Pelagic Freezing Ltd v Lovie Construction

Scottish Court of Session
Oct 28, 2010
Smart Summary (Beta)

Factual and Procedural Background

In approximately 2001, the Plaintiff entered into a contract with the First Defendant for the conversion and extension of an existing warehouse in The City into a fish processing complex. The First Defendant was responsible for completing the design of the cladding system. The Second Defendant was appointed to provide architectural, quantity surveying, and planning supervision services under the building contract. Partial demolition began in 2001, and the Plaintiff commenced operations in the new building around 10 July 2002, with a certificate of practical completion issued on 8 October 2002, backdated to 2 September 2002.

Following completion, persistent issues with water ingress through the roof arose. On 3 February 2009, the Plaintiff initiated proceedings against both Defendants, alleging breach of contract and negligence. The Defendants contended that any right of action was extinguished by the short negative prescription. The Plaintiff denied this and relied on Sections 11(3) and 6(4) of the Prescription and Limitation (Scotland) Act 1973 as amended.

A preliminary proof was allowed on the question of prescription, during which evidence was led solely for the Plaintiff. Both parties submitted detailed written outlines and a joint minute of admissions was lodged.

Legal Issues Presented

  1. Whether the Plaintiff's cause of action against the Defendants has been extinguished by the short negative prescription under Section 11(1) of the Prescription and Limitation (Scotland) Act 1973.
  2. Whether the Plaintiff had actual or constructive awareness of the relevant defects and damage within the prescriptive period, engaging the provisions of Section 11(3) of the 1973 Act.
  3. Whether the Plaintiff was induced by error, caused by the words or conduct of the Second Defendant, to refrain from making a claim, under Section 6(4) of the 1973 Act.
  4. The proper identification and characterization of defects and defaults alleged, including whether later-emerging defects constitute separate and distinct causes of action for prescription purposes.
  5. The allocation of the burden of proof regarding prescription and exceptions thereto.

Arguments of the Parties

Plaintiff's Arguments

  • The Plaintiff's principal defect complaint is panel corrosion, first manifesting in 2005, distinct from earlier minor defects and roof leaks.
  • The Plaintiff contends that the Defendants failed to prove that the defects occurred outside the prescriptive period.
  • Relying on Sections 11(3) and 6(4), the Plaintiff argues that they lacked actual or constructive knowledge of the defects until less than five years before the action and were induced by the Second Defendant's conduct to delay raising proceedings.
  • The Plaintiff asserts that the Defendants' administration of the contract, including issuing a certificate of making good defects in 2006, misled them into believing the roof problems were being addressed.
  • The Plaintiff maintains that the Second Defendant had a continuing duty to monitor and remedy design defects.
  • The Plaintiff submits that the burden of proof for prima facie prescription under Section 11(1) lies with the Defendants, and since no evidence was led by them, inferences favorable to the Plaintiff should be drawn.

First Defendant's Arguments

  • The First Defendant disputes the reliability of some Plaintiff witnesses but accepts limited knowledge of events by one witness.
  • The First Defendant argues that the burden of proof regarding prescription lies with the Plaintiff.
  • They submit that the defects and defaults alleged constitute a single indivisible obligation, and the Plaintiff cannot split the loss to avoid prescription.
  • The First Defendant contends that material damage and actionable defaults occurred by January 2004, including widespread water ingress and storm damage.
  • The First Defendant rejects the Plaintiff's argument that prescription only began after the defects liability period or after 2005.
  • They assert the Plaintiff had actual awareness of damage and actionable defaults by early 2004.
  • The First Defendant argues that the Plaintiff failed to prove lack of awareness or inducement to delay under Sections 11(3) and 6(4).
  • They seek absolution from the case on the basis that the action has prescribed.

Second Defendant's Arguments

  • The Second Defendant adopts the submissions of the First Defendant.
  • They maintain the Plaintiff's case is based on design failures completed before practical completion in 2002, and no continuing breaches post-date that.
  • The Second Defendant contends that the cause of action accrued at the latest by January 2004, with material damage and defaults evident then.
  • They argue the Plaintiff was aware or could with reasonable diligence have been aware of actionable loss and damage by early 2004.
  • The Second Defendant denies inducing any relevant error causing the Plaintiff to refrain from raising proceedings.
  • They submit that reliance on the Rigidal warranty does not constitute a relevant error under Section 6(4) as it concerned third parties and did not affect the Defendants' liability.
  • The Second Defendant requests that the plea of prescription be sustained and the action against them dismissed.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Ross v Associated Portland Cement Manufacturers Ltd [1964] 1 WLR 768 Drawing favorable inferences for the party who led evidence when the opposing party led none. The court accepted that the Defendants, having led no evidence, could not complain if favorable inferences were drawn for the Plaintiff.
AMN Group Ltd v Gilcomston North Ltd 2008 SLT 835 Onus of proof regarding prescription; multiple distinct defects may give rise to multiple prescriptive periods. The court applied the principle that multiple discrete defaults may have separate prescriptive periods but emphasized a pragmatic approach to identifying distinct causes of action.
BP Exploration Operating Co Ltd v Chevron Shipping Co 2001 SC(HL) 55 Onus of proving "prima facie" prescription rests with the party pleading prescription. The court considered the onus of proof in relation to prescription and discussed its application.
Strathclyde Regional Council v W A Fairhurst & Partners 1997 SLT 658 Burden of proof in prescription and limitation contexts. The court referenced this case in considering burden of proof issues.
Britannia Building Society v Clarke 2001 SLT 1355 Shifting onus of proof regarding knowledge of cause of action under Section 11(3) of the 1973 Act. The court acknowledged that once prima facie prescription is established, the onus shifts to the Plaintiff to prove lack of awareness.
Dunlop v McGowans 1980 SC(HL) 73 Requirement of concurrence of damnum and iniuria for cause of action; indivisibility of obligation to make reparation. The court applied this principle to reject the Plaintiff's attempt to split causes of action.
Sinclair v MacDougall Estates Ltd 1994 SLT 76 Pragmatic approach to identifying discrete defaults and their prescriptive periods. The court used this principle to assess whether later defects were distinct or developments of earlier ones.
Musselburgh & Fisherrow Co-operative Society Ltd v Mowlem Scotland Ltd 2004 SCLR 412 Consideration of distinct and discrete defaults for prescription. The court referenced this case in applying a pragmatic approach to the facts.
Brickfield Properties Ltd v Newton [1971] 1 WLR 862 Continuing duty of design professionals to monitor and correct errors. The Plaintiff alleged a continuing duty, but the court found no such averment on record post practical completion.
Glasper v Rodger 1996 SLT 44 Standard of awareness for prescription under Section 11(3) of the 1973 Act. The court applied this standard in assessing the Plaintiff's awareness of damage and actionable defaults.
Kelly v Gilmartins Executrix 2004 SC 784 Requirement for separate damnum and iniuria to establish distinct causes of action for prescription. The court applied this principle to reject the Plaintiff's attempt to treat later defects as separate causes of action.
Jackson v Clydesdale Bank Plc 2003 SLT 273 Prescription runs from accrual of cause of action; warranty or indemnity from third parties does not affect this. The court held that reliance on a warranty does not extend prescription against the Defendants.
Adams v Thorntons 2005 SC 30 Tests for error-induced postponement of prescription under Section 6(4) of the 1973 Act. The court applied these tests and found the Plaintiff failed to satisfy them.
Warren James (Jewellers) Limited v Overgate GP Limited [2010] CSOH 57 Interpretation of multiple defaults and prescription periods; concurrent faults. The court applied the reasoning to the present case, emphasizing concurrent faults rather than distinct causes.
Greater Glasgow Health Board v Baxter Clark and Paul 1990 SC 237 Concurrent fault and indivisibility of cause of action for prescription. Referenced to support the court's view on concurrent fault in this case.
Pirelli General Cable Works Limited v Oscar Faber and Partners [1983] 2 AC 1 Accrual of cause of action upon material damage and breach. The court applied this authority to determine accrual date as at latest January 2004.
Richardson v Quercus Limited (unreported 1997; 1999 SC 278) Burden of proof in prescription cases may lie with the pursuer. The court considered this authority in its analysis of the burden of proof.
Brown v North British Steel Foundry Limited 1968 SC 51 Burden of proof in limitation and prescription contexts. Referenced regarding burden of proof considerations.
Cartledge v E Jopling & Sons Ltd [1963] AC 758 Onus of proof in limitation cases; distinction from prescription. Discussed in relation to burden of proof but distinguished from Scots prescription law.
London Congregational Union Inc v Harriss & Harriss [1988] 1 All ER 15 Limitation principles relevant to prescription. Referenced in burden of proof discussion.
First National Commercial Bank Plc v Humberts [1995] 2 All ER 673 Limitation principles relevant to prescription. Referenced in burden of proof discussion.
DNB Mortgages Limited v Bullock & Lees [2000] PNLR 427 Limitation principles relevant to prescription. Referenced in burden of proof discussion.

Court's Reasoning and Analysis

The court began by assessing the burden of proof concerning prescription. It found that while there is some divergence in authority, the burden of proving that a legal right of action exists and has been preserved rests with the Plaintiff. This includes proving that the concurrence of damnum (damage) and iniuria (wrong) occurred within the prescriptive period.

The court applied established principles allowing multiple discrete incidents of loss or damage to give rise to separate prescriptive periods only if they involve distinct and discrete defaults. A pragmatic approach was required, focusing on the nature, location, and scale of defects and defaults.

Examining the Plaintiff's pleadings and evidence, the court found that the roof defects and defaults, including panel corrosion and problems with fixings, were closely connected and constituted concurrent faults rather than distinct causes of action. The panel corrosion was not a truly separate defect but rather a development of earlier problems linked to inadequate fixings.

Material damage and actionable defaults were found to have occurred by early January 2004, evidenced by widespread water ingress and storm damage. The Plaintiff's own evidence acknowledged ongoing roof problems and reliance on the Defendants' management and warranties.

The court rejected the Plaintiff's submission that prescription only began after the defects liability period or after 2005, emphasizing that the defects liability period did not extend the prescriptive period, especially against the Second Defendant, who had no continuing duty post practical completion.

Regarding Sections 11(3) and 6(4) of the 1973 Act, the court held that the Plaintiff failed to discharge the burden of proving lack of awareness or inducement to refrain from raising proceedings. The Plaintiff had actual awareness of material damage and actionable defaults by early 2004 and was not misled in a manner sufficient to postpone prescription.

The court concluded that the Plaintiff's right of action was extinguished by the short negative prescription before 4 February 2004, and therefore the pleas-in-law of prescription for both Defendants were sustained.

Holding and Implications

The court sustained the third plea-in-law for each of the First and Second Defendants and granted absolvitor, thereby dismissing the Plaintiff's action on the basis that it had prescribed.

The direct effect of this decision is that the Plaintiff's claims against both Defendants are barred due to the expiry of the prescriptive period. The court did not establish any new legal precedent but applied existing principles of prescription, burden of proof, and the characterization of defects and defaults in construction cases.