MT Hojgaard AS v EON Climate and Renewables UK Robin Rigg East Ltd & Anor

United Kingdom Supreme Court
Aug 3, 2017
Smart Summary (Beta)

Case Summary

Factual and Procedural Background

Company A engaged Company B to design, fabricate and install the foundations for two offshore wind farms in the Solway Firth (“the Project Site”). The written contract incorporated extensive “Technical Requirements” (TR) and required compliance with an international standard known as J101. Shortly after completion in February 2009, the foundations began to fail because the grouted connections slipped. Investigation revealed that J101 contained an erroneous design value, causing the axial capacity of the connections to be significantly overstated.

Company A undertook remedial works costing £26.25 million and sought to recover that sum. Company B denied liability, asserting that it had exercised reasonable skill and care and had complied with J101. After an eight-day trial before Judge Edwards-Stuart in 2013, Company B was held liable. The Court of Appeal (per Judge Jackson, with Judges Patten and Underhill agreeing) reversed that decision. Company A appealed to the Supreme Court, where Judge Neuberger delivered the unanimous judgment (with Judges Mance, Clarke, Sumption and Hodge concurring).

Legal Issues Presented

  1. Whether paragraph 3.2.2.2(ii) of the Technical Requirements—stating that the foundations “shall ensure a lifetime of 20 years in every aspect without planned replacement”—was contractually binding on Company B.
  2. If binding, whether that paragraph imposed (a) a warranty that the foundations would function for 20 years or (b) an obligation that they be designed to achieve a 20-year life.
  3. Whether the 20-year obligation was inconsistent with, and therefore overridden by, the contractual requirement to design in accordance with J101.
  4. Whether clauses 30, 33 and 42 (which imposed a two-year post-completion defect liability regime) displaced or limited any 20-year obligation.
  5. Consequently, whether Company B was liable for the cost of remedial works despite having followed J101 and exercised reasonable skill and care.

Arguments of the Parties

Company A’s Arguments

  • Clause 8.1(x) required the works to be “Fit for Purpose,” which Part C defined by reference to the Employer’s Requirements; those requirements expressly included the TR.
  • Paragraph 3.2.2.2(ii) (and similar wording in paragraph 3b.5.1) therefore formed part of the contract and imposed a clear 20-year obligation.
  • Paragraph 3.1 of the TR states that the listed requirements are “MINIMUM” standards; where J101 and the 20-year obligation conflict, the more rigorous 20-year requirement prevails.
  • The foundations demonstrably failed the 20-year standard within months, establishing breach.

Company B’s Arguments

  • The contract’s primary obligation was to comply with J101; Company B did so and exercised due skill and care, so it should not be liable.
  • Paragraph 3.2.2.2(ii) is “too slender a thread” in a technical document to create a far-reaching warranty; if such an obligation were intended it would have been stated prominently as a “Key Functional Requirement.”
  • Clauses 30, 33 and 42 create an exclusive two-year defect regime, inconsistent with any 20-year warranty.
  • Any design-life references in the TR merely recorded the 20-year design assumption contemplated by J101 and did not impose additional legal duties.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Thorn v Mayor of London (1876) 1 App Cas 120 A contractor cannot rely on the employer’s defective specification to avoid liability. Cited as early authority illustrating contractor responsibility when agreeing to an employer-specified design.
The Hydraulic Engineering Co Ltd v Spencer (1886) 2 TLR 554 Where a contract sets performance criteria and prescribes a design, the contractor remains liable if the criteria are unmet. Used to support giving full effect to performance obligations notwithstanding compliance with prescribed design.
A M Gillespie & Co v John Howden & Co (1885) 22 SLR 527 A contractor who undertakes an impossible specification is still liable for failure to meet agreed performance. Reinforced the principle that design approval by the employer does not shift performance risk.
The Steel Co of Canada v Willand Management [1966] SCR 746 Express performance guarantees override obligations merely to follow plans and specifications. Endorsed by the Court as persuasive Commonwealth authority favouring Company A’s interpretation.
Greater Vancouver Water District v North American Pipe (2012) BCCA 337 Clear performance warranties apply even where specifications are defective. Cited to underline modern acceptance of performance-over-design obligations.
Cammell Laird v Manganese Bronze [1934] AC 402 Contractual language controls; performance obligations are enforceable even if design makes them difficult. Quoted for Lord Wright’s summary of the governing principle.
Wood v Capita Insurance Services [2017] 2 WLR 1095 Sets out modern principles of contractual interpretation. Provided interpretive framework for reading the parties’ documents.
In re Sigma Finance Corp [2010] 1 All ER 571 Courts should interpret diffuse, multi-authored documents realistically. Referenced to acknowledge drafting imperfections but insist on giving effect to clear words.
In re Lehman Bros (No 4) [2017] 2 WLR 1497 Redundancy is not a strong reason to disregard plain contractual language. Used to rebut Company B’s argument that paragraph 3.2.2.2(ii) was superfluous.

Court’s Reasoning and Analysis

1. Incorporation of the 20-Year Provision. Clause 8.1(x) linked “Fit for Purpose” to the Employer’s Requirements, which expressly included the TR. Accordingly paragraph 3.2.2.2(ii) was contractually binding.

2. Interaction with J101. Paragraph 3.1 of the TR declared that all listed requirements were “MINIMUM” standards and obliged Company B to identify any need for “more rigorous requirements.” Therefore, if literal compliance with J101 (which contained the erroneous design value) would prevent achievement of a 20-year life, Company B had to depart from J101 to meet the higher standard. The two provisions were not inconsistent; the more demanding requirement prevailed.

3. Clauses 30, 33 and 42. Those clauses provided an exclusive two-year defect-liability and limitation regime. The Court held that regime could co-exist with a 20-year design obligation: Company A merely had to discover within two years that the foundations were not designed for 20 years, which in fact occurred.

4. “Too Slender a Thread” Argument. The Court rejected Company B’s submission that a single sub-paragraph in a technical document could not impose so weighty an obligation. The language was clear, appeared against the background of repeated references to a 20-year design life, and must be given its natural meaning.

5. Precedent and Policy Considerations. Drawing on UK and Canadian authorities, the Court emphasized that where a contractor agrees both to follow a design and to meet performance criteria, it bears the risk that the design will achieve those criteria unless the contract states otherwise.

Holding and Implications

Holding: The Supreme Court allowed the appeal and restored the first-instance judgment holding Company B liable for breach of contract.

Implications: The decision affirms that clear performance or design-life obligations in technical schedules are fully enforceable, even where the contract also mandates adherence to an industry standard. Contractors must treat employer-specified standards as a minimum and satisfy any more stringent performance language. The case provides authoritative guidance on reconciling “design” and “fitness for purpose” clauses in complex construction contracts but does not create new law beyond reinforcing existing interpretive principles.