Interserve Construction Ltd v Hitachi Zosen Inova AG

England and Wales High Court (Technology & Construction Court)
Oct 31, 2017
Smart Summary (Beta)

Factual and Procedural Background

These proceedings arise from the construction of an energy from waste plant in The City. The Defendant, Company A, was the main EPC contractor and entered into a design and build sub-contract with the Plaintiff, Company B, concerning civil works and building facilities ("the Contract"). The Contract was executed on 21 May 2014, with Company A designated as the Purchaser and Company B as the Contractor. Work commenced on 27 May 2014. On 6 July 2015, Company A sought to terminate Company B's employment under the Contract, and Company B was subsequently removed from the site.

The termination provisions were set out in clause 43 of the Contract, particularly clause 43.1 and 43.1A, which detailed the grounds and procedures for termination for Contractor default. Company A delivered a termination notice on 7 July 2015, citing specific breaches including failure to proceed regularly and diligently and material breaches of contract. Company B disputed the termination, contending it was wrongful and constituted a repudiatory breach by Company A, and exercised its right to accept the repudiation, treating the Contract as terminated.

Company B commenced proceedings in November 2016 seeking declarations regarding the proper interpretation of clause 43.1 and 43.1A, specifically whether it was a condition precedent for Company A to issue a notice under clause 43.1A before terminating under clause 43.1(h) and (q). Company A contended that the giving of notice under clause 43.1A was at its absolute discretion and not a condition precedent to termination.

Legal Issues Presented

  1. Whether it was a condition precedent under the Contract that the Purchaser (Company A) must first issue a notice under clause 43.1A and allow a seven-day period for rectification before terminating the Contractor's (Company B's) employment pursuant to clause 43.1(h) and/or 43.1(q).

Arguments of the Parties

Appellant's Arguments (Company B)

  • The natural and proper construction of clause 43.1 is that the right to terminate for defaults specified in sub-clauses (h), (p), and (q) is "subject to" clause 43.1A, meaning termination can only occur after a notice under 43.1A and a seven-day rectification period.
  • The phrase "subject to" elsewhere in the Contract consistently limits rights, supporting this interpretation.
  • Company A’s construction renders the words "subject to" redundant, which is unlikely in a carefully drafted commercial contract.
  • Company A could always require rectification without the need for explicit contractual language, so clause 43.1A creates a meaningful procedural step.

Appellee's Arguments (Company A)

  • The giving of notice under clause 43.1A is at the Purchaser’s absolute discretion and is not a condition precedent to termination under clause 43.1.
  • If Company A chooses not to give a notice under clause 43.1A, it may terminate forthwith under clause 43.1.
  • The words "subject to" in clause 43.1 clarify that clause 43.1A provides an additional right but does not limit the right to terminate immediately.
  • The phrase "at its absolute discretion" means Company A’s decision to give or withhold notice under 43.1A carries no adverse consequences or waiver of rights.
  • Company B did not raise the absence of a notice under clause 43.1A in its initial repudiation letter, indicating both parties’ shared understanding of clause 43.1’s operation.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Wood v Capita [2017] UKSC 24 Principles of contractual construction: objective meaning, textual and contextual analysis, and the iterative process in interpretation. The court applied these principles to interpret clause 43.1 and 43.1A, focusing on the natural meaning of "subject to" and the contract as a whole.
Secretary of State for Defence v Turner Estate Solutions Ltd. [2015] EWHC 1150 Interpretation of contractual language avoiding redundancy, especially in bespoke contracts. The court relied on this authority to support the view that the phrase "subject to" must be given effect and not rendered redundant.

Court's Reasoning and Analysis

The court began by applying established principles of contractual interpretation, emphasizing an objective approach considering both textual and contextual elements as set out in Wood v Capita. The court noted the Contract was a complex commercial document between sophisticated parties, warranting careful textual analysis.

The court examined the phrase "subject to Sub-Clause 43.1A" in clause 43.1 and concluded that its natural meaning is that the right to terminate under sub-clauses (h), (p), and (q) is conditional upon first issuing a notice under clause 43.1A and allowing a seven-day rectification period. This interpretation was supported by consistent use of "subject to" elsewhere in the Contract, where it limits or circumscribes rights, and by the principle that contractual words should not be rendered redundant.

The court rejected Company A’s argument that the clause gives an absolute discretion to omit the notice under 43.1A and terminate immediately, reasoning that the phrase "at its absolute discretion" serves to emphasize the choice to give notice without adverse consequences, not to negate the condition precedent. The court found that Company A’s construction made the words "subject to" redundant, which is unlikely in a bespoke contract.

The court also considered the commercial sense of the construction, noting that the opportunity to remedy breaches that are evaluative in nature aligns with the requirement to give notice and a rectification period.

The court was not persuaded by Company A’s submission that the parties’ conduct or the absence of a specific argument from Company B at an earlier stage indicated a shared interpretation of the Contract.

Accordingly, the court granted the declaration sought by Company B that issuing a notice under clause 43.1A and allowing a seven-day rectification period is a condition precedent to termination under clause 43.1(h) and 43.1(q).

Holding and Implications

The court held that it was a condition precedent to the Purchaser's right to terminate under clause 43.1(h) and 43.1(q) that the Purchaser must first issue a notice under clause 43.1A and allow the Contractor a seven-day period in which to commence and diligently pursue rectification of the default.

The direct effect of this decision is that the Purchaser’s termination notice dated 6 July 2015 was invalid insofar as it failed to comply with this condition precedent. No further declarations were granted, and the court did not establish any new precedent beyond the interpretation of the specific contractual provisions before it. The ruling underscores the importance of procedural compliance with contractual termination provisions in complex commercial contracts.