Ramsay & Son v. Brand

Scottish Court of Session
Jul 20, 1898
Smart Summary (Beta)

Factual and Procedural Background

This case arises from a contract between Company A, builders, and Defendant for the mason work of a cottage located in The City. The contract required the work to be completed to the entire satisfaction of the architect in every respect, for a lump sum of £79, 10s. The Defendant changed architects multiple times during the project, with three architects involved sequentially.

Company A commenced the work, but Defendant contended that the mason work executed was materially disconform to the contract specifications, and thus Company A was not entitled to payment or to complete the work. Company A raised an action in the Sheriff Court seeking declarator that they were entitled to complete the mason work and payment of the contract price.

The Sheriff-Substitute initially found in favour of Company A, granting them the right to complete the work under the supervision of the current architect and awarding the contract price. Defendant appealed, and the Court recalled the interlocutors and remitted to the architect to report on whether the work executed prior to the initial ruling was done to his entire satisfaction, the nature of any disconformity, and the cost to complete the work in accordance with the contract.

The architect submitted a detailed report identifying several deviations from the contract specifications and estimated the cost to complete the work properly and the sum to be deducted if the building remained as it was. The parties argued based on this report, with Defendant relying on the disconformity to deny payment, and Company A relying on the architect’s expressed satisfaction to claim the contract price.

Legal Issues Presented

  1. Whether Company A is entitled to the contract price despite deviations from the contract specifications.
  2. Whether deviations from contract specifications that are only matters of detail entitle Company A to payment less the cost of completing the work in accordance with the contract.
  3. The legal effect and authority of the architect’s approval when work is disconform to the contract specifications.

Arguments of the Parties

Defendant's Arguments

  • The mason work executed and materials supplied were materially disconform to the contract.
  • Company A is not entitled to payment or declarator to complete the work because the work does not conform to the contract.
  • The architect’s report conclusively proves the non-conformity of the work and thus denies Company A’s claim.
  • It is irrelevant that the work might be better than specified if it does not comply with the contract terms.

Company A's Arguments

  • The architect’s award is final and he expressed satisfaction with the work despite some disconformity.
  • This satisfaction entitles Company A to the contract price.
  • Deviations from the contract specifications that are only matters of detail should result in a deduction from the contract price, not forfeiture of the entire claim.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Waddell v. Campbell (January 21, 1898) Work done disconform to contract does not entitle claim for contract price. Supported Defendant’s argument that non-conformity negates entitlement to contract price.
Chapman v. Edinburgh Prison Board (July 16, 1844) Architect’s award is final and entitles contractor to payment despite some deviations. Supported Company A’s argument regarding architect’s approval.
Muldoon v. Pringle (June 9, 1882) Architect’s satisfaction as a basis for payment under contract. Referred to in support of Company A’s position.
Ayr Road Trustees v. Adams (December 14, 1883) Architect’s approval and contract compliance principles. Referred to in support of Company A’s position.
Moore v. Paterson (December 16, 1881) Architect’s role in contract execution and satisfaction. Referred to in support of Company A’s position.

Court's Reasoning and Analysis

The Court emphasized the fundamental principle that a contractor cannot claim the contract price unless the work has been executed "modo et forma"—in accordance with the contract terms. This principle applies equally to building contracts.

The Court acknowledged that strict adherence to every minute detail is required, but the law recognizes that minor deviations or omissions that are matters of detail do not preclude payment. Instead, the contract price should be reduced by the cost necessary to complete the work in exact compliance with the contract.

The Court observed that the deviations identified in the architect's report were of a minor nature and fell within this exception, justifying a deduction rather than a complete denial of payment. The amount of £41, 4s. was fixed as the sum necessary to complete the work in accordance with the contract, to be deducted from the contract price.

The Court rejected the use of the architect’s estimate of savings to the builder from the deviations as a basis for deduction, as well as any comparison of the value of the work done versus the contract work.

The Court clarified the role of the architect's approval, stating that the architect cannot approve work done disconform to the contract without special permission. The architect’s approval applies only to the manner of fulfilling the contract terms, not to dispensation from them.

Finally, the Court noted that the Defendant's changing of architects multiple times likely contributed to the difficulties in supervision and execution of the work, which was a factor in the Court’s hesitation to place full responsibility on the builder.

Holding and Implications

The Court granted decree in favour of Company A for the contract price less the sum of £41, 4s., which represents the cost to complete the work in accordance with the contract specifications.

The decision confirms the legal principle that a contractor must perform work strictly according to contract terms to claim full payment. However, where deviations are minor and matters of detail, the contractor is entitled to the contract price minus a reasonable deduction to complete the contract properly. The architect’s approval is significant but cannot override express contract requirements without explicit authority.

No new precedent was set; rather, the decision applied and clarified existing principles regarding contract compliance, architect approval, and partial deviations in building contracts.