G Mackay & Son v. Police Commissioners of Leven

Scottish Court of Session
Jul 20, 1893
Smart Summary (Beta)

Factual and Procedural Background

A firm of contractors ("Plaintiff") tendered to construct waterworks according to a specification issued by the police commissioners of a burgh ("Defendant"). The specification stated that the contractor would receive possession of the ground immediately after acceptance of the tender and required a formal contract. The tender was accepted on 11th September 1889, and a formal contract was executed thereafter. This contract incorporated the specification but reserved to the Defendant the right to appoint the time when the Plaintiff could enter the lands and proceed with the works.

The Plaintiff did not gain entry to the lands until June 1890 and claimed damages for the Defendant's failure to provide timely entry as allegedly required by the contract or tender acceptance. The Plaintiff maintained that the question of timely entry should be referred to an arbiter named in the contract.

The Defendant denied fault, explaining that statutory proceedings delayed entry and that the delay was not due to their negligence. The case proceeded through interlocutors, with the Lord Ordinary finding the claim for damages did not fall within the arbitration clause and that no relevant averments supported the claim. The Plaintiff appealed this decision.

Legal Issues Presented

  1. Whether the claim for damages due to delayed possession of the land falls within the scope of the arbitration clause in the contract.
  2. Whether the arbiter has jurisdiction to assess damages arising from the Defendant's alleged failure to give timely entry.
  3. Whether the Plaintiff's averments sufficiently establish a relevant claim for damages against the Defendant.
  4. Whether the question of the true meaning or construction of the contract regarding entry timing falls to the arbiter or the Court.

Arguments of the Parties

Appellant's Arguments

  • The Plaintiff argued that the failure to provide timely entry raised a question as to the true meaning of the contract, which according to the arbitration clause should be referred to the arbiter for decision.
  • They contended that even if the arbiter lacked power to assess damages, he should decide on the contract's construction, and if he found the Defendant liable, the Court should then assess damages.
  • The Plaintiff asserted that the statutory proceedings causing delay constituted "legal proceedings" under the arbitration clause, thus authorizing the arbiter to assess related damages.
  • The Plaintiff maintained that the delay of over eight months was unreasonable and that they were entitled to damages for losses sustained due to late possession.

Respondent's Arguments

  • The Defendant contended that the contract expressly reserved their right to fix the time of entry, and thus no obligation existed to give immediate possession upon acceptance of the tender or contract.
  • They argued that the arbitration clause did not empower the arbiter to assess damages except in cases of work stoppage due to legal proceedings by third parties, which did not apply here.
  • The Defendant maintained that the statutory proceedings to obtain possession were not "legal proceedings" within the meaning of the arbitration clause.
  • They asserted that the Plaintiff's claim for damages was irrelevant as no special damage or unfair conduct causing delay was properly averred.
  • The Defendant argued that if the Plaintiff disagreed with the timing of entry, their remedy was to decline to proceed with the contract, not to claim damages.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Shotts Iron Company v. Dempster (October 27, 1891, 29 S.L.R. 40) Effect of arbitration clauses and the scope of an arbiter's jurisdiction regarding contract interpretation and damage assessment. Referenced by the Plaintiff to support that questions as to the true meaning of the contract fall within the arbiter's jurisdiction, even if damages are not assessable by the arbiter.
Caledonian Railway Company v. Gilmour (December 16, 1892, 30 SLR 172) Interpretation of arbitration clauses according to their terms and parties' intentions. Used to argue that the Court must give effect to the arbitration clause as written, including reference of contract construction disputes to the arbiter.
M'Alpine v. Lanarkshire and Ayrshire Railway Company (November 26, 1889, 17 R. 113) Limits on an arbiter's power to assess damages absent express authority in the contract. Applied to hold that the arbiter has no jurisdiction to assess damages unless expressly empowered.

Court's Reasoning and Analysis

The Court began by acknowledging that the arbitration clause expressly empowered the arbiter to assess damages only in the event of the works being stopped by legal proceedings initiated by third parties, a situation not present here. The Plaintiff's claim for damages due to delayed possession was not covered by this express power.

The Court found that the contract clearly reserved to the Defendant the right to appoint the time for the Plaintiff's entry onto the land. This reservation was necessary because the Defendant itself did not possess the land when the contract was signed and had to obtain possession through statutory means.

The Plaintiff's averments did not allege any unfairness, neglect, or bad faith by the Defendant in causing the delay. The mere fact of delay, without relevant allegations of improper conduct, was insufficient to sustain a claim for damages.

The Court held that the arbitration clause did not confer jurisdiction on the arbiter to assess damages in this case, and the question of damages was for the Court to decide if properly pleaded. However, the Plaintiff's pleadings were found irrelevant and insufficient to support the damages claim.

Regarding the argument that the question of the contract's true meaning should be referred to the arbiter, the Court reasoned that the arbitration clause's reference to disputes about the contract's meaning must be read in context. It applies only to disputes arising under the contract matters that are referred to arbitration, not to all possible disputes or to claims for damages outside the arbiter's jurisdiction.

The Court considered it anomalous to require the Court to remit to an engineer (arbiter) questions of law regarding contract construction when the Court alone has jurisdiction to interpret contracts.

Lord President expressed a differing view that the dispute as to the contract's meaning could fall within the arbitration clause, but since the claim was bad in law, the difference was academic for the parties' interests.

Holding and Implications

The Court DISMISSED the Plaintiff's claim for damages arising from delayed possession of the land. It held that:

  • The arbitration clause did not empower the arbiter to assess damages in the circumstances of this case.
  • The Defendant had the contractual right to fix the time for entry, and no relevant averments established breach of any duty to give possession within a reasonable time.
  • The Plaintiff's claim for damages was irrelevant and unsupported by the pleadings.
  • The Court was not required to remit the question of contract construction to the arbiter for decision.

The direct effect is that the Plaintiff's damages claim was rejected, and the Defendant was absolved from the claim. No new precedent was established beyond reaffirming the limits of arbitration clauses and the Court's role in contract interpretation and damage claims.