construction from Wood v Capita Insurance Services Ltd, the court found that the Agreement's language and commercial context require the site agreement to be reached at the outset of the works. The notion of a retrospective agreement or retrospective calculation of compensation was rejected as inconsistent with the plain wording and commercial purpose of the Agreement.

The claimant's submission that the court could treat the agreement/arbitration requirement as non-essential and substitute its own decision was considered in light of Sudbrook and Herbert v Doyle. The court distinguished these authorities, emphasizing that the measurement site determination involves technical expertise of engineers and is an essential term, not a subsidiary mechanism. Unlike valuation cases, the court found it could not identify the site from the evidence before it.

Finally, the court rejected the contention that arbitration could be used retrospectively to determine the site, holding that the court's role is to interpret the objective meaning of the contract, not to amend or improve the bargain beyond its terms.

Holding and Implications

The court granted the defendant's application for summary judgment, holding that the claimant has no real prospect of succeeding on the claim based on the pleaded case and the construction of the Agreement.

The direct effect of this decision is the dismissal of the claimant's claim for compensation under the Agreement. The court did not establish any new legal precedent but reaffirmed established principles of contract construction, the essential nature of certain contractual terms, and the limits of judicial intervention in contractual machinery absent clear authority or evidence. The claimant’s failure to plead an agreement and the absence of evidence precluded the claim’s success.